    ORDER OF THE BOARD (by T.E. Johnson):
     
    On May 1, 2003, at the parties’ request, the Board extended until July 17, 2003, the time
    period for Thompson Service to appeal a March 14, 2003 determination of the Illinois
    Environmental Protection Agency (Agency).
    See
    415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code
    101.300(b), 105.402, 105.406. At issue is the Agency’s approval of the site classification
    completion report and amended site classification work plan budget, with modifications,
    regarding Thompson Service’s underground storage tank site at 601 East Locust, Bloomington,
    McLean County. Because petitioner failed to timely file an appeal, the Board dismisses this case
    and closes the docket.
     
    IT IS SO ORDERED.
     
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
    adopted the above order on July 24, 2003, by a vote of 6-0.
     
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board

    Back to top