ILLINOIS POLLUTION CONTROL BOARD
    June 5. 2003
     
    RANDALL INDUSTRIES,
     
    Petitioner,
     
    v.
     
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
     
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
     
     
    PCB 03-219
    (UST Appeal)
    (90-Day Extension)
     
    ORDER OF THE BOARD (by T.E. Johnson):
     
    On May 29, 2003, the parties timely filed a joint notice to extend the 35-day period
    within which Randall Industries may appeal a April 21, 2003 determination of the Illinois
    Environmental Protection Agency (Agency).
    See
    415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code
    105.402, 105.406. Because the postmark date of the joint request is within the time for filing, the
    joint request was timely filed. 35 Ill. Adm. Code 101.300(b)(2), 105.404. At issue is the
    Agency’s approval of the site classification work plan budget, with modifications, for Randall
    Industries’ leaking underground petroleum storage tank facility located at 741 South Route 83,
    Elmhurst, DuPage County. The Board extends the appeal period until August 25, 2003, as the
    parties request.
    See
    415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code 105.406. If Randall
    Industries fails to file an appeal on or before that date, the Board will dismiss this case and close
    the docket.
     
    IT IS SO ORDERED.
     
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
    adopted the above order on June 5, 2003, by a vote of 6-0.
     
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board
     

    Back to top