ILLINOIS POLLUTION CONTROL BOARD
May 15, 2003
WINSLOW BOCO,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 03-213
(UST Appeal)
(90-Day Extension)
ORDER OF THE BOARD (by T.E. Johnson):
On May 7, 2003, the parties timely filed a joint notice to extend the 35-day period within
which Winslow Boco may appeal a March 28, 2003 determination of the Illinois Environmental
Protection Agency (Agency).
See
415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code 105.402,
105.406. Because the postmark date of the joint request is within the time for filing, the joint
request was timely filed. 35 Ill. Adm. Code 101.300(b)(2), 105.404. At issue is the Agency’s
approval of the reimbursement of requested corrective action costs, with modifications, for
Winslow Boco’s leaking underground petroleum storage tank facility located at 204 Carver
Street, Winslow, Stephenson County. The Board extends the appeal period until August 1, 2003,
as the parties request.
See
415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code 105.406. If Winslow
Boco fails to file an appeal on or before that date, the Board will dismiss this case and close the
docket.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
adopted the above order on May 15, 2003, by a vote of 7-0.
Dorothy M. Gunn, Clerk