ILLINOIS POLLUTION CONTROL BOARD
March 2, 1972
NORTH SHORE SANITARY DISTRICT
#PCB71—343
v.
ENVIRONMENTAL PROTECTION AGENCY
MR. MURRAY H. CONZELMAN and MR. JOHN H. SLOAN appeared for the
NORTH SHORE SANITARY DISTRICT
MR. RICHARD COSBY
and MR. THOMAS W. SCHUENEMAN
appeared for the
ENVIRONMENTAL PROTECTION AGENCY
MR. RICHARD M. KATES appeared for the
LEAGUE OF WOMEN
VOTERS
MR.
THOMAS H. COMPERE and MR. BERLE
L. SCHWARTZ appeared for
the CITY OF HIGHLAND PARE
OPINION OF THE BOARD (BY MR. KISSEL):
On January 31, 1972, the Board entered its order in this case
after consideration of all of the evidence and arguments by the pa:
—
ties: The North Shore Sanitary District (“District”), the Agency nd
the League of Women Voters (“League”)
.
Although the order must,
of course, speak for itself, generally it granted the District a
variance to permit the connection of 1,000 living units (4,000 Pop
lation Equivalents) on certain conditions. On February 10, 1972, the
District filed a “Petition for Reconsideration and Rehearing” with
the Board in which it objected to the following paragraphs of the
January 31, 1972 order, and here seeks to have those orders modifI ~d.
2. “The District shall be permitted to add a total of 100)
living units or 4000 P.R. to the sewers tributary to the
Clavey and Waukegan plants.”
14. “The District shall install disinfection facilities ~:
the Water Street and Gillette Avenue Sewers. Within 45 days
of the entry of the order, the District shall present a time-
table for the installation of such facilities to the Agency an
the Board. The Agency shall formulate a written response to t
Board within 15 days of receipt of the District timetable. Tt
Board shall then issue an implementation schedule.”
Its objections to the quoted paragraphs were nuxnerous~
3
—
697
1. The District would not realize sufficient revenues from
the 1000 living units to finance the various interim
improvements required by the Board in previous orders,
including the January 31, 1972 order and particularly
the requirement for interim chlorination at the Water
Street and Gillette Avenue Bypasses;
2. The issuance of only 1000 permits precludes developers,
contractors and others engaged in the Lake County housing
industry from proceeding with concrete commitments for
construction in the upcoming years; and
3. The chlorination facilities required by the Board would
not insure the use of the beaches in 1972 and 1973.
The League filed a brief with the Board suggesting that the Board
grant the variance for 5000 units on condition that the District
expedite the construction of the Waukegan retention basin, and com-
plete it by June 1973. The League’sposition was that if the
retention basin would be completed by that date, or soon thereafter,
there would be no need to require the disinfection facilities
at the Water Street andGillette Avenue overflows. The Agency
recommended that the Board not grant the additional variance
requested by the District.
As a result of the District’s motion,
a public hearing was held before the entire Board on February 22,
1972 at the Board’s office in Chicago, Illinois. At that hearing,
the City of Highland Park sought leave to intervene in this case;
the City’s motion was objected to by each of the parties on the
ground of lack of proper notice. Opposing counsel were given five
days to respond to the City’s motion. The City remained, at the
hearing and was afforded an opportunity to present its position
for the record. After receipt
of the arguments of opposing counsel,
the Board agrees that the City of Highland Park
should be added
as a party to the case.
The Board has considered motions made by other parties in other
cases for reconsideration of the Board’s order against them. We have
consistently taken the position that we will not reconsider our
initial decision unless there is a significant change in the circum-
stances, or there is new evidence available after the hearing which was
not available at the time of the hearing. We think that both of those
circumstances exist in this case.
The
order of January 31, 1972 was predicated on the Board’s con-
clusion that granting of the variance under the conditions detailed
in this order would actually improve the quality of the water of Lake
Michigan, and that had the variance not have been granted, (and therefore
the conditions are met)
the
Lake wouI~Thave continued to show signs
of bacterial contamination near the beaches located within the District’s
bounds. One of the
most important conditions of the variance was,
therefore, “paragraph 14” which required disinfecting of Water
Street and GilletteAvenue bypasses by September of 1972. If met,
this would have meant that for part of the 1972 and all of the 1973
bathing season, the bacterial contamination from the overflows would
have been substantially
reduced and the beaches within the District
most likely would have been useable during those periods.
In its motion
3
—
698
;i r.o:o:
~.
i1e~
~:::~rictcb;e:;’.ed
to
caragi
oph t.4” on a number
(LO.
05. 7 OL j~15~
~dtLLVeS COOS
(.tsrnd
by rho
Board before
T:~cL .j~~nuaroI .;rcwr
.
arc: now favcyed by the District, was
~ooct. :~:~a
chlorine
r.Lor,
~.t rhf. Wabor Street and GIllette Avenue
~
~
we..~ crib:
I
r~e
i&;ent3cr~ 5asz~ at ~aukegan
plant
lb aro~ ~oi-aii~.
no ~hct at. couid handle the overflows,
and treat
r.enocs I.
t ‘sos ce~.met:
bc do. Tut based upon the evidence in the
•:n: ir~!-:rtI
he.ar:LrLu,
ahe lntLcr was not: a feasible alternative
at that tine
boc~~~cof abe tie t~rict’
:5 si stcro of
delay in completing not only
ci sf sts oro-~arts
,
but this r:o~uct
Jo particular.’
if the “reten—
son ~
:~ltcroatavc nod
been
the
one selected by
tao Board in its
iu:iny 31
order, disinfection of one cverfiows
would not have been
occvtded
untis ar least September,
1973
and perhaps later, knowinci
Lh.:: t:~s Cistrich
had
a nor
coano for I~1ay in completing its projects.
in thr’
hearing on abe
Motion for Reconsideration,
the District’s
en t:o ccu:piet on of
the
“rateotaon
casIo” pro300t
was strongly
Tue District: has
actually awarded the contracts for the retention
and
for th~:
sttendant
oumping facilities
since the original
bearing on the I.
~:
rariance no sr tion.
The contract provides for
c::’mpiatlon date ~or cii scsi:
faciiat~os of September 1, 1973, which
the Dastrict testified
at would reguire be met.
Further, it may also
be
possible to advance that completion date by declaring the retention
oasis
pro~ecb. at:
Waukecan
an ‘emergency project’, as t has done in other
other cases,
Since the installation
of the retention basin and the pump-
ing faciliti.’
basically determines whether or not Lake Michigan bathing
can occur
in
197:3, we believe that cause exists for the use of the
Distrtct’s
‘emergency” declaration
power. One
way
of
completing the
project earlier would be for the District to employ overtime whenever
that will speed up work.
Another way of speeding up would be the
leasing of
the
necessary pumps and using
them
before
tire
installation
of the permanent pumps. We will require, therefore, that the District
complete the retention
basin no later than Sept. 1, 19732 and
investigate
all means available to speed up this project,
including
the availability
of leased pumps, and toe use of overtime work, and
report to the Board and the other parties the results of its investigation,
the manner in which it intends to proceed, and the reasons therefor.
Even given the availability
of the retention basin and the atten-
dant facilities
by the end of the summer, 1973, the Board believes that
disinfection
of the Water Street and Gillette Avenue bypasses would
have been the most appropriate measure to be taken.
Unfortunately,
the evidence presented at the recent hearing indicated that disinfection
facilities
could not be installed
by September, 1972 as originally
forecast.
prospects are also dim for installation
by summer, 1973, the
next bathing season.
In order to install the disinfection
facilities
at the Water Street bypass, the District would have to acquire rights
from E.J.&F.. Railroad.
Under the Eminent Domain Act, this could
not be done without prior approval from the Illinois
Commerce Commission:
i-The original contemplated completion date was March, 1973, and
the contemplated date now ~s September 1, 1973.
2The League has asked us
to
recuirs: a completion date of June 1973.
hut based
upon the present record on do not know
if this car, be done,
we
agree with the League that all sccns an the tiOtrict’s
disposal should
be used
to speed
up the Project and ~: after .tnvestiqation the June
dote can be met, we will
require it.
3
—
699
cwo proceedings, one before the Commerce
Commission and
then a condemna-
tion suit, would most likely have to
occur
ti-ien before the District could
obtain the necessary right—of—way.
A seven-’rnonth construction
period
would then be pyramided on top of those hearing processes..
The water
Street project therefore appears to be effectively
stymied.
If
that is the case, then to chlorinate
at Gillette
Avenue will make
little
sense since with Water Street still untreated,
a large amount
of untreated sewage will still be cascading into Lake Michigan wheb
overflow conditions occur.
Therefore,
Paragraph 14 of the Board
order of January 31, 1972 will be rescinded;
instead,
the District
will be ordered to take the steps outlined above to advance the avail-
ability date for the Waukegan retention
basin, the pumping station, and
the interceptor
and relief sewer.
While Lake Michigan will suffer
for a few more months under this new Order, the people of the county will
not he required to waste their money on a useless,
and maybe, never
available project.
At the recent hearing,
the District also objected to the Board’s
limitation
of 1000 hookups (4000 P. E.) to the Clavey Road and Waukegan
Sewage Treatment plants. In support
of this contention, the District
indicated that
it would not receive sufficient revenues from the 1000
permits granted to finance the
improvements which the Board had ordered
because
the grant of only 1000 permits would preclude developers, con-
tractors and others in the housing and building industry from proceeding
with concrete conirnitmen~s for construction in 1973 and 1974. Though
the District’s
first argument has been somewhat obviated by the Board’s
rescission of its order directing that disinfection take place at the
bypasses (because the disinfection facilities involved a large part of
the cost)
,
the
second contention still remains a
matter for concern.
At the recent hearing, the District introduced new evidence regarding
the need for 5000 permits.
Allan Pickus, a Waukegan architect and
contractor, indicated that scheduling and financing of projects requires
that preparations
be made several years in advance. Thus, for the
lifting of this sewer ban to have any beneficial
economic effect,
the
District would require that a sufficiently
large number of
permits be
granted so that construction
can proceed at an appropriate
pace.
This is necessary because builders need
to obtain financing for the
total construction
project,
be it an apartment house, or private homes,
so that the costs common to the entire project, i.
e., roads, sewers,
etc. can be done at once and amortized over the entire project. Without
the firm commitment to connect the entire construction project, builders
could not risk the funds for the common costs. Pickus’ testimony was
corroborated by that of Thomas A. Rostron, President of the First Federal
Savings and Loan Association of Waukegan, who stressed that developers
must be assured that sewers will be available at the conclusion of a
project before they can commit capital toa building program. He
in-
dicated that no lending institution would make a mortgage commitment
unless there were written approval from the Board as to the availability
of sewer hookups. Based on this new evidence, the District shall have
the power to issue 5000 living unit (20,000 P.E.) permits for the
Waukegan and Clavey Road plants. Just because the Board authorizes
the issuance of 5000 permits does not mean that such connections will
occur within the next year; as Pickus indicated, actual connections
to the plants will most likely total
between 700 and 1000 the first
3—
700
year, with approximately 2000 occurring ih each subsequent year.
Of
prime consideration
in limiting the original grant to 1000 units was
the Board’s desire to maintain a continuing supervision over the Dis-
trict’s
expansion program.
Placing the limitation
at 1000 would force
the District to return to the Board at the end of that first year in
order to renew the variance; at such a time, the District
would have
to show substantial
compliance with the deadlines under their construc-
tion program.
Raising the level to 5000 does not preclude the maintenance
of such supervision, sinpe in order that advance
planning can take place
for construction year 1975,
the District will most likely have to
return to the Board in about a year for a renewal of its variance.
If the District is not
complying with our Order, or proves that it
has
not exercised all good faith in trying to comply, new variances should
not be granted in the future beyond those granted today. In addition,
through the District’s
monthly progress reports,
the Board and the
Agency will continue to be apprised of the District’s
activities.
It is important to note that the granting of a variance for 5000
living units is essentially
the same grant as previously made by the
Board on January 31. In the January 31 order, the Board
granted a variance for 1000 units for the next year,
recognizing that
if
the District met its schedule,
it
would receive per-
mission to connect additional living units in the next year, probably
2000 such units, and so on. With the present grant of 5000 units, the
testimony is that not more than 1000 units will be connected in the
first year anyway. What the Board is really doing is to give the
builders the wherewithal
to build the 1000 units this year.
Under
the January 31 order, the manner of apportioning the 1000 unit allotment
was left to the discretion of the District.
Since 5000 units will
ultimately be connected to the District system under this variance,
however, we must now take into account the relative capacities of the
Clavey and Waukegan plants.
Accordingly, the District shall apportion
the loadings under this variance in the approximate one—third to Clavey,
two-thirds to Waukegan ratio proposed by
the District in its original
variance request in this case.
One other point must be mentioned
---
the District’s
financial
problems. Testimony at the
hearing established that the value of
the
appraised real estate in the District had increased by 150 million
dollars
since the voters in the District had passed the original 36 million dollar
bond issue in 1968. This increase
in assessed valuation makes 7.5
million dollars available to the District for its programs.
Such funds
are available within the five percent bonding limitation imposed on the
District under Sec. 285,. Ch. 42,
Ill. Rev. Stat. (1971)
.
At present,
the District is committed to a large—scale construction and expansion
program. Those
facilities are being constructed in order to abate pollu-
tion. (See Opinion, PCB7O—7, 12, 13 and 14, March 31, 1971)
.
The
facilities ordered in this variance case are also directed to abating
pollution (See opinion PCB71—343, January 31, 1972).
To comply with
such an order, the District is authorized by Section 46 of the Environ-
3
—
701
mental Protection Act to issue general obligation
or revenue bonds, if
necessary,
without referendum.
No specific order to issue bonds is
necessary; we leave the question of how to raise money to the District.
but the money must be raised.
See Ruth v. Aurora Sanitary District,
17 Ill.
2d 11, 158 N.E. 2d 601 (1959).
The parties
entered :into a stipulation
regarding certain matters
and •the League has asked that the Board make the stipulation
part
of the Board’s order.
The stipulation, inter alia, would provide
for operation of interim
chlorination facilities at the North
Chicago plant during the 1972 swirnminq season, for ample notice in
the District and to
contractors regarding the district’s
bidding
processes,
and
for the adoption of a fine schedule by the
District.
Such steps, we believe will assure better operation
and a higher quality effluent,
as well as possibly advancing the
completion date for the District’s
expansion program.
The stipulation
shall
be incorporated into the Board Order.
-ORDER-
Upon examination of the record, the Order of the Board of
January 31, 1972 in the ‘above—entitled case, PCB 71—343, granting the
North Shore Sanitary District a variance from Paragraph 7 of the
Order of the Board in the case of the League of Women Voters, et al
v. North Shore Sanitary District, PCB 70-7, 12, 13 and 14 is hereby
modified as follows:
1. Paragraph 2 of the Board Order of January 31, 1972 is
hereby repealed in full and replaced as follows:
2. The District shall be permitted to add a total of
5000 living units or 20,000 P.E. to the sewers
tributary to the Clavey and Waukegan plants.
2. Paragraph 4 of the Board Order of January 31, 1972 is
hereby repealed in full and replaced as follows:
4. The District shall apportion the allotment under the
variance between the subject plants in approximate
ratio of one—third of the new connections to Clavey,
the remainder to Waukegan. Such apportioni~ent shall
also be subject to the conditions in Paragraph 5 below.
3. Paragraph 14 of the Board Order of January 31, 1972 is
hereby repealed in full.
4. The following paragraphs are hereby added to the Board Order
of January 31, 1972:
21. The District shall have the retention basin at the
Waukegan plant (P3B)
,
the pumping station (P3F), and
the interceptor and relief sewers (S6A) (hereinafter
called “retention basin”) tributary
to the basin in
operation as soon as possible and no later than Septem-
3
—
702
her 1, 1973.
The District
shalL employ all means avail-
able to advance the date of operation of the retention
basin.
The District shall investigate
all available
means to advance the date of operation of the retention
basin, including the use of its emergency powers, over-
time
and leased pumps. Within
60
days of the entry of
this Order, the District shall begin reporting in its
monthly progress reports to the Board,the Agency and
the
other parties in this case, the results of its
investigations,
the steps it has taken to
advance
the
operation date, the manner in which it intends to
proceed, and the reasons therefor.
Such reporting
shall be included within each monthly progress report
until the date of completion of the retention basin
report.
22,
The District
shall abate its discharge of untreated or
inadequately
treated sewage and its violations
of the
Environmental Protection Act and of regulations
thereunder,
in accordance with this Order and the Board Orders of
January 31,. 1972, June 23, 1971 and March 31, 1971.
23.
Within 90 days of the entry of this Order, the District
shall submit to the Agency and the Board a plan assuring
financing of the program herein and heretofore
approved,
together with a study by bond counsel discussing
the various
financing alternatives
available.
5. The following stipulation
is hereby incorporated, into the Board
Order of January 31, 1972:
24.
Within sixty (60) days from the date of this Stipulation,
the North Shore Sanitary District will adopt a fine schedule
to a certain Ordinance relating to sewers and sewer
systems as amended.
25.
That the North Shore Sanitary District will take whatever
legal steps
are necessary in the matter of illegal
connections to its systems and facilities.
26.
That the North Shore Sanitary District
will study the
toxicity
of polymers it plans to use by making a study
of the literature
and report its findings to the Illinois
Pollution Control Board.
27. That in connection with the interim chlorination
facilities
at its North Chicago Plant, the North Shore Sanitary
District will install and operate such facilities
for
the swimming season of 1972.
28. That the North Shore Sanitary District states that it
;
advertises for bids on construction contracts in the Waukegan
Nev~’s-Sun and notifies the
Dodge Reports. That in addition
it furnishes notices to contractors.
3
‘03
29. That a pilot study of ozone may be done at a plant
approved by the North Shore Sanitary District
if
done
by the Illinois
Institute
for Environmental Quality or
other governmental agency so long as such study does not
interfere
with construction.
30.
That the North Shore Sanitary District will file its
impact study of a sludge disposal site in Newport Township,
Lake County, Illinois
with the Federal Environmental
Protection
Agency as soon as a permit is issued by the
Illinois
Environmental
Protection Agency.
6. All other conditions
of the variance granted on January 31,
1972 in this cause shall remain in full force and effect.
I, Christan Moffett, Clerk of the Illinois Pollutoin Cont~1. Board,
certify that the above Opinion & Order was adopted this day of March
1972, by a vote of
9-c
~‘t4;L&v~~,
I
3
—
704
ILLINOIS POLLUTION CONTROL BOARD
March 2, 1972
NORTH SHORE SANITARY DISTRICT
v.
)
PCB 71—343
ENVIRONMENTAL PROTECTION AGENCY
Concurring Opinion by Jacob D. Dumelle
While I concur in
the
Board’s decision to grant 5,000 connec-
tions as it did this date I do not agree with all the language of
the March 2, 1972 opinion.
In my dissent filed February 17, 1972 to the original January
31, 1972 Board order granting only 1,000 connections I fully explored
my reasons. Those reasons still hold and I shall not repeat them
here.
I do not feel that the “new evidence” mentioned in the Bo~d
opinion (p.4) was needed or necessary. I think that our exten~ive
sewer ban hearings plus the instant case proceedings fully developed
the material for the conclusions reached.
The
distribution of the connections between the Waukegan and
Clavey plants in the 2:1 ratio is not one I would have made. The
Clavey plant’s effluent has been of such good quality
that I
would
have reversed the ratio or made an unlimited grant at Clavey subject
to the effluent stanc ~rd for secondary plants not being exceeded.
~/
r\~/
If.,!
/
/
\/~//~~
th~-b2~_
/ ____________________________________________
./
,Jacob D. Dumelle
/
/Board Member
I, Christan~~.Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Concurring Opinion was filed on the
.~2//~dayof March, 1972.
Christan L. Moffe’~t~4Clerk
Illinois Pollution control Board
3
—
705