ILLINOIS POLLUTION CONTROL BOARD
May 1, 2003
HOWARD WARSAW,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 03-201
(UST Appeal)
(90-Day Extension)
ORDER OF THE BOARD (by T.E. Johnson):
On April 25, 2003, the parties timely filed a joint notice to extend the 35-day period
within which Howard Warsaw may appeal a March 12, 2003 determination of the Illinois
Environmental Protection Agency (Agency).
See
415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code
105.402, 105.406. Because the postmark date of the joint request is within the time for filing, the
joint request was timely filed. 35 Ill. Adm. Code 101.300(b)(2), 105.404. At issue is the
Agency’s approval of the high priority corrective action plan budget, with modifications, for
Howard Warsaw’s leaking underground petroleum storage tank facility located at Warsaw
Itco/Route 122, Minier, Tazewell County. The Board extends the appeal period until July 15,
2003, as the parties request.
See
415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code 105.406. If
Howard Warsaw fails to file an appeal on or before that date, the Board will dismiss this case
and close the docket.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
adopted the above order on May 1, 2003, by a vote of 7-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board