ILLINOIS POLLUTION CONTROL BOARD
    April 3, 2003
     
    MINERAL SOLUTIONS, INC.,
     
    Petitioner,
     
    v.
     
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
     
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
     
     
     
     
    PCB 03-39
    (Permit Appeal – Land)
     
     
     
    ORDER OF THE BOARD (by G.T. Girard):
     
    On March 6, 2003, the Illinois Environmental Protection Agency (Agency) filed a motion
    (Mot.) asking the Board to reconsider a January 23, 2003 opinion and order striking a contested
    condition from a permit. On March 20, 2003, Mineral Solutions, Inc. (Mineral Solutions) filed a
    response to the motion (Resp.). For the reasons discussed below, the Board denies the motion to
    reconsider.
     
    The Board will briefly summarize the arguments put forth by the Agency and Mineral
    Solutions. The Board will then delineate the standard used by the Board in ruling on motions to
    reconsider and the Board’s reasons for denial.
     
    MOTION FOR RECONSIDERATION
     
    The Agency asks the Board to reconsider because the Board “erred in failing to
    acknowledge, consider and discuss all arguments raised” by the Agency. Mot. at 2. The Agency
    maintains that the Board “neglected to consider an argument in” the Agency’s post-hearing
    response brief.
    Id
    . Specifically, the Agency maintains that the Board did not discuss the
    Agency’s argument which addressed the possibility that the Board might find that the fly ash
    received at the Indian Creek Landfill was not a waste.
    Id
    . The Agency’s argument was that if
    the Board found that the fly ash received in 1996 was not waste then Mineral Solutions was an
    on-site manufacturing process generating waste. Mot. at 3. The Agency asserts that such
    activity is exempt from the permitting process under Section 21(d) of the Environmental
    Protection Act (Act) (415 ILCS 5/21(d) (2002)).
    Id
    .
     
    The Agency argues that since the Board’s finding was that the material accepted in 1996
    was not waste, failing to address the Agency’s argument “was tantamount to conceding the
    appeal to Mineral Solutions without having heard” the Agency’s argument on that key point.
    Mot at 2. The Agency argues that if the case is appealed to the appellate court it would be
    advantageous to all parties if a “complete discussion and analysis of the parties’ arguments were
    present for review.” Mot. at 4. The Agency submits that failure to “consider” the Agency’s
    argument was error. Therefore the Agency argues that the Board should reconsider the January

     
    2
    23, 2003 opinion and order to either reverse the Board’s decision or at a minimum discuss the
    Agency’s argument.
    Id
    .
     
    RESPONSE TO THE MOTION TO RECONSIDER
     
    Mineral Solutions argues that the Agency’s motion is based on a “mistaken belief” that
    the Board failed to consider an Agency argument because the argument was not mentioned in the
    Board’s opinion. Resp. at 1. Mineral Solutions states that this “fallacy is made even the more
    egregious when one considers that the location of [the argument on] this allegedly ‘key point’.”
    Id
    . Mineral Solutions states that the “key point” was “buried” in the middle of arguments in the
    response brief and was not raised in the letter or the Agency’s original brief.
    Id
    . Mineral
    Solutions asserts that the argument “should have remained buried since it is inconsistent with
    positions already taken” by the Agency in this “permit review and in previous permit reviews
    regarding this facility.”
    Id
    .
     
    Mineral Solutions also argues that the Board did not “neglect any duty” in issuing the
    opinion. Resp. at 2. Mineral Solutions asserts that the Agency has not identified any legal
    obligation or requirement that the Board failed to apply. Conversely, Mineral Solutions
    maintains that the Agency did neglect to act in that the Agency’s failure to include in the letter
    the “perceived applicability of Section 21(d) of the Act” was a failure to meet a legal
    requirement. Resp. at 2. Mineral Solutions argues that the Board must confine the Board’s
    considerations to the decision of the Agency (Resp. at 2, citing Illinois Environmental Protection
    Agency v. Illinois Pollution Control Board 86 Ill. 2d 390, 405 (1981)) and the Agency’s failure
    to include Section 21(d) of the Act as a reason for the condition on the permit means the Board
    need not consider the argument. Resp. at 2-3.
     
    DISCUSSION
     
    In ruling on a motion for reconsideration, the Board will consider factors including new
    evidence or a change in the law, to conclude that the Board’s decision was in error. 35 Ill. Adm.
    Code 101.902. In Citizens Against Regional Landfill v. County Board of Whiteside, PCB 93-
    156 (Mar. 11, 1993), we observed that "the intended purpose of a motion for reconsideration is to
    bring to the court's attention newly discovered evidence which was not available at the time of
    hearing, changes in the law or errors in the court's previous application of the existing law.”
    Korogluyan v. Chicago Title & Trust Co., 213 Ill. App. 3d 622, 627, 572 N.E.2d 1154, 1158 (1st
    Dist. 1992). For the following reasons, the Board finds that the Agency’s motion to reconsider
    presents the Board with no new evidence, change in the law, or other reason to conclude that the
    Board’s January 23, 2003 decision was in error. Therefore the motion to reconsider is denied.
     
    The law is clear that the Agency’s letter frames the issues on appeal. ESG Watts, Inc. v.
    PCB, 286 Ill. App. 3d 325, 676 N.E.2d 299 (3rd Dist. 1997). In this case the Agency issued a
    permit that was conditioned on Mineral Solutions receiving siting approval and a new operating
    permit because “the last time Indian Creek Landfill ‘accepted waste disposal’ was more than five
    years prior” to the receipt of the application for temporary suspension of waste acceptance. R. at
    0003. This was the only condition challenged and the issue as framed by the Agency’s letter was
    what constitutes “accepted waste disposal” under the facts of this case. The Board’s January 23,

     
    3
    2003 opinion analyzed the arguments regarding what constitutes “accepted waste disposal” and
    found that the Agency’s condition was not necessary to meet the purposes of the Act.
     
    The Board did review, but did not and will not discuss, the Agency’s hypothetical
    argument that is unrelated to the issue as framed by the Agency’s letter. The law requires the
    Board to review the Agency’s decision to determine if conditions imposed by the Agency are
    necessary to meet the purposes of the Act.
    See
    415 ILCS 5/40 (a)(1) (2002); 35 Ill. Adm. Code
    Section 105.204(a); Browning-Ferris Industries of Illinois, Inc. v. PCB, 179 Ill. App. 3d 598, 534
    N.E. 2d 616, (2nd Dist. 1989) and John Sexton Contractors Company v. Illinois (Sexton), PCB
    88-139 (Feb. 23, 1989). Further, the Act requires that the Board make final decisions on permit
    appeals in 120 days (
    See
    415 ILCS 5/40(a)(3) (2002)) and at most that final decision need only
    be a written decision stating the facts and reasons leading to the decision (415 ILCS 5/33(a)
    (2002) and 5 ILCS 100/10-50(a) (2002)). Neither the Act nor case law requires that the Board
    discuss
    every
    argument raised before the Board and the Board sees no reason here to do so.
     
    CONCLUSION
     
    The Board finds that the Agency’s motion to reconsider presents the Board with no new
    evidence, change in the law, or other reason to conclude that the Board’s January 23, 2003
    decision was in error. Therefore the motion to reconsider is denied.
     
    IT IS SO ORDERED.
     
    Section 41(a) of the Environmental Protection Act provides that final Board orders may
    be appealed directly to the Illinois Appellate Court within 35 days after the Board serves the
    order. 415 ILCS 5/31(a) (2002));
    see also
    35 Ill. Adm. Code 101.300(d)(2), 101.906, 102.706.
    Illinois Supreme Court Rule 335 establishes filing requirements that apply when the Illinois
    Appellate Court, by statute, directly reviews administrative orders. 172 Ill. 2d R. 335. The
    Board’s procedural rules provide that motions for the Board to reconsider or modify its final
    orders may be filed with the Board within 35 days after the order is received. 35 Ill. Adm. Code
    101.520;
    see also
    35 Ill. Adm. Code 101.902, 102.700, 102.702.
     
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
    adopted the above order on April 3, 2003, by a vote of 7-0.
     
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board
     
     

    Back to top