ILLINOIS POLLUTION CONTROL BOARD
March
2,
1972
VILLAGE OF LENA
V.
)
PCB 71—384
ENVIRONMENTAL PROTECTION AGENCY
OPINION OF THE BOARD
(by Richard
J.
Kissel):
The Village of Lena filed a petition
for variance with
the
Board asking for an extension of time within which to design and
complete
its waste treatment
facilities.
The effluent from the Village’s waste treatment plant is
dischargthI into
a tributary of Yellow Creek, which is itself
tributary
to the Pecatonica River.
While
the effluent flow rate
from the Village’s waste treatment plant
is only 130,000 gallons
per day,
the flow of the tributary
to which it discharges
is
so
small that the dilution ratio is less than
1 to
1.
Since the
tributary
is
an intrastate stream,
SWB-l4 applies,
and it requires
that in situations where
the dilution is less than
1 to
1,
the
effluent must average
4 mg/l
.BOD and
5 mg/l suspended solids by
July,
1972.
Presently,
the Village’s waste treatment plant, which
is
a trickling filter plant, can accomodate
all of the influent
(except the digester which is 100
overloaded)
and
it produces
an effluent of
35 mg/l
BOD and
25 ing/l suspended solids.
Recognizing that it had to build new facilities providing
for tertiary treatment by July
31,
1972,
the following sequence of
events took place:
A.
The Village of Lena entered into an engineering agree-
ment with their consulting engineer April
27,
1970,
to prepare
plans
and specifications for tertiary treatment facilities to
bring their effluent in line with State criteria.
B.
Additional ground was necessary
to provide tertiary
treatment facilities, but final purchase
and location could not
be made until the State Highway Department completed their State
Route
20 location hearings,
as
the proposed route was immediately
south
of the existing treatment facility.
On January
25,
1971,
a letter was sent to the Environmental Protection Agency informing
them that our plans were held up pending final location of the
proposed Route
20.
3
—
709
C.
In February of 1971 the State Highway Department
finalized their State
Route
20
location, and the Village of Lena
then purchased
six acres of additional land
for tertiary treat-
ment facilities.
D.
On April
27,
1971, preliminary plans were forwarded
to the Environmental Protection Agency office for review and
comments before final plans and specifications were completed.
These preliminary plans consisted of tertiary
lagoons.
E.
On July,
1971
WPC
Technical Policy 20—24
(Waste Treat-
ment Plant Design Criteria) was revised to require mechanical
settling and chemical precipitation of all lagoon effluents.
F.
On September
10,
1971,
a letter was sent to
the Environ-
mental Protection Agency office asking about the status of our pre-
liminary plan
review.
C.
On Septembe~r23,
1971,
the Village received a letter from
the Environmental Protection Agency office stating the review of cur
preliminary plans had been completed,
and
the Village of Lena
would have
to comply with the revised criteria and furnish mechanical
settling and chemical precipitation for the lagoon effluent.
H.
In the interim between plan submission on April
27,
1971,
and completed plan review on
Septenther 23,
1971, the Village
of Lena had been studying
the Johns-Manville moving bed filter
as
an alternate solution for the Village of Lena tertiary treatment
process.
The moving bed filter
is
a continuous filtration process
in which
the wastewater moves countercurrent to the filter medium.
The system is not shut down
for backwash since the spent sand is
removed and washed in
a separate unit operation and then returned
to the filter bed.
Village Board members on two separate occasions
visited
a moving bed filter installation at Manville, New Jersey.
I.
The revised criteria change and the technological ad-
vances in the moving bed filtration process have caused the Village
of Lena to abandon tertiary lagoons and approve the moving bed
filter process for tertiary treatment.
J.
The Village of Lena on December
1,
1971, received a
firm proposal for supplying the hardware
for
a moving bed filter
from Peabody Welles, which has
a license to sell from Johns-Manville.
They have also guaranteed to meet the EPA criteria of
4 mg/i
and
5~rng/1of
5
day BOD and suspended solids respectively.
The proposal
guarantees delivery of the moving bed filter hardware
such that the
Village of Lena waste treatment effluent will meet the Water Quality
Criteria Standards by December
1,
1972.
3— 710
It is obvious from the record that the Village has made
a
good
faith effort to meet the July
31, 1972 deadline,
It was
slowed both by the
lack of decision on
the part of the State
High-
way Department on the location of Route
20 and by the Agency’s
new technical release calling for algae removal among other things.
We
feel that the Village was justified in its actions, and lacking
any proof of harm to the stream, we will grant the variance.
U
An important reason why
the variance is granted is that the Village
is
only asking for a four—month extension,
As we said in the
Marion case,
“Without condoning past lapses,
we
think it appro—
~ii~e
to encourage those who have fallen behind to make every
effort
to make up for it.
We shall therefore look with some in-
dulgence upon local governments that file programs in the immediate
future that will result in compliance within a short time after
the ultimate deadline.”
EPA
V.
City of Marion, PCB 71-25, opinion
dated October 28, 1971.
The Agency in
its
recommendation agreed
that the variance should be granted,
and therefore the
new time
schedule of the Village will be as follows:
1.
Completion of plans and specifications and submission
to the Agency by March 15,
1972,
2.
Award of construction contracts by July
1,
1972.
3.
Completion of project by December 1,
1972.
One other issue must be dealt with.
In its petition, the
Village requests that the Board “order the Village of Lena,
Illinois,
to issue General Obligation Bonds to finance the required waste
treatment facilities” as provided for in Section
46 of the Act.
The Agency recommends that before the Board enter any such “order
to issue bonds”
it hold a public hearing on the necessity for the
bonds and require as
a preliminary condition that the citizens
defeat a referendum.
Unfortunately, neither the Village or the
Agency understood
thi,s
procedural position of the Board as set
forth in Section
46 of the Act.
Essentially, Section
46 of the
Act does
not give
the power to the Board tb’say “issue bqnds”,
but,
does give the Board the power to say “abate pollution”.
Once
having said this,
the municipality must take all steps ordered
by the Board and if necessary, issue non—referendum bonds,
In
11
The petition alleged that the stream is not used for
recreational purposes until Freeport, Illinois, which is eighteen
miles away.
3
*
711
other words, under Section
46
the Board does not tell the city
how
to raise money, but Section 46 does remove the
lack of money
E~a municipality as an excuse.
As we said in the Marion case:
we leave the question of how
to raise money
to the City, but the money must be raised!
See Ruth
v.
Aurora Sanitary District,
17
Ill.
2d
11,
158 N.E.
2d 601
(1959).”
Environmental Protection Agency v.
City of Marion, PCB 71-25, opinion dated October
28,
1971.
Thus,
the issue of whether the Village must issue non-referendum
bonds
is out of our hands.
The Village has been told and by
this
order
is being told,
that it must abate pollution.
With the
relief provided by Section 46,
lack of money is no excuse.
We
feel,
therefore,
that no benefit would be served by
a Board hear-
ing,
since the only issue to be decided would be whether pollution
should be
abated.
We can decide that without
a hearing.
We will
require that the Villag4
tell us how they are going to finance
this project.
This type of report was also made mandatory
in the
Marion case,
supra.
This opinion constitutes
the Board’s findings
of fact and
conclusions of law.
ORDER
1.
The petition of
the Village of Lena
for
a variance
extending the date
for compliance with the treatment and effluent
standards
of SWB-14 until December
1,
1972
is hereby granted on
condition that
the provisions of this Order
are met.
2.
The Village
of Lena shall abate its discharge of
inadequately treated sewage
in accordance with its revised program
with
the following schedule:
a)
Completion of plans and
specifications and sub-
mission to Agency
:
By March
15,
1972
b)
Award of construction
contracts
:
By July
1,
1972
c)
Completion of project
as outlined by
the
Village
:
By December
1,
1972
3
—
712
3.
Within forty—five
(45)
days of the receipt of this
Order,
the Village shall submit to the Board and the Agency a
plan assuring financing of the program herein approved,
together
with
a study by bond counsel discussing
the various financing alter-
natives available.
I, Christan
L. Moffett, Clerk of the Pollution Control Board,
cer~fy that
the Board adopted the
above Opinion and Order this
~ day of March, 1972 by
a vote of
9~’O
~
4’l’
.~
~-
3
—
713