ILLINOIS POLLUTION CONTROL BOARD
    March
    2,
    1972
    VILLAGE OF LENA
    V.
    )
    PCB 71—384
    ENVIRONMENTAL PROTECTION AGENCY
    OPINION OF THE BOARD
    (by Richard
    J.
    Kissel):
    The Village of Lena filed a petition
    for variance with
    the
    Board asking for an extension of time within which to design and
    complete
    its waste treatment
    facilities.
    The effluent from the Village’s waste treatment plant is
    dischargthI into
    a tributary of Yellow Creek, which is itself
    tributary
    to the Pecatonica River.
    While
    the effluent flow rate
    from the Village’s waste treatment plant
    is only 130,000 gallons
    per day,
    the flow of the tributary
    to which it discharges
    is
    so
    small that the dilution ratio is less than
    1 to
    1.
    Since the
    tributary
    is
    an intrastate stream,
    SWB-l4 applies,
    and it requires
    that in situations where
    the dilution is less than
    1 to
    1,
    the
    effluent must average
    4 mg/l
    .BOD and
    5 mg/l suspended solids by
    July,
    1972.
    Presently,
    the Village’s waste treatment plant, which
    is
    a trickling filter plant, can accomodate
    all of the influent
    (except the digester which is 100
    overloaded)
    and
    it produces
    an effluent of
    35 mg/l
    BOD and
    25 ing/l suspended solids.
    Recognizing that it had to build new facilities providing
    for tertiary treatment by July
    31,
    1972,
    the following sequence of
    events took place:
    A.
    The Village of Lena entered into an engineering agree-
    ment with their consulting engineer April
    27,
    1970,
    to prepare
    plans
    and specifications for tertiary treatment facilities to
    bring their effluent in line with State criteria.
    B.
    Additional ground was necessary
    to provide tertiary
    treatment facilities, but final purchase
    and location could not
    be made until the State Highway Department completed their State
    Route
    20 location hearings,
    as
    the proposed route was immediately
    south
    of the existing treatment facility.
    On January
    25,
    1971,
    a letter was sent to the Environmental Protection Agency informing
    them that our plans were held up pending final location of the
    proposed Route
    20.
    3
    709

    C.
    In February of 1971 the State Highway Department
    finalized their State
    Route
    20
    location, and the Village of Lena
    then purchased
    six acres of additional land
    for tertiary treat-
    ment facilities.
    D.
    On April
    27,
    1971, preliminary plans were forwarded
    to the Environmental Protection Agency office for review and
    comments before final plans and specifications were completed.
    These preliminary plans consisted of tertiary
    lagoons.
    E.
    On July,
    1971
    WPC
    Technical Policy 20—24
    (Waste Treat-
    ment Plant Design Criteria) was revised to require mechanical
    settling and chemical precipitation of all lagoon effluents.
    F.
    On September
    10,
    1971,
    a letter was sent to
    the Environ-
    mental Protection Agency office asking about the status of our pre-
    liminary plan
    review.
    C.
    On Septembe~r23,
    1971,
    the Village received a letter from
    the Environmental Protection Agency office stating the review of cur
    preliminary plans had been completed,
    and
    the Village of Lena
    would have
    to comply with the revised criteria and furnish mechanical
    settling and chemical precipitation for the lagoon effluent.
    H.
    In the interim between plan submission on April
    27,
    1971,
    and completed plan review on
    Septenther 23,
    1971, the Village
    of Lena had been studying
    the Johns-Manville moving bed filter
    as
    an alternate solution for the Village of Lena tertiary treatment
    process.
    The moving bed filter
    is
    a continuous filtration process
    in which
    the wastewater moves countercurrent to the filter medium.
    The system is not shut down
    for backwash since the spent sand is
    removed and washed in
    a separate unit operation and then returned
    to the filter bed.
    Village Board members on two separate occasions
    visited
    a moving bed filter installation at Manville, New Jersey.
    I.
    The revised criteria change and the technological ad-
    vances in the moving bed filtration process have caused the Village
    of Lena to abandon tertiary lagoons and approve the moving bed
    filter process for tertiary treatment.
    J.
    The Village of Lena on December
    1,
    1971, received a
    firm proposal for supplying the hardware
    for
    a moving bed filter
    from Peabody Welles, which has
    a license to sell from Johns-Manville.
    They have also guaranteed to meet the EPA criteria of
    4 mg/i
    and
    5~rng/1of
    5
    day BOD and suspended solids respectively.
    The proposal
    guarantees delivery of the moving bed filter hardware
    such that the
    Village of Lena waste treatment effluent will meet the Water Quality
    Criteria Standards by December
    1,
    1972.
    3— 710

    It is obvious from the record that the Village has made
    a
    good
    faith effort to meet the July
    31, 1972 deadline,
    It was
    slowed both by the
    lack of decision on
    the part of the State
    High-
    way Department on the location of Route
    20 and by the Agency’s
    new technical release calling for algae removal among other things.
    We
    feel that the Village was justified in its actions, and lacking
    any proof of harm to the stream, we will grant the variance.
    U
    An important reason why
    the variance is granted is that the Village
    is
    only asking for a four—month extension,
    As we said in the
    Marion case,
    “Without condoning past lapses,
    we
    think it appro—
    ~ii~e
    to encourage those who have fallen behind to make every
    effort
    to make up for it.
    We shall therefore look with some in-
    dulgence upon local governments that file programs in the immediate
    future that will result in compliance within a short time after
    the ultimate deadline.”
    EPA
    V.
    City of Marion, PCB 71-25, opinion
    dated October 28, 1971.
    The Agency in
    its
    recommendation agreed
    that the variance should be granted,
    and therefore the
    new time
    schedule of the Village will be as follows:
    1.
    Completion of plans and specifications and submission
    to the Agency by March 15,
    1972,
    2.
    Award of construction contracts by July
    1,
    1972.
    3.
    Completion of project by December 1,
    1972.
    One other issue must be dealt with.
    In its petition, the
    Village requests that the Board “order the Village of Lena,
    Illinois,
    to issue General Obligation Bonds to finance the required waste
    treatment facilities” as provided for in Section
    46 of the Act.
    The Agency recommends that before the Board enter any such “order
    to issue bonds”
    it hold a public hearing on the necessity for the
    bonds and require as
    a preliminary condition that the citizens
    defeat a referendum.
    Unfortunately, neither the Village or the
    Agency understood
    thi,s
    procedural position of the Board as set
    forth in Section
    46 of the Act.
    Essentially, Section
    46 of the
    Act does
    not give
    the power to the Board tb’say “issue bqnds”,
    but,
    does give the Board the power to say “abate pollution”.
    Once
    having said this,
    the municipality must take all steps ordered
    by the Board and if necessary, issue non—referendum bonds,
    In
    11
    The petition alleged that the stream is not used for
    recreational purposes until Freeport, Illinois, which is eighteen
    miles away.
    3
    *
    711

    other words, under Section
    46
    the Board does not tell the city
    how
    to raise money, but Section 46 does remove the
    lack of money
    E~a municipality as an excuse.
    As we said in the Marion case:
    we leave the question of how
    to raise money
    to the City, but the money must be raised!
    See Ruth
    v.
    Aurora Sanitary District,
    17
    Ill.
    2d
    11,
    158 N.E.
    2d 601
    (1959).”
    Environmental Protection Agency v.
    City of Marion, PCB 71-25, opinion dated October
    28,
    1971.
    Thus,
    the issue of whether the Village must issue non-referendum
    bonds
    is out of our hands.
    The Village has been told and by
    this
    order
    is being told,
    that it must abate pollution.
    With the
    relief provided by Section 46,
    lack of money is no excuse.
    We
    feel,
    therefore,
    that no benefit would be served by
    a Board hear-
    ing,
    since the only issue to be decided would be whether pollution
    should be
    abated.
    We can decide that without
    a hearing.
    We will
    require that the Villag4
    tell us how they are going to finance
    this project.
    This type of report was also made mandatory
    in the
    Marion case,
    supra.
    This opinion constitutes
    the Board’s findings
    of fact and
    conclusions of law.
    ORDER
    1.
    The petition of
    the Village of Lena
    for
    a variance
    extending the date
    for compliance with the treatment and effluent
    standards
    of SWB-14 until December
    1,
    1972
    is hereby granted on
    condition that
    the provisions of this Order
    are met.
    2.
    The Village
    of Lena shall abate its discharge of
    inadequately treated sewage
    in accordance with its revised program
    with
    the following schedule:
    a)
    Completion of plans and
    specifications and sub-
    mission to Agency
    :
    By March
    15,
    1972
    b)
    Award of construction
    contracts
    :
    By July
    1,
    1972
    c)
    Completion of project
    as outlined by
    the
    Village
    :
    By December
    1,
    1972
    3
    712

    3.
    Within forty—five
    (45)
    days of the receipt of this
    Order,
    the Village shall submit to the Board and the Agency a
    plan assuring financing of the program herein approved,
    together
    with
    a study by bond counsel discussing
    the various financing alter-
    natives available.
    I, Christan
    L. Moffett, Clerk of the Pollution Control Board,
    cer~fy that
    the Board adopted the
    above Opinion and Order this
    ~ day of March, 1972 by
    a vote of
    9~’O
    ~
    4’l’
    .~
    ~-
    3
    713

    Back to top