ILLINOIS POLLUTION CONTROL BOARD
    February 3, 1972
    LAKE
    COUNTY DEPARTMENT OF
    )
    PUBLIC WORKS
    v.
    )
    PCB 71—337
    ENVIRONMENTAL PROTECTION AGENCY
    Mr. Lawrence S. Bloom, appeared for the Petitioner;
    Mr. Lee A. Camtbell, Assistant Attorney General, appeared for the
    Respondent
    OPINION OF THE BOARD (by. Mr. Dumelle)
    On October 28, 1971 the Lake County Department of Public Works
    (hereafter Department) filed a petition for variance seek4ng a waiver
    of one of the special conditions established in a permit3-~ issued by
    the Environmental Protection Agency (EPA) to the Department for the
    Department’s Vernon Hills Sewage Treatment Plant (Vernon Hills
    STP). The Department sought to be relieved from complying with the
    permit requirement for clarification and chemical treatment following
    tertiary lagoons.
    We grant a variance for one year, until January 23, 1973 subject
    to several conditions.
    A new sewage treatment plant is to be in operation for the area
    now served by the Vernon Hills STP by August of 1973 (R. 29). The
    present plant will then be abandoned. After August of 1973 the
    Vernon Hills STP will be serving as a lift station to transport wastes
    to the New Century Town Sewage Treatment Plant. The permit applied
    for in this case was to enlarge the existing plant to accommodate
    the additional population load up untill the time that the new plant
    1 Permit Number l971-~B—4O3
    “Special Condition. This permit is issued subject to the condition
    that the owner/operator shall submit plans and specifications within
    four weeks of the date of this permit to provide for final clari-
    fication with chemical coagulation following the two cell lagoon,
    in accordance with the latest policies and technical requirements
    of this agency.”
    3
    601

    is in operation. The Department, on ~1ay 11, 1971 submitted plans
    for the use of a temporary portable plant until the new plant is on
    line. The expansion was to be accomplished with the use of four
    modular units handling 50,000 gallons each (R. 53). A permit was
    granted bn July 13, 1971 which approved the submitted plans and
    added the special condition for clarification by chemical trtatment
    which is the subject of this variance request.
    The equipment called for by the special condition was necessitated
    by a new technical policy statement issued by the EPA in July of
    1971. The added requirement came into existence some two or three
    months after the Department had applied for a permit to operate the
    temporary facilities. The special condition requirement related to
    removal of algae. The algae growth represents a problem for about
    three months of the year at the end of the summer season (R. 45).
    For the remaining months there would be no need for the chemical
    clarifier
    (R. 45-46). There was testimony that had the Department
    known of the new requirement before they start~ed on their expansion
    plans by excavating the lagoons they would have likely opted to
    install mixed media filters instead of the lagoon system. The
    special condition was a requirement for the Department to change
    courses in midstream.
    Compliance with the special condition
    will add a substantial
    expense to the temporary plant.. In making
    our decision the fact
    that the facilities required to meet the special condition of the
    permit were of a temporary nature weighed heavily.
    In little more
    than one year the need for the additionally required treatment will
    surcease. Meanwhile an increment of one—third of the cost of the
    temporary
    plant will have been added to the estimated cost of the
    temporary facilities.
    Mr. Robert J. Degan, Directof of Public Works
    for the Department testified that the cost of engineering and con-
    struction of the temporary plant, exclusive of the special condition
    requirements, was $206,064 (R. 26). The cost of the chemical clarifier
    required by the special condition would be approximately $65,000.
    On the record facts we find that the special condition require-
    ments impose an unreasonable hardship on the petitioner. Further
    since the algae growth will potentially be a problem for cnly about
    three months of the.year we find that there will not be such a
    significant detriment to the environment to not allow the operation
    of the temporary plant without the special condition requirements.
    The evidence showed that the effluent from the temporary plant as
    regards BOD and suspended solids will very likely be of such a quality
    as to exceed the quality of the receiving stream. The plant effluent
    was characterized as meeting the applicable standards of 4 mg/i BOD
    and S mg/l suspended solids (R. 5). The receiving stream~ Seavey
    Ditch, was sampled and showed concentrations of 22 and 19 mg/i ROD
    and 5 and 12 mg/l suspended solids (R. 14). ‘The 22 mg/i BOD and
    5 mg/l suspended solids were samples taken upstream from the present
    plant and would not be a reflection of the character of the present
    plant effluent. With the use of the temporary plant ~which is expected
    to be operational in February 1972 (R. 46) the quality of the
    eceiving ditch should improve.
    3
    602

    We have a precedent for granting a variance in a case such as
    this where it is requested that a governmental body operate a
    sewage treatment facility at variance with the regulatory require-
    ments on a temporary basis while permanent improvements are being
    made. In The Metropolitan Sanitary District of Greater Chicago v.
    EPA, PCB 71-166, (September 16, 1971) we allowed the operation of
    ?he
    District’s Orland Park plant until permanent adequate facilities,
    a new interceptor sewer, could be constructed which would lead to
    the abandonment of the plant for which a variance was asked. There,
    as here, it was demonstrated that no permanent ecological harm would
    occur in the receiving stream.
    We therefore grant the variance subject to the conditions that
    the Department complete construction of its tertiary lagoons by
    February 1972; that the Department abandon the Vernon Hills
    STP as a treatment facility after the ~ Century Town plant is
    in operation and; that the Department submit quarterly reports to
    the Board and the EPA on the~rogressto date.
    One final note, there was some considerable record discussion as
    to the commencement of the ninety day period by which this Board must
    make a decision on the instant variance request. Our rule states
    that “A variance proceeding shall be commenced by filing a petition
    for variance with the Ag~ncyand by filing ten copies of the petition
    with the Clerk of the Board.” (Pollution Control Board Regulations
    40. (a), emphasis added). The instant request was filed with the
    Board on Oôtober 28, 1971. The clock started running on that date.
    This opinion constitutes the Board’s findings of fact and,:con-
    clusions of law.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the Board adopted the above Opinion on the~~
    day of February, 1972 by a vote of ~
    Christan L. Moffett; erk
    tllinois Pollution Control Board
    3— 603

    S
    S

    Back to top