ILLINOIS POLLUTION CONTROL BOARD
December 21, 1971
CITY OF LINCOLN
v
)
PCB 71—295
ENVIRONMENTAL PROTECTION AGENCY
Warren Peters, attorney for the City of Lincoln
Frederick C. Hopper and Thomas 3. Immel, attorneys for the
Environmental Protection Agency
Opinion and Order of the Board (by Samuel R. Aldrich):
Petition for variance was filed October 1, 1971, by the City of
Lincoln, Illinois, requesting a variance of one year from the time
schedule contained in Section 14 of Rule 1.08 of Article I of Rules
and Regulations SWH—L4. The Rule provides a schedule of construction
of municipal treatment works improvements to adequately meet the
water quality standards by July 1972. The City seeks an extension
of time in which to redesign and construct additional facilities
at its sewage treatment plant.
Rule 1.08 of SWB-l4 requires that by July 1972, municipal treatment
plants discharging to small intrastate streams produce an effluent
not exceeding 4 mg/l BOD and 5 mg/l suspended solids. The record
indicates that the City’s present treatment facilities produce an
effluent averaging 20 mg/i BOD (R. 41). The present capacity of the
sewage treatment plant is 2 1/4 million gallons per day (mgd) for
secondary treatment and 5 mgd for primary treatment (R. 42). The
average daily flow is 2.14 mgd. During wet weather, the plant’s cap-
acity is at times inadequate to handle the combined input of sewage
and storm water, with the result that the overflow is passed
untreated to the Rubicon Creek (R. 41, 52, 76). Information as to
the frequency with which wastes are bypassed and the quantity of
wastes bypassed is not available. An inspector for the Agency
testified that on one occasion he observed that none of the sewage
flowing to the plant was receiving any treatment. The plant
operators explained that they had closed down the plant to prevent
grit and rags from entering and clogging the raw sewage pumps (R. 80).
Rule 1.08 of SWB-l4 requires that plans and specifications for
improvements to treatment facilities b~ submitted 30—33 months prior
to the completion date. The latter requirement was met by the City
which submitted preliminary plans and specifications on September 23,
1969 CR. 15). These plans called for the construction of two lagoons
and of a pumping station to pump the effluent from the present plant
plus the first flush of storm water from the combined sewers to the
lagoons CR. 24). Provisions were also made for increasing the
plant’s capacity and for chlorination of the effluent. On September 2,
1970, the Environmental Protection Agency (~‘Agency”) approved the
3
— 295
preliminary engineering report subject to the receipt of final
engineering plans (Pet. Ex 1—A).
The City submitted detailed plans and specifications for its proposed
improvements on April 26, 1971 CR. 26). A permit was received from
the Agency on August 2, 1971 (Pet. Ex. 5)
.
Issuance of the permit
was, however, conditioned upon the submittal of engineering plan
documents for additional facilities to remove BOD and suspended
solids. This condition, denoted Condition #9 in the permit, was
imposed pursuant to Technical Policy 20-24 which requires removal of
algae from the effluents of waste stabilization ponds. According
to the City’s petition, that Technical Policy was adopted by the
Agency approximately two weeks before the City was issued its
permit on August 2, 1971. The City received no notification of the
change in policy prior to issuance of the permit CR. 29).
It is Condition #9 from which the City’s present difficulty stems.
Leonard K. Crawford, a consulting engineer for the City, testified
that the requirement for additional treatsient would necessitate
redesigning the City’s proposed facilities. In its petition, the
City contends that the requirement that it satisfy Condition #9 would
pose an arbitrary and unreasonable hardship upon it: arbitrary,
because at present there is no known professional engineering
knowledge available to permit compliance; and unreasonable, because
the Agency adopted Condition #9 after the City had submitted its
plans and specifications on April 26, 1971, and did not inform the
City of the change in policy until the permit was issued.
Although knowing of no case in which algae are satisfac.torily removed
from lagoon effluent on other than an experimental basis, Mr. Crawford
was of the opinion that such removal could be accomplished (R. 28, 34).
His firm proposed to eliminate the use of the secondary lagoon and
to substitute in its place two final settling tanks provided with
mechanical sludge removal, and to construct a mixing tank for possible
future addition of chemical flocculants (R. 34)
.
Mr. Crawford was
of the opinion that the primary lagoon would be a necessary component
of any system designed to upgrade the City’s effluent (R. 47).
Preliminary plans and specifications incorporating the new proposals
were submitted to the Agency on November 18, 1971 (Pet. Ex. 7-A).
The City now awaits approval of these plans.
Mr. Crawford indicated that once the preliminary plans and specifi-
cations were approved, detailed plans could be prepared within
sixty days (R. 36). He estimated that construction could probably
k~eginin July of 1972 provided prompt approval of both preliminary
and detailed plans was received from the Agency and provided the
necessary additional monies could be raised CR. 38, 36). He indicated
that the project could then be completed by July nf 1973 (R. 38). The
City thus requests a variance of one year from the time schedule
contained in Rule 1.08 of SWB—14.
3—
296
There is no question that the City has been placed in a difficult
situation by the Agency’s new requirements for treatment of lagoon
effluents. The City had complied fully with the provisions of
Rule 1.08 by the timely submittal of preliminary plans and speci-
fications, only to have the rules changed at the last minute. To
require compliance with the orginal schedule now would impose a
substantial hardship on the City. We are therefore persuaded that
the City deserves additional time in which to comply with the rules
governing effluent criteria. Cf. EPA v. City of Marion, PCB 71—25,
(October 28, 1971). The Agency recommends that a variance be granted
for a period of six months (Ex. B). The City contends that this
is insufficient CR. 104). We agree that the City is likely to need
more than six months in view of the technical and financial prob-
lems to be overcome. Section 36(b) of the Environmental Protection
Act permits the granting of variances for a period not exceeding
one year. We will therefore grant to the City a variance of one
year from the date the accompanying order is entered, that is,
until December 21, 1972. At that time the City may request addi-
tional time if the project has not been completed.
We are concerned that the City proceed with the completion of its
improvements with ~ll due speed. The evidence indicates that a primary
lagoon will have to be built on the same site regardless of what
other steps are taken. We will therefore require the City to submit
additional information indicating any additional costs that would
result from proceeding immediately with the construction of a lagoon
and the date by which completion of such a lagoon could be expected.
If construction of a lagoon in the near future is feasible we shall
require that steps are taken to do so at once.
Finally, we note the objections of several local citizens to the
construction of the proposed lagoon. Some of those testifying felt
that in the event of flood conditions, the lagoon would threaten
water supplies and recreational facilities in the area (R. 100, 102).
However, it is not for us to decide the merits of those claims.
Section 39 of the Environmental Protection Act grants to the Agency
the authority to grant permits for. the construction of pollution
control facilities upon proof that the facilities will not violate
the Act or applicable regulations. In issuing a permit for con-
struction of the facilities originally proposed by the City, the
Agency has already indicated its approval of the lagoon. Thus, we
can only assume that adequate measures will be taken to assure the
safety of the surrounding area.
This opinion constitutes the Board’s findings of fact and conclusions
of law.
3
—
297
ORDER
1.
A variance from Section 14 of Rule 1.08 of Rules and
Regulations SWB—14 until December 21, 1972 is hereby
granted to the City of Lincoln, Illinois, for comple-
tion of improvements to its sewage treatment facili-
ties.
2. The City of Lincoln shall, by January 15, 1971,
submit to the Pollution Control Board an affidavit
indicating any additional costs that would result
from proceeding immediately with the construction
of a primary lagoon and the date by which completion
of such a lagoon could be expected.
3. The City of Lincoln shall post a bond or other secu-
rity in the amount of $150,000 in a form acceptable
to the Agency within 35 days after the date of this
Order, such bond to be forfeited in case of failure
to comply with the provisions of this Order.
4. The City of Lincoln shall file quarterly reports
with the Pollution Control Board on March 1, 1972
and at 3—month intervals thereafter to show progress
toward achieving the plan approved by the Agency.
I, Chr~stan Moffett, Acting Clerk of the Pollution Control
Board, certi~fythat the above Opinion and Order was adopted on this
21st day of December, 1971 by a vote of 4—0.
Christan M ff
Acting Cle
3
—
298