ILLINOIS POLLUTION CONTROL BOARD
    December 21, 1971
    CITY OF LINCOLN
    v
    )
    PCB 71—295
    ENVIRONMENTAL PROTECTION AGENCY
    Warren Peters, attorney for the City of Lincoln
    Frederick C. Hopper and Thomas 3. Immel, attorneys for the
    Environmental Protection Agency
    Opinion and Order of the Board (by Samuel R. Aldrich):
    Petition for variance was filed October 1, 1971, by the City of
    Lincoln, Illinois, requesting a variance of one year from the time
    schedule contained in Section 14 of Rule 1.08 of Article I of Rules
    and Regulations SWH—L4. The Rule provides a schedule of construction
    of municipal treatment works improvements to adequately meet the
    water quality standards by July 1972. The City seeks an extension
    of time in which to redesign and construct additional facilities
    at its sewage treatment plant.
    Rule 1.08 of SWB-l4 requires that by July 1972, municipal treatment
    plants discharging to small intrastate streams produce an effluent
    not exceeding 4 mg/l BOD and 5 mg/l suspended solids. The record
    indicates that the City’s present treatment facilities produce an
    effluent averaging 20 mg/i BOD (R. 41). The present capacity of the
    sewage treatment plant is 2 1/4 million gallons per day (mgd) for
    secondary treatment and 5 mgd for primary treatment (R. 42). The
    average daily flow is 2.14 mgd. During wet weather, the plant’s cap-
    acity is at times inadequate to handle the combined input of sewage
    and storm water, with the result that the overflow is passed
    untreated to the Rubicon Creek (R. 41, 52, 76). Information as to
    the frequency with which wastes are bypassed and the quantity of
    wastes bypassed is not available. An inspector for the Agency
    testified that on one occasion he observed that none of the sewage
    flowing to the plant was receiving any treatment. The plant
    operators explained that they had closed down the plant to prevent
    grit and rags from entering and clogging the raw sewage pumps (R. 80).
    Rule 1.08 of SWB-l4 requires that plans and specifications for
    improvements to treatment facilities b~ submitted 30—33 months prior
    to the completion date. The latter requirement was met by the City
    which submitted preliminary plans and specifications on September 23,
    1969 CR. 15). These plans called for the construction of two lagoons
    and of a pumping station to pump the effluent from the present plant
    plus the first flush of storm water from the combined sewers to the
    lagoons CR. 24). Provisions were also made for increasing the
    plant’s capacity and for chlorination of the effluent. On September 2,
    1970, the Environmental Protection Agency (~‘Agency”) approved the
    3
    — 295

    preliminary engineering report subject to the receipt of final
    engineering plans (Pet. Ex 1—A).
    The City submitted detailed plans and specifications for its proposed
    improvements on April 26, 1971 CR. 26). A permit was received from
    the Agency on August 2, 1971 (Pet. Ex. 5)
    .
    Issuance of the permit
    was, however, conditioned upon the submittal of engineering plan
    documents for additional facilities to remove BOD and suspended
    solids. This condition, denoted Condition #9 in the permit, was
    imposed pursuant to Technical Policy 20-24 which requires removal of
    algae from the effluents of waste stabilization ponds. According
    to the City’s petition, that Technical Policy was adopted by the
    Agency approximately two weeks before the City was issued its
    permit on August 2, 1971. The City received no notification of the
    change in policy prior to issuance of the permit CR. 29).
    It is Condition #9 from which the City’s present difficulty stems.
    Leonard K. Crawford, a consulting engineer for the City, testified
    that the requirement for additional treatsient would necessitate
    redesigning the City’s proposed facilities. In its petition, the
    City contends that the requirement that it satisfy Condition #9 would
    pose an arbitrary and unreasonable hardship upon it: arbitrary,
    because at present there is no known professional engineering
    knowledge available to permit compliance; and unreasonable, because
    the Agency adopted Condition #9 after the City had submitted its
    plans and specifications on April 26, 1971, and did not inform the
    City of the change in policy until the permit was issued.
    Although knowing of no case in which algae are satisfac.torily removed
    from lagoon effluent on other than an experimental basis, Mr. Crawford
    was of the opinion that such removal could be accomplished (R. 28, 34).
    His firm proposed to eliminate the use of the secondary lagoon and
    to substitute in its place two final settling tanks provided with
    mechanical sludge removal, and to construct a mixing tank for possible
    future addition of chemical flocculants (R. 34)
    .
    Mr. Crawford was
    of the opinion that the primary lagoon would be a necessary component
    of any system designed to upgrade the City’s effluent (R. 47).
    Preliminary plans and specifications incorporating the new proposals
    were submitted to the Agency on November 18, 1971 (Pet. Ex. 7-A).
    The City now awaits approval of these plans.
    Mr. Crawford indicated that once the preliminary plans and specifi-
    cations were approved, detailed plans could be prepared within
    sixty days (R. 36). He estimated that construction could probably
    k~eginin July of 1972 provided prompt approval of both preliminary
    and detailed plans was received from the Agency and provided the
    necessary additional monies could be raised CR. 38, 36). He indicated
    that the project could then be completed by July nf 1973 (R. 38). The
    City thus requests a variance of one year from the time schedule
    contained in Rule 1.08 of SWB—14.
    3—
    296

    There is no question that the City has been placed in a difficult
    situation by the Agency’s new requirements for treatment of lagoon
    effluents. The City had complied fully with the provisions of
    Rule 1.08 by the timely submittal of preliminary plans and speci-
    fications, only to have the rules changed at the last minute. To
    require compliance with the orginal schedule now would impose a
    substantial hardship on the City. We are therefore persuaded that
    the City deserves additional time in which to comply with the rules
    governing effluent criteria. Cf. EPA v. City of Marion, PCB 71—25,
    (October 28, 1971). The Agency recommends that a variance be granted
    for a period of six months (Ex. B). The City contends that this
    is insufficient CR. 104). We agree that the City is likely to need
    more than six months in view of the technical and financial prob-
    lems to be overcome. Section 36(b) of the Environmental Protection
    Act permits the granting of variances for a period not exceeding
    one year. We will therefore grant to the City a variance of one
    year from the date the accompanying order is entered, that is,
    until December 21, 1972. At that time the City may request addi-
    tional time if the project has not been completed.
    We are concerned that the City proceed with the completion of its
    improvements with ~ll due speed. The evidence indicates that a primary
    lagoon will have to be built on the same site regardless of what
    other steps are taken. We will therefore require the City to submit
    additional information indicating any additional costs that would
    result from proceeding immediately with the construction of a lagoon
    and the date by which completion of such a lagoon could be expected.
    If construction of a lagoon in the near future is feasible we shall
    require that steps are taken to do so at once.
    Finally, we note the objections of several local citizens to the
    construction of the proposed lagoon. Some of those testifying felt
    that in the event of flood conditions, the lagoon would threaten
    water supplies and recreational facilities in the area (R. 100, 102).
    However, it is not for us to decide the merits of those claims.
    Section 39 of the Environmental Protection Act grants to the Agency
    the authority to grant permits for. the construction of pollution
    control facilities upon proof that the facilities will not violate
    the Act or applicable regulations. In issuing a permit for con-
    struction of the facilities originally proposed by the City, the
    Agency has already indicated its approval of the lagoon. Thus, we
    can only assume that adequate measures will be taken to assure the
    safety of the surrounding area.
    This opinion constitutes the Board’s findings of fact and conclusions
    of law.
    3
    297

    ORDER
    1.
    A variance from Section 14 of Rule 1.08 of Rules and
    Regulations SWB—14 until December 21, 1972 is hereby
    granted to the City of Lincoln, Illinois, for comple-
    tion of improvements to its sewage treatment facili-
    ties.
    2. The City of Lincoln shall, by January 15, 1971,
    submit to the Pollution Control Board an affidavit
    indicating any additional costs that would result
    from proceeding immediately with the construction
    of a primary lagoon and the date by which completion
    of such a lagoon could be expected.
    3. The City of Lincoln shall post a bond or other secu-
    rity in the amount of $150,000 in a form acceptable
    to the Agency within 35 days after the date of this
    Order, such bond to be forfeited in case of failure
    to comply with the provisions of this Order.
    4. The City of Lincoln shall file quarterly reports
    with the Pollution Control Board on March 1, 1972
    and at 3—month intervals thereafter to show progress
    toward achieving the plan approved by the Agency.
    I, Chr~stan Moffett, Acting Clerk of the Pollution Control
    Board, certi~fythat the above Opinion and Order was adopted on this
    21st day of December, 1971 by a vote of 4—0.
    Christan M ff
    Acting Cle
    3
    298

    Back to top