ILLINOIS POLLUTION CONTROL BOARD
    December
    91
    1971
    ENVIRONMENTAL PROTECTION AGENCY
    v.
    )
    PCB 71—272
    SOIL ENRICHMENT MATERIALS CORPORATION
    Opinion of the Board
    (by Mr. Dumelle)
    A complaint on behalf of
    the Environmental Protection Agency
    (EPA) was filed by the Attorney General in this matter on
    September
    13,
    1971.
    Soil Enrichment Materials Corporation
    (SEMCO)
    was alleged to have caused or
    to have tended to cause water pollution
    on six separate occasions between February 22 and August
    7,
    1971 all
    in violation of the Environmental Protection Pct and/or a condition
    of the permit issued to SEMCO by
    the Sanitary Water Board
    (one of
    this Board’s and the Environmental Protection Agency’s predecessors)
    on May
    27,
    1970.
    The condition of the permit which SENCO
    is alleged
    to have violated is Condition
    9 which requires
    the maint~ianceof
    a constraining berm around the sludge application areas.
    A money
    penalty and cease and desist order were asked for by the EPA.
    The parties agreed to submit the controversy to the Board upon
    a Stipulation and Supplemental Stipulation transmitted to the Board
    on November
    8,
    1971.
    The total agreement
    is comprised of
    19 numbered
    paragraphs and
    a number of exhibits.
    We find this Board to be
    limited to the factual matters in the stipulation but
    not necessarily
    constrained to the conclusions expressed
    in the stipulation.
    We
    accept the parties agreement as
    to the factual matters in this
    proceeding which has expedited resolution of
    this controversy by
    eliminating
    the necessity of
    a hearing.
    We must emphasize, both
    for the instant parties and for the guidance of future parties before
    1
    Permit #1970
    GA—342
    Condition #9
    -
    This permit is issued on the basis that
    •a
    perimeter berm of adequate construction and height will be
    constructed around the sludge application areas to retain
    all runoff during or immediately after
    the application of
    sludge before
    the material has been plowed into
    the ground.
    The perimeter berm shall be adequate to insure the capture
    and storage of runoff from the most severe historical
    storm of record which has ever occurred in the area,
    all in
    accordance with the intent stated in the February
    26, 1970
    letter to this Board from Bauer Engineering,
    Inc.
    under
    the heading of “Prevention of Surface Runoff”.
    3~
    23~

    the Board,
    that parties can only enter into binding stipulations
    with regard
    to facts and not to legal conclusions.
    It is the
    Board’s function to draw the appropriate legal conclusions from the
    facts.
    Within the generally recognized limitations of public policy
    and reasonableness parties may enter
    into stipulations or agreements
    in respect to either controversial or uncontroverted matters of
    fact and questions of law.
    Any subject matter
    involving
    the parties
    rights may be made the subject of
    a stipulation and the Board must look
    with
    favor on such agreements which have the effect of avoiding delay,
    trouble and expense by simplifying, shortening and settling contested
    matters.
    All, however, must be bound by the rule that parties may
    not by their admissions of law bind the Board
    to adopt their point
    of view.
    In this case,
    as in others, we want to thake
    two aspects of
    stipulations
    clear;
    we welcome parties’ agreement as
    to questions
    of law and legal conclusions but are not necessarily bound by
    them.
    (See, Wiegal v. One LaSalle Co.
    75 Ill. App.
    2d 272
    (1966)
    at
    276)
    SEMCO owns
    and controls certain facilities
    in Douglas County,
    Illinois, designed and used
    for the purpose of applying sludge from
    the Metropolitan Sanitary District of Greater Chicago
    (MSD)
    to farm
    lands controlled by SENCO.
    SEMCO’s facilities include
    a sludge
    unloading trench,
    a sludge storage
    lagoon, piping and pumping
    equipment and spraying facilities.
    The Douglas County facility
    is part of the MSD’s utilization plans
    for nutrient-rich liquid
    wastes.
    The underlying rationale of transporting digested metropo-
    litan Chicago sewage sludge to Douglas County is
    to make
    a beneficial
    use of the digested sludge rather than conceptionalizing it as
    a
    waste product to be dealt with as
    a “problem”.
    In principle
    the
    nutrient-rich liquid waste
    is to be applied to the land in such
    a
    way as to not hydraulically disrupt the surface soil condition.
    As the
    liquid filters down through the crop land it
    is used by the crop root
    system,
    the plant nutrients being transformed by bacteria into
    a form
    used by the
    plants for growth.
    The carrier—water continues downward,
    being filtered as
    it moves,
    and becomes part of
    the ground water supply.
    The Environmental Protection Act defines
    “waters”
    as
    “all
    accumulations of water, surface and underground,
    natural,
    and
    artifical, public and private, or parts thereof, which are wholly
    or partially within,
    flow through,
    or border upon this State.”2
    In this case we
    are not considering
    the sludge leachate which mi-
    grates through the ground.
    We are,
    rather,
    concerned about the
    sludge contaminated water which escapes through
    a break in the
    restraint,
    or which is directed to an area outside of the contained
    area
    and flows into
    a drainage ditch or other water course and
    ultimately pollutes or threatens to pollute the waters of
    this state.
    2T
    Ill.
    Rev.
    Stat.
    Ch.
    111—1/2 ~ 1003
    (o)
    3
    240

    The digested sludge
    is characterized by the EPA as
    a pollutant
    by reason of its concentration of heavy metals
    and suspended solids
    (Stipulation paragraph
    14).
    In at least two places in the stipulation
    the sludge is said to contain no pathogenic organisms
    (paragraph
    6,
    14).
    However,
    the presence of pathogens in the sludge is manifest
    from even
    a casual observation of the exhibits attached to the
    stipulation.
    Both fecal coliform and fecal streptococcus
    are noted
    in varying quantities among the samples
    (Exhibit B—B, D-5, D-6,D-8).
    There are
    also references in the stipulation to use of chlorine,
    presumably
    as
    a disinfectant.
    Further, we can take official notice
    of the oxygen-demanding qualities of sludge and its nutrient content.
    We could not be
    far of£ the mark
    (in the absence of
    a description
    in the record)
    in characterizing the digested sludge as being
    approximately 3-6
    solids and rich in nitrogen and phosphorus
    and
    containing an array of materials
    in lesser quantities which we
    can generically refer to as contaminants.
    On February
    22,
    1971, an accumulation of surface water containing
    dissolved and suspended sludge materials escaped around the end of
    the
    berm and ultimately into the natural surface drainage.
    Upon
    the
    request of the EPA,
    the berm was extended to prevent the recurrence
    of the incident.
    It
    is believed that all of the runoff was cleared
    up
    (paragraph
    7).
    The flow of the surface water was apparently
    caused by the frozen condition of the ground and high rate of rain
    fall at the time
    (Ex. A—3).
    During the night of April
    29,
    1971,
    sludge washed through
    a
    protective berm around
    a field tile catch basin in
    a field under
    irrigation.
    The catch basin had been protected from the sludge by
    a
    12” berm around the perimeter and covering with
    a layer of heavy
    duty plastic.
    The weight of the sludge which collected on the
    plastic was enough to pull
    the plastic loose allowing the sludge
    to wash through the protective berm and enter
    the tile of
    the catch
    basin, which drained into
    an open railroad drainage ditch.
    There
    was little or no water
    in the drainage ditch at the time and the
    sludge was entrapped there.
    Upon discovery on April
    30,
    spraying
    was immediately stopped and
    a berm was constructed across the
    drainage ditch to prevent further drainage of
    sludge.
    On the same
    day the catch basins were replugged with plywood and the berm
    was replaced with compacted earth.
    The
    tile was dug
    up and plugged
    near its terminal point
    and its contents pumped into
    a large storage
    lagoon
    (paragraph
    8).
    A discernible flow of sludge apparently
    extended
    for approximately one—half mile in the drainage ditch
    (Ex.
    B-i).
    On May
    7,
    1971,
    following a substantial rain after sludge had
    been applied,
    sludge over-ran a protective berm and flowed into
    a
    road ditch adjacent to SENCO property.
    The situation was cleaned
    up in short order
    (paragraph 9).
    Not however before sludge had
    traveled down the drainage ditch for approximately one-eighth of
    a mile
    (Ex. C-l).
    Samples were collected from the ditch and from
    3
    241

    the SEMCO field and analyzed for mercury.
    Concentrations of 18.4
    and 2.9 mg/i of mercury respectively were noted
    (Ex.
    0—3,
    0—4).
    We
    find the
    three preceding incidents to be violations of the permit
    condition
    *9.
    On June
    28,
    1971, SEMCO reported to EPA that
    a six inch
    diameter pressure rubber hose which connected a booster pump to
    the sludge pipeline
    from
    a lagoon to the spreading site had ruptured
    causing sludge
    to flow along a ditch and enter
    a subsurface 24”
    drainage tile.
    Upon discovery of the leak, operations were ceased
    and
    a cleanup followed.
    A berm was erected around the tile to
    prevent sludge from entering.
    The tile was then dug up and blocked.
    A portable pump and water truck were used to pump the sludge material
    back over the berm.
    Six gallons of Clorox Bleach were added to
    the ditch and tile.
    It was believed that all the lost sludge was
    contained.
    However,
    the field tile was
    then inspected at
    a downstream
    point and it was evident that an unknown quantity of sludge had
    entered the tile and flowed into
    a watercourse which flows directly
    to the Kaskaskia River.
    The point of discharge was viewed and
    a heavy
    concentration of sludge was
    noted.
    The watercourse was black
    for
    approximately the two-hundred and fifty yards which were viewed,
    No
    trace of
    the sludge could be found where
    the watercourse was inspected
    approximately three quarters of
    a mile below the point where the tile
    surfaces; apparently bdcause of the
    low velocity of the stream the
    sludge had not yet reached that point
    (paragraph
    10).
    Samples were
    taken from the break in the field tile which upon analysis showed
    a fecal coliform concentration of 1090/100 ml, total coliform of
    22,000/100
    ml and fecal streptococcus of 690/100 ml
    (Exhibits D—5)
    Another sample taken off—site showed higher concentrations of fecal
    and total coliform bacteria
    (Exhibit D-6).
    We
    find this incident to
    have caused water pollution.
    On July
    27,
    1971,
    SEMCO reported to EPA that failure of
    a connecting clamp on the pipe line from the holding lagoon to the
    spreading site caused a small quantity of sludge to enter
    a road
    side ditch.
    The ditch was immediately blocked and no sludge reached
    any field tiles.
    The contained sludge was then diluted with wash
    water, chlorinated with HTH tablets,
    and pumped onto SEMCO property
    (paragraph 11).
    The Board finds no threat of water pollution in this
    incident though
    I would have so found.
    Had it been raining at the
    time the pollution would probably not have been contained.
    On August
    7,
    1971
    a
    pipeline
    broke
    at
    a
    “U”
    bend
    under
    a
    road
    causing sludge to flow into a ditch on the side of the road.
    The
    pump was shut off after
    a drop in line pressure was noted.
    As soon
    as the break was located,
    earth dams were made in the ditch to
    contain the sludge.
    The sludge was then pumped out of the ditch
    onto adjacent SEMCO property.
    The area was cleaned and the earth
    dams in the ditch were removed.
    The following corrective actions were
    instituted to prevent recurrence of
    this type of spill:
    (1)
    Addi-
    tional
    walkie-taikie
    radios
    were
    procured
    so
    that
    immediate
    coinmuni-
    cation
    could
    be
    made
    with
    the
    personnel
    at
    the
    pumps
    at
    all
    times.
    (2)
    The
    personnel
    were
    instructed in how to interpret pressure
    gauge readings at
    the pumps
    and to shut off the pumps immed~,ateiyif
    there were
    any indications of
    a pipe line failure.
    (3)
    Stakes and
    3
    242

    an
    earth
    cover
    were
    used
    to
    secure
    the
    pipe
    line
    against
    pressure
    surges
    where
    the
    pipe
    line
    makes
    the
    “U”
    bend
    under
    the
    road,
    (4)
    T
    Field
    Superintendent
    was
    relieved
    of
    his
    duties
    and
    replaced
    (para-
    graph
    12).
    An
    EPA
    memorandum
    attached
    to
    the
    stipulation
    of
    the
    facts
    in this incident indicates that the sludge involved in the
    spill on this date was not as well digested as other material
    ureviously received
    (Ex.
    F—4).
    The same exhibit reports that
    approximately 50,000 gallons of sludge was lost into SEMCO’s
    drainage channel.
    Again the majority of the Board finds this inciden
    not to constitute a threat
    to water pollution.
    I would have found
    otherwise,
    Had
    it been raining
    the 50,000 gallons of partially
    digested sludge probably could not have been contained.
    Clearly the four occurrences
    first outlined above constitute
    separate viola~ons of Section 12(a),
    (b)
    or
    (d)
    of the Environmental
    Protection Act~’~and/or Condition
    9 of the permit issued by SEMCO.
    There are multiple violations connected with some of these several
    occurrences,
    In each instance in which the restraining berm was
    breached
    a violation of permit Condition
    9 occurred.
    In the June
    28
    instance sludge reached protected waters and caused water pollution.
    The majority cannot find violations on July
    27
    or August
    7,
    since
    there
    was
    neither
    pollution
    of
    a
    stream,
    violation
    of
    the
    permit
    conditions,
    hor proof of negligence such as to justify
    a finding that
    the
    risk
    (“threat”)
    of
    pollution
    was
    iiir~n~n~h1~.
    Digested sludge
    may
    in
    fact
    be
    a
    “resource
    out of place” but it
    is
    also
    a
    serious
    contaminant if not handled properly.
    It
    is the intent of this
    opinion to reflect the Board’s concern for care in handling digested
    sludge when land placement
    is undertaken.
    We will impose
    a penalty
    of
    $500 for each
    violation for
    a total penalty of $2,000.
    Further
    we will order SEMCO to cease and desist its violations of the
    Environmental Protection Act and the conditions of the permit.
    This opinion constitutes
    the Board’s findings
    of fact and con-
    clusions of law in this proceeding.
    Mr. Aldrich will file
    a separate
    concurring
    Opinion.
    3
    111.
    Rev.
    Stat.
    Ch.
    111—1/2
    ~
    1012(a)
    ,
    (b)
    ,.
    (d)
    3
    24,~

    Back to top