ILLINOIS POLLUTION CONTROL BOARD
November
11,
1971
METROPOLITAN SANITARY DISTRICT
OF GREATER CHICAGO
v.
)
#
71—183
ENVIRONMENTAL PROTECTION AGENCY,
Allan
S. Lavin
and Paul
D.
Lindauer for Metropolitan Sanitary District
Roger Ganobcik and Thomas McMahon for
the Environmental Protection Agency
Opinion of the Board
(by Mr.
Currie):
The Metropolitan Sanitary District seeks
a variance from the
effluent and treatment requirements
of Rules
and Regulations
SWB-l4.
We deny
the variance
for reasons given below.
The District operates
a small trickling filter plant for
sewage treatment at Streamwood.
Designed
to treat 1.2 million
gallons per day,
it has become grievously overloaded by the continued
allowance
of increased waste discharges that there
is
no capacity
to treat.
The average dry weather flow
is today nearly 20
above capacity, and the overload
is greater during rains.
Treat-
ment efficiency has declined from 88,
which
is reasonably good
secondary treatment,
to 70
in 1970, which is not
(R.. 10—12,
18,
37,
129).
Rules
and Regulations SWB-14, adopted
in 1967, require the
construction
of additional facilities, quite apart from the
question of overload,
in order to provide tertiary treatment afford-
ing
an effluent containing no more than
4 mg/l
of biochemical
oxygen demand and
5 mg/l of suspended solids, because, as
the
record here makes clear
(R.
145-46)
,
there is so little flow in
the receiving stream during portions of the year that the effluent
is virtually
the entire stream.
Provision for control of storm
water overflows
and bypasses
is also required.
Submission of
plans for these facilities was required
in January,
1971; construction
contracts were to be
let by
July;
and the facilities are required
to be in full operation by July,
1972.
It
is from these requirements that the present petition
seeks relief.
The District has
not submitted the plans
that
were required nearly
a year
ago, nor awarded the contracts
as
it was required to do by
last July.
Even at the date of hearing
in October the District did not commit itself to any program for
achieving compliance with the regulations.
The evidence shows
that the District
is considering several alternative plans
CR.
61-72)
3
—
57
most prominent
of which
are
the construction of
a new 7.4 mgd
plant with advanced treatment to serve the whole Poplar Creek area
(R.
66)
and
a joint project with the Elgin Sanitary District
for expansion
of the latter’s secondary facilities with discharge
of the effluent
to the Fox River
CR. 72)J
The Poplar Creek
plant was
the District’s
idea, but
it ran afoul of
the regionalization
policies of the Northeastern
Illinois Planning Commission,
which has refused to aporove the plant for
federal or state financial
aid
(R.
80-83,
102).
The Elgin Sanitary District has appeared
less than enthusiastic about the proposed
joint facility
(R.
84,
105—06)
,
but at latest word had agreed
to participate
in
a study
of
the possibility
CR.
110).
In the meantime pollution goes on.
The District testified that even
if construction of the Poplar
Creek plant——not yet designed——began
as
soon as is possible today
compliance could not be achieved until some
time in 1975
(R.
71—72)
And
the District is not
committed
to
starting that construction.
In place
of
a program
for meeting the tertiary treatment
requirement,
the District seeks approval of
a plan for providing
interim improvements to
the existing facility in hopes that
doing so will make
it possible
for still more new homes to be
connected
to
the plant, although
there
is
no suggestion that
the
improvements will come
close
to
complying with what
is required.
The
proposal
is
to
construct
facultative
lagoon
to
provide
some
degree
of
treatment
for
flows
ii’.
excess
of
the
capacity
ct
the
trickling
filter
(P.
12—13)
.
Even
at
the
outset,
the
lagoon
will
be
incapable
o:E
producing
an
effluent
meeting
existing
standards
for
secondary
treatment
(P.
32)
,
much
less
the
tertiary
treatment
that
is
recruired
by
next
July.
Further,
the
District’s
own
evidenco
is
that
the
rerformance
of
the
lagoon
will
progressive-
ly
degenerate
as
additional
wastes
are
added,
so
that
by
the
beginning
of
1975-—before
any
permanent
facility
can
be
completed
according
to
this
record—-its
treatment
efficiency
will
be
little
better
than
that
of
the
presently
overloaded
trickling
filter,
and
the
‘total
flow
of
effluent
will
have
increased
considerably
(P.
16,
18,
49,
57).
The
program
also
contemplates
chlorination
of
the
lagoon
effluent
in
a
contact
chamber
(P.
13)
,
but
at
least
until
the
time
of
the
hearing
the
District
had
no
plans
to
provide
adequate
retention
time
for
the
effluent
from
the
trickling
filter
itself,
which
is
now
given
disinfection
on
the
run
(F.
39)
with
the
result
that
the
receiving
stream
is
alarmingly
high
in
bacteria.
The
essence
of
a
variance,
as we have pointed out
before
(e.g.,
Swords
v.
EPA,
#70—6,
Sept.
2,
1970; Mt.
Carmel Public
Utility
Co.
v.
EPA,
#
71-15, April
14,
1971; Flintkote Co.
v.
EPA,
# 71-68, November
11,
1971)
,
is
a firm and adequate program
for achieving compliance with the regulations
1n the shortest
1.
The Agency’s objection to evidence
as
to the District’s plans
for meeting the advanced treatment requirements was misplaced.
This,
as said below,
is
‘,ihat
the case
is
all about.
3—58
practicable time.
There
is
no such program here.
We have
no commitment from the District to build anything to comply with
the advanced treatment requirements,
for the District has
not
decided whether to build
its own plant or
to join with Elgin.
We have no date for expected compliance.
We are asked to grant
an open—ended extension of time
for compliance with this extreme-
ly important regulation while the District tries once again to
get approval
for federal and state help.
But years
have gone
by and nothing has been done.
As we have held elsewhere,
the
desire that others help foot the bill
is no excuse for continuing
to pollute;
the obligation
is that of the Sanitary District to
meet the regulations by whatever means are available
(City of
Mattoon v.
EPA,
#
71-8, April
14,
1971; Durand Sanitary District
V.
EPA,
# 71—317, October 14,
1971).
Similarly, while we have had several occasions
to express
our endorsement
of regionalization of sewage treatment in order
to avoid the proliferation of uneconomic and unreliable small
treatment plants
(see DuPage County Regionalization,
*R 70-17,
proposed regulation and explanation,
June
9,
1971;
Gages Lake
Sanitary District v.
EPA,
#
71-104,
September
16,
1971; EPA
v.
City of Silvis,
#
71—157
(October
18,
1971)
,
we do not believe
that necessary measures for
the abatement of existing pollution
should be generally or long delayed while painful plans are made
for
joint treatment facilities.
In
‘the present case, moreover,
the preference of the Planning Commission
for
the
joint facility
seems
to be based largely upon the
fact that under present
regulations
sewage pumped to
the Fox
River need be given only
secondary treatment, with attendant cost
savings.
See NIPC
letter
of Aug.
30,
1971, and attachments.
In League of Women
Voters
v. North Shore Sanitary District,
# 70-7,
March
31,
1971, we rejected
a similar proposal on the ground that
the small
cost savings did not justify
the
less adequate treatment.
While
we do not say the
facts relative
to Streamwood
and Elgin would
require us to reach the same conclusion,
it
is also relevant to
note that the present provision
for secondary treatment on the
Fox
is not necessarily immutable;
that river has been prominently
mentioned for special protection
as
a scenic river,
and it
already receives
a heavy load of secondary
effluents’.
Dilution
with someone else’s secondary effluent is not the equivalent of
dilution with clean stream water,
and additional treatment may
be
found necessary on the Fox as well.
In short, there
is neither an adequate program for complying
with SWB—l4 nor an adequate excuse
for the delays so far incurred
in doing
so.
The case
is
thus distinguishable from Metropolitan
Sanitary District v.
EPA,
*71-166
(September
16,
1971),
(Orland
Park), where
the delay was due
to problems with
a contractot’s
performance and
a definite and reasonably short program for
compliance was presented.
3—59
Moreover,
the proposed interim measures are inadequate to
provide
the best practicable treatment until compliance
is
achieved.
If the problem were simply additional retention time
for disinfecting
the filter effluent, we could order
that to be
provided on the basis of
the record
(R.
40).
But the quality
of
the effluent from the proposed lagoon will be unsatisfactory
even at the beginning,
and it will be wholly unacceptable
long
before advanced treatment can be provided.
No provision
is made,
as
it was by the same District to deal with an interim situation
at Orland Park
(Metropolitan
Sanitary District
v.
EPA,
#
71—166,
supra)
,
for the use of chemicals
‘to aid in precipitation of
objectionable materials
(F.
46-47).
No consideration was given
to
the possibility, conceded by the District in testimony
to
be probably more satisfactory, that placing the filter and
lagoon
in series rather than
in parallel might significantly
improve overall performance
(P.
50-51)
.
Too little is said
about dealing with stormwater problems
(F.
199-201),
The interim
program is inadequate.
The Board
takes official notice of
the issuance in October,
1971 of
the
“Process Design Manual for Upgrading Existing Waste-
water Treatment Plants”
by
the U.S. Environmental Protection
Agency.
The
Board expects
that the District in
its further study
of
ways
to
upgrade
the
Streamwood
plant will consult this manual
and explore
and
comment
on
the
possible
applicability
of
at
least
the following methods for improvement of the effluent:
1.
Operation
of
the
lagoon in series with the Imhoff—trickling
filter plant.
2.
Replacement
of stone in ~he trickling filters with
plastic media.
3.
Addition
of chemicals
to
‘the Imhoff tank.
4.
Addition
of chemicals
to the final clarifiers.
5.
Installation of tube settlers
in the Imhoff tank.
6.
Installation of tube settlers
in the
final clarifiers.
In summary, we must deny the variance.
We cannot approve
a orogram for complying with
the standards, since there is
no program.
We cannot approve the interim proposal,
since
it
is inadequate.
We cannot give the District
a shield against
possible money penalties for failing to comply with
the regulations,
or for allowing the present overload
‘to come about,
for it has
not proved any satisfactory excuse.
Cf.
Flintkote Co.
v.
EPA,
* 71-68, November
11,
1971.
We cannot give permission for
the addition of still more wastes,
for
they cannot adequately
be treated.
With respect to
the question of overload,
this
is
still another case of growth without concern
for
the provision
3—60
of essential services.
With respect to the question of
tertiary
treatment,
it is another case where
the often illusory hope
that someone else will pay the bill has delayed what
is necessary
to avoid pollution.
On both counts the environment
is the
loser.
Denial of the variance obviously does
not require
the plant
to close;
that would he
to make the problem far worse.
It leaves
the District in the same position
it put itself
in when it missed
the deadlines
of SWB-l4:
It
is
subject to whatever sanctions
might be found appropriate
in an enforcement proceeding,
and
it
is free to submit
a further petition correcting the present
deficiencies.
If
such
a petition contemplates
a
joint project.
other parties to the project should be made additional
parties
Meantime the District would be well advised
to get started with
dispatch upon adequate interim measures to alleviate the present
intolerable situation and upon the construction of whatever it
decides
is
the appropriate means
of
achieving compliance with
the
effluent standards of
SWB—l4.
The petition for variance is denied.
This opinion constitutes
the Board’s findings
of fact,
conclusions
of
law,
and order.
I,
Christan Moffett, Acting Clerk of the Pollution Control Board,
certify that
the Board adopted the above Opinion this______
day of
‘‘
‘‘
‘
,
1971.
3 —6~