ILLINOIS POLLUTION CONTROL BOARD
    November
    11,
    1971
    METROPOLITAN SANITARY DISTRICT
    OF GREATER CHICAGO
    v.
    )
    #
    71—183
    ENVIRONMENTAL PROTECTION AGENCY,
    Allan
    S. Lavin
    and Paul
    D.
    Lindauer for Metropolitan Sanitary District
    Roger Ganobcik and Thomas McMahon for
    the Environmental Protection Agency
    Opinion of the Board
    (by Mr.
    Currie):
    The Metropolitan Sanitary District seeks
    a variance from the
    effluent and treatment requirements
    of Rules
    and Regulations
    SWB-l4.
    We deny
    the variance
    for reasons given below.
    The District operates
    a small trickling filter plant for
    sewage treatment at Streamwood.
    Designed
    to treat 1.2 million
    gallons per day,
    it has become grievously overloaded by the continued
    allowance
    of increased waste discharges that there
    is
    no capacity
    to treat.
    The average dry weather flow
    is today nearly 20
    above capacity, and the overload
    is greater during rains.
    Treat-
    ment efficiency has declined from 88,
    which
    is reasonably good
    secondary treatment,
    to 70
    in 1970, which is not
    (R.. 10—12,
    18,
    37,
    129).
    Rules
    and Regulations SWB-14, adopted
    in 1967, require the
    construction
    of additional facilities, quite apart from the
    question of overload,
    in order to provide tertiary treatment afford-
    ing
    an effluent containing no more than
    4 mg/l
    of biochemical
    oxygen demand and
    5 mg/l of suspended solids, because, as
    the
    record here makes clear
    (R.
    145-46)
    ,
    there is so little flow in
    the receiving stream during portions of the year that the effluent
    is virtually
    the entire stream.
    Provision for control of storm
    water overflows
    and bypasses
    is also required.
    Submission of
    plans for these facilities was required
    in January,
    1971; construction
    contracts were to be
    let by
    July;
    and the facilities are required
    to be in full operation by July,
    1972.
    It
    is from these requirements that the present petition
    seeks relief.
    The District has
    not submitted the plans
    that
    were required nearly
    a year
    ago, nor awarded the contracts
    as
    it was required to do by
    last July.
    Even at the date of hearing
    in October the District did not commit itself to any program for
    achieving compliance with the regulations.
    The evidence shows
    that the District
    is considering several alternative plans
    CR.
    61-72)
    3
    57

    most prominent
    of which
    are
    the construction of
    a new 7.4 mgd
    plant with advanced treatment to serve the whole Poplar Creek area
    (R.
    66)
    and
    a joint project with the Elgin Sanitary District
    for expansion
    of the latter’s secondary facilities with discharge
    of the effluent
    to the Fox River
    CR. 72)J
    The Poplar Creek
    plant was
    the District’s
    idea, but
    it ran afoul of
    the regionalization
    policies of the Northeastern
    Illinois Planning Commission,
    which has refused to aporove the plant for
    federal or state financial
    aid
    (R.
    80-83,
    102).
    The Elgin Sanitary District has appeared
    less than enthusiastic about the proposed
    joint facility
    (R.
    84,
    105—06)
    ,
    but at latest word had agreed
    to participate
    in
    a study
    of
    the possibility
    CR.
    110).
    In the meantime pollution goes on.
    The District testified that even
    if construction of the Poplar
    Creek plant——not yet designed——began
    as
    soon as is possible today
    compliance could not be achieved until some
    time in 1975
    (R.
    71—72)
    And
    the District is not
    committed
    to
    starting that construction.
    In place
    of
    a program
    for meeting the tertiary treatment
    requirement,
    the District seeks approval of
    a plan for providing
    interim improvements to
    the existing facility in hopes that
    doing so will make
    it possible
    for still more new homes to be
    connected
    to
    the plant, although
    there
    is
    no suggestion that
    the
    improvements will come
    close
    to
    complying with what
    is required.
    The
    proposal
    is
    to
    construct
    facultative
    lagoon
    to
    provide
    some
    degree
    of
    treatment
    for
    flows
    ii’.
    excess
    of
    the
    capacity
    ct
    the
    trickling
    filter
    (P.
    12—13)
    .
    Even
    at
    the
    outset,
    the
    lagoon
    will
    be
    incapable
    o:E
    producing
    an
    effluent
    meeting
    existing
    standards
    for
    secondary
    treatment
    (P.
    32)
    ,
    much
    less
    the
    tertiary
    treatment
    that
    is
    recruired
    by
    next
    July.
    Further,
    the
    District’s
    own
    evidenco
    is
    that
    the
    rerformance
    of
    the
    lagoon
    will
    progressive-
    ly
    degenerate
    as
    additional
    wastes
    are
    added,
    so
    that
    by
    the
    beginning
    of
    1975-—before
    any
    permanent
    facility
    can
    be
    completed
    according
    to
    this
    record—-its
    treatment
    efficiency
    will
    be
    little
    better
    than
    that
    of
    the
    presently
    overloaded
    trickling
    filter,
    and
    the
    ‘total
    flow
    of
    effluent
    will
    have
    increased
    considerably
    (P.
    16,
    18,
    49,
    57).
    The
    program
    also
    contemplates
    chlorination
    of
    the
    lagoon
    effluent
    in
    a
    contact
    chamber
    (P.
    13)
    ,
    but
    at
    least
    until
    the
    time
    of
    the
    hearing
    the
    District
    had
    no
    plans
    to
    provide
    adequate
    retention
    time
    for
    the
    effluent
    from
    the
    trickling
    filter
    itself,
    which
    is
    now
    given
    disinfection
    on
    the
    run
    (F.
    39)
    with
    the
    result
    that
    the
    receiving
    stream
    is
    alarmingly
    high
    in
    bacteria.
    The
    essence
    of
    a
    variance,
    as we have pointed out
    before
    (e.g.,
    Swords
    v.
    EPA,
    #70—6,
    Sept.
    2,
    1970; Mt.
    Carmel Public
    Utility
    Co.
    v.
    EPA,
    #
    71-15, April
    14,
    1971; Flintkote Co.
    v.
    EPA,
    # 71-68, November
    11,
    1971)
    ,
    is
    a firm and adequate program
    for achieving compliance with the regulations
    1n the shortest
    1.
    The Agency’s objection to evidence
    as
    to the District’s plans
    for meeting the advanced treatment requirements was misplaced.
    This,
    as said below,
    is
    ‘,ihat
    the case
    is
    all about.
    3—58

    practicable time.
    There
    is
    no such program here.
    We have
    no commitment from the District to build anything to comply with
    the advanced treatment requirements,
    for the District has
    not
    decided whether to build
    its own plant or
    to join with Elgin.
    We have no date for expected compliance.
    We are asked to grant
    an open—ended extension of time
    for compliance with this extreme-
    ly important regulation while the District tries once again to
    get approval
    for federal and state help.
    But years
    have gone
    by and nothing has been done.
    As we have held elsewhere,
    the
    desire that others help foot the bill
    is no excuse for continuing
    to pollute;
    the obligation
    is that of the Sanitary District to
    meet the regulations by whatever means are available
    (City of
    Mattoon v.
    EPA,
    #
    71-8, April
    14,
    1971; Durand Sanitary District
    V.
    EPA,
    # 71—317, October 14,
    1971).
    Similarly, while we have had several occasions
    to express
    our endorsement
    of regionalization of sewage treatment in order
    to avoid the proliferation of uneconomic and unreliable small
    treatment plants
    (see DuPage County Regionalization,
    *R 70-17,
    proposed regulation and explanation,
    June
    9,
    1971;
    Gages Lake
    Sanitary District v.
    EPA,
    #
    71-104,
    September
    16,
    1971; EPA
    v.
    City of Silvis,
    #
    71—157
    (October
    18,
    1971)
    ,
    we do not believe
    that necessary measures for
    the abatement of existing pollution
    should be generally or long delayed while painful plans are made
    for
    joint treatment facilities.
    In
    ‘the present case, moreover,
    the preference of the Planning Commission
    for
    the
    joint facility
    seems
    to be based largely upon the
    fact that under present
    regulations
    sewage pumped to
    the Fox
    River need be given only
    secondary treatment, with attendant cost
    savings.
    See NIPC
    letter
    of Aug.
    30,
    1971, and attachments.
    In League of Women
    Voters
    v. North Shore Sanitary District,
    # 70-7,
    March
    31,
    1971, we rejected
    a similar proposal on the ground that
    the small
    cost savings did not justify
    the
    less adequate treatment.
    While
    we do not say the
    facts relative
    to Streamwood
    and Elgin would
    require us to reach the same conclusion,
    it
    is also relevant to
    note that the present provision
    for secondary treatment on the
    Fox
    is not necessarily immutable;
    that river has been prominently
    mentioned for special protection
    as
    a scenic river,
    and it
    already receives
    a heavy load of secondary
    effluents’.
    Dilution
    with someone else’s secondary effluent is not the equivalent of
    dilution with clean stream water,
    and additional treatment may
    be
    found necessary on the Fox as well.
    In short, there
    is neither an adequate program for complying
    with SWB—l4 nor an adequate excuse
    for the delays so far incurred
    in doing
    so.
    The case
    is
    thus distinguishable from Metropolitan
    Sanitary District v.
    EPA,
    *71-166
    (September
    16,
    1971),
    (Orland
    Park), where
    the delay was due
    to problems with
    a contractot’s
    performance and
    a definite and reasonably short program for
    compliance was presented.
    3—59

    Moreover,
    the proposed interim measures are inadequate to
    provide
    the best practicable treatment until compliance
    is
    achieved.
    If the problem were simply additional retention time
    for disinfecting
    the filter effluent, we could order
    that to be
    provided on the basis of
    the record
    (R.
    40).
    But the quality
    of
    the effluent from the proposed lagoon will be unsatisfactory
    even at the beginning,
    and it will be wholly unacceptable
    long
    before advanced treatment can be provided.
    No provision
    is made,
    as
    it was by the same District to deal with an interim situation
    at Orland Park
    (Metropolitan
    Sanitary District
    v.
    EPA,
    #
    71—166,
    supra)
    ,
    for the use of chemicals
    ‘to aid in precipitation of
    objectionable materials
    (F.
    46-47).
    No consideration was given
    to
    the possibility, conceded by the District in testimony
    to
    be probably more satisfactory, that placing the filter and
    lagoon
    in series rather than
    in parallel might significantly
    improve overall performance
    (P.
    50-51)
    .
    Too little is said
    about dealing with stormwater problems
    (F.
    199-201),
    The interim
    program is inadequate.
    The Board
    takes official notice of
    the issuance in October,
    1971 of
    the
    “Process Design Manual for Upgrading Existing Waste-
    water Treatment Plants”
    by
    the U.S. Environmental Protection
    Agency.
    The
    Board expects
    that the District in
    its further study
    of
    ways
    to
    upgrade
    the
    Streamwood
    plant will consult this manual
    and explore
    and
    comment
    on
    the
    possible
    applicability
    of
    at
    least
    the following methods for improvement of the effluent:
    1.
    Operation
    of
    the
    lagoon in series with the Imhoff—trickling
    filter plant.
    2.
    Replacement
    of stone in ~he trickling filters with
    plastic media.
    3.
    Addition
    of chemicals
    to
    ‘the Imhoff tank.
    4.
    Addition
    of chemicals
    to the final clarifiers.
    5.
    Installation of tube settlers
    in the Imhoff tank.
    6.
    Installation of tube settlers
    in the
    final clarifiers.
    In summary, we must deny the variance.
    We cannot approve
    a orogram for complying with
    the standards, since there is
    no program.
    We cannot approve the interim proposal,
    since
    it
    is inadequate.
    We cannot give the District
    a shield against
    possible money penalties for failing to comply with
    the regulations,
    or for allowing the present overload
    ‘to come about,
    for it has
    not proved any satisfactory excuse.
    Cf.
    Flintkote Co.
    v.
    EPA,
    * 71-68, November
    11,
    1971.
    We cannot give permission for
    the addition of still more wastes,
    for
    they cannot adequately
    be treated.
    With respect to
    the question of overload,
    this
    is
    still another case of growth without concern
    for
    the provision
    3—60

    of essential services.
    With respect to the question of
    tertiary
    treatment,
    it is another case where
    the often illusory hope
    that someone else will pay the bill has delayed what
    is necessary
    to avoid pollution.
    On both counts the environment
    is the
    loser.
    Denial of the variance obviously does
    not require
    the plant
    to close;
    that would he
    to make the problem far worse.
    It leaves
    the District in the same position
    it put itself
    in when it missed
    the deadlines
    of SWB-l4:
    It
    is
    subject to whatever sanctions
    might be found appropriate
    in an enforcement proceeding,
    and
    it
    is free to submit
    a further petition correcting the present
    deficiencies.
    If
    such
    a petition contemplates
    a
    joint project.
    other parties to the project should be made additional
    parties
    Meantime the District would be well advised
    to get started with
    dispatch upon adequate interim measures to alleviate the present
    intolerable situation and upon the construction of whatever it
    decides
    is
    the appropriate means
    of
    achieving compliance with
    the
    effluent standards of
    SWB—l4.
    The petition for variance is denied.
    This opinion constitutes
    the Board’s findings
    of fact,
    conclusions
    of
    law,
    and order.
    I,
    Christan Moffett, Acting Clerk of the Pollution Control Board,
    certify that
    the Board adopted the above Opinion this______
    day of
    ‘‘
    ‘‘
    ,
    1971.
    3 —6~

    Back to top