ILLINOIS POLLUTION CONTROL BOARD
    October
    3,
    1972
    CINNAMON CREEK ASSOCIATES
    v.
    )
    #
    72—377
    ENVIRONMENTAL PROTECTION AGENCY
    THOMAS
    I. SIMPSON
    v.
    )
    #
    72—368
    CINNAMON CREEK ASSOCIATES et al
    Opinion & Order of the Board on Motion for Emergency Disposition
    (by Mr. Currie)
    Cinnamon Creek,
    as all parties concede, made a connection
    to
    a Waukegan sewer in the summer of 1971,
    after the entry
    of our order forbidding such connections because of the
    unsatisfactory condition of the sewage treatment plants
    in the North Shore Sanitary District, League of Women
    Voters v.
    NSSD,
    #70-7,
    1 PCB 369
    (March 31,
    1971)
    .
    The
    question is what we should do about it.
    This question was first raised by
    a variance petition,
    #72-340,
    seeking permission
    to utilize the connection on
    grounds of hardship.
    We dismissed the petition without
    prejudice for failure to allege the inability to obtain
    a permit under North Shore Sanitary District
    V.
    EPA,
    #71—343,
    3 PCB 541 and 697
    (Jan.
    31 and March
    2,
    1972)
    which allowed
    a number of connections because of improve-
    ments at the treatment plants.
    Cinnamon Creek Associates
    v.
    EPA,
    #72-340,
    5 PCB
    (Aug.
    22,
    1972)
    .
    There follow-
    ed the filing of Simpson’s complaint asking us~toorder
    disconnection; Cinnamon Creek’s motion for suminary~judg—
    ment in its favor;
    Simpson’s admission of the facts
    alleged by Cinnamon Creek; the filing of an amended variance
    petition reciting that no permit can be had because the
    sewer to which the connection was made has itself been
    disignated as overloaded pursuant to our decision in
    #71-343; and a motion for expedited consideration because
    of the alleged need to proceed
    with
    construction before
    winter.
    The Agency’s recommendation, which is favorable
    to
    the
    petition,
    was
    received
    by
    telephone
    Seotember
    26~

    —2—
    No hearing has been held.
    The immediate question is whether the relevant facts
    are sufficiency clear to enable us to dispose of these cases
    without hearing.
    A detailed consideration of the law and of
    the present record
    is necessary.
    1.
    Actions Taken Before the Sewer Ban
    In a long line of cases beginning with Wachta
    V.
    EPA,
    #71-77,
    2 PCB 117
    (July 12, 1971), we have allowed connections
    to be made despite our general ban orders in cases in which
    actual construction of the builaings to be connected has been
    completed or substantially begun prior to the date the ban
    was imposed.
    As explained in our opinion in Illinois National
    Bank of Springfield
    v.
    EPA, #72—307,
    5 P03
    (Oct.
    3,
    1972),
    in which a number of the precedents are cit~and discussed,
    actual building construction prior to the ban indicates not
    only the commitment of substantial resources in good faith
    expectation that a connection may be made, but also the
    significant risk,
    as is alleged in the present case, of dam-
    age to the partly completed structures from vermin,
    vandals,
    and weather.
    Even in such cases, recognizing that each
    case depends upon its own peculiar facts, we have refused to
    hold that the timely commencement of construction in it-
    self will always suffice for a variance,
    for we must balance
    the harm from a denial of a connection against the serious-
    ness of the pollution threat in the event the connection is
    allowed.
    See Illinois National Bank v.
    EPA, cited above.
    Nevertheless,
    if buildings are actually built before
    a ban
    is imposed,
    a case can be made for granting a variance
    without hearing
    if the Agency suggests no risk of serious
    pollution in its recommendation.
    On the other hand, we have consistently distinguished
    sharply between actual construction of buildings and pre-
    paratory site development such as the installatiDn of streets
    and sewers.
    In the Wachta case a varaince was granted as
    to seven homes already constructed but denied as to other
    lots in which streets and sewers had been installed at
    considerable expense.
    Enjoyment of the fruits of preliminary
    expenditures, as we have observed,
    is not necessarily lost
    if immediate use of municipal sewers is denied;
    it may be
    merely postponed,
    since architectural plans, streets, and
    sewers may still he there when the ban is lifted:
    “Petitioner
    has expended approximately $60,000 for the purchase of the
    land and for development costs, none of which will be lost
    to
    it
    if
    it is obliged to wait until the sewage situation
    in Mattoon has been ameliorated.”
    Pyramid Mobile Estates,
    Inc.
    v.
    EPA, #71—154
    (Sept.
    16, 1971);
    see also Wagnon v.
    EPA,
    # 71—85,
    2 PCB 131
    (July
    26, 1971).
    5
    598

    —3—
    Although the
    Z~ency’srecommendation in the present
    case, evidently based upon allegations in the petition, con-
    cludes that “construction commenced prior to March
    31,
    1971,” it appears clear that the supporting information
    does not refer to the construction of the buildings them-
    selves.
    Although paragraph
    8 of the amended petition alleges
    that the
    contractor,
    in reliance on
    a building permit issued
    by the City of Waukegan,
    “moved onto the site in mid-January,
    1971,
    and commenced construction work,” the permit itself
    referred only to preparatory activities:
    “1.
    Earth moving
    2.
    Construction of on—site water retention basins
    and lakes
    3.
    All underground utilities including:
    (a)
    Electric
    (b)
    Storm Sewers
    (c)
    Sanitary Sewers
    (d)
    Water
    (e)
    Gas
    4.
    Seven building excavations
    5.
    Interior roadways
    6.
    Footings, piers and foundation walls for seven
    buildings.”
    Moreover,
    in its motion for judgment on the citizen complaint
    Cinnamon Creek state.s that it was after the sewer ban was
    imposed that it “installed the sewer connection and commenced
    construction”
    (Motion for Summary Judgment, paragraph
    6)
    We therefore find an absence of allegations sufficient to
    bring this case within the Wachta doctrine insofar as that
    case strongly favors the grant of variances for buildinqs
    under construction when the ban was ordered.
    The extensive
    allegations of hardship because of preliminary activities
    are similar
    to the hardships we found insufficient in the
    Wachta case,
    and we cannot determine without a hearing whether
    the actual hardships involved justify a varaince
    in light of
    the particular facts of the present cases,
    including the
    effect of the additional wastes upon the sewer in question.
    2.
    Actions Taken Since theSewer Ban.
    The next question is whether actions taken since the date
    of the sewer ban entitle Cinnamon Creek to relief without
    a
    hearing.
    The amended petition alleges, and the attached
    photograph
    (Exhibit U) confirms,
    that Cinnamon Creek has now
    “commenced erection of solid masonry walls,” although for
    how many buildings we cannot without testimony be certain.
    5
    599

    As noted above, had construction proceeded this far before
    the ban was imposed, we would grant the variance unless the
    result would be very serious pollution.
    But the relevant
    date for commencing construction
    is before, not after the
    ban is imposed.
    If
    the ban is to have any meaning, we must
    hold,
    and we have held,
    that in general one who commences
    construction after
    a connection ban is imposed does so at
    his peril; any hardships resulting from actions taken after
    that date must be regarded as self-inflicted and entitled to
    no considerations.
    To hold otherwise would put it in
    the power of any potential developer to avoid the ban simply
    by defying
    it.
    See Cook v.
    EPA, #72-178,
    5 PCB
    (Aug.
    29,
    1972)
    Cinnamon creek alleges without contradiction, and we
    accept as
    a fact,
    that it began construction and made the
    sewer connection only after requesting and receiving from the
    North Shore Sanitary District assurance that, because Cinnamon
    Creek held
    a permit to build the sewers that had been issued
    before the sewer ban,
    the ban did not apply to Cinnamon Creek.1
    In Glovka v. North Shore Sanitary District,
    471-269,
    3 PCB 647
    (Feb.
    17,
    1972)
    ,
    we explicitly held that the issuance of
    a
    permit
    prior to the imposition of the ban did not make the
    ban inapplicable:
    The March 31,
    1971 sewer ban prohibited sewer connections
    irrespective of any pre-existing permits granted by
    the
    State or the District itself.
    The order was unequivocal,
    plenary and without exception.
    The same reasoning applies to permits issued by the City of
    Waukegan.
    We further found that the District had acted de-
    liberately and inexcusably in giving an erroneous interpre-
    tation of the
    order:
    The Village of Lake Bluff, by its repeated inquiries
    of the District, was seeking sanction for what both
    undoubtedly knew violated the letter and spirit of the
    March
    31, 1971
    sewer ban.
    There
    is no question that the
    District took upon itself, unilaterally and in direct
    defiance of the Board’s order, jurisdiction
    to allow
    violation of the law by authorizing the Village of Lake
    Bluff
    to permit sewer connections.
    The District was penalized $5,000 and ordered to revoke all
    similar authorizations in Lake Bluff and to cause disconnection
    of any taps actually made pursuant to such authorizations.
    One exception was made to this sweeping order, and on
    this exception Cinnamon Creek places heavy reliance.
    Six
    building permits had been issued pursuant to District
    authorization to Nilles,
    Inc.,
    and two sewer connections
    for individual homes had been made by Nilles before the
    5
    600

    —5—
    Glovka case was filed.
    “Because of the apparent good faith
    reliance on the acts of the District and the Village,”
    the
    Board held,
    “connections made by Nilles,
    Inc. prior to ser-
    vice of this complaint are excepted from this order” of
    disconnection.
    Cinnamon Creek argues that its situation
    is similar and that, because Nilles was not required to dis-
    connect,
    it should be affirmatively authorized
    to use the
    sewer connection it made, presumably before the Glovka case
    was filed.
    The present case
    is by no means on all fours with that
    of Nilles.
    First, we did not hold that Nilles was free
    to discharge sewage through the connections that he had made;
    we held only that he was not required to incur the additional
    expense of making a physical disconnection.
    The issue was
    what remedy to order for violations proved in an enforce-
    ment case, not whether a variance should be granted to allow
    additional wastes to the treatment plant.
    Nilles’s right
    to discharge sewage was not settled one way or another
    by the Glovka decision.
    Second, we dealt in Nilles’s case
    with the
    connection of two homes to the sewer system;
    we deal
    here with seven buildings containing
    a total of 245 apart-
    ruents.
    Cinnamon Creek’s own estimate of the load to be
    added to the municipal sewer
    is 36,750 gallons per day.
    As we said in our opinion when we dismissed the original
    petition in this case,
    “the large number of apartments
    here involved (nearly 250)
    increases the hardship if
    a
    connection is denied and also the pollution if one is granted.”
    Cinnamon Creek Associates v. EPA, #72-340,
    5 PCB
    (Aug.
    22,
    1972.
    The possible adverse effect of the additional
    wastes contemplated by the present petition is orders of
    magnitude removed from that
    in Nilles;
    even if actual use
    of the Nilles connection had been authorized,
    the precedent
    would therefore not have been controlling.
    Furthermore, as also noted in our prior opinion, the
    large
    number
    of apartments here involved “may bring about
    a greater duty of inquiry into the legality of a connection,
    since we cannot delegate authority to local officials
    to under-
    mine or repeal our orders.”
    It is one thing to hold that the
    ordinary man in the street, or even the builder of two
    houses,
    is entitled to rely exclusively upon the opinion of
    municipal officials as to the meaning of an order issued by
    another governmental body, and can be in good faith in so
    doing.
    it is quite another to imagine that the developer
    of an apartment complex containing over two hundred units
    costing over four million dollars to build could be
    so
    naive.
    Cinnamon Creek could hardly have believed the District
    was in
    a position to give authoriative interpretations of
    our orders; ordinary prudence would seem to have suggested
    to men of good
    faith and judgment that the way to ascertain
    one’s rights before making extensive expenditures in con-
    structing such a huge project wasby filing
    a petition for
    5
    601

    —6—
    variance,
    as was done in the Wachta case.
    We cannot avoid the
    suspicion,
    on the
    facts presently before us, that Cinnamon
    Creek may have determined to push ahead with its project on the
    basis of assurances that would not have been found adequate by
    men of good faith and judgment with responsibility for such
    large sums of money,
    in hopes either that the ban would be lifted
    or reversed before construction was finished or that the Board
    would take pity and grant a variance after Cinnamon Creek had
    crawled out on
    a limb.
    If such was the case Cinnamon Creek pro-
    ceeded at its own risk and the hardships created by its subse-
    quent construction of walls that are in danger of collapsing
    are of its own making.
    We do not so find without giving the
    opportunity for proof at a hearing, but the conclusory
    allegation of
    “good faith” is not enough to dispel our doubts
    without a hearing.
    3.
    The Second Sewer Ban Decision.
    Thus Cinnamon Creek’s position,
    in this regard,
    is much
    like that with which we dealt in Cook v.
    EPA, #72-178,
    5 PCB
    (Aug.
    29,
    1972)
    ,
    in which
    a builder had proceeded
    to construct a home with knowledge that the sewer ban had been
    imposed, gambling on the possibility that it would,
    as pre-
    dicted by local officials,
    be lifted in the near future.
    In
    fact the ban was relaxed after construction began because of
    treatment plant improvements, but there as here the relaxation
    was of no help to the petitioner because it did not extend
    to sewers with inadequate capacity to carry the wastes to the
    treatment plant.
    Cook’s petition was denied on the ground
    that he had taken the risk that the ban would not be lifted and
    had lost;
    he and not the public should bear the burden of his
    erroneous prediction.
    What was true of
    a small individual
    builder like Cook, with only
    a single home to connect to the over-
    loaded sewer, would appear to be true in spades of
    a large
    developer like Connamon Creek:
    Having knowingly taken a calculated
    risk for business advantage,
    it should bear the loss when
    things go sour.
    In Bender v. EPA, 472—324,
    5 PCB
    (Oct.
    3,
    1972)
    ,
    we
    have taken another look at the Cook doctrine.
    Like Cook,
    Bender began construction knowing he could not connect un-
    til the ban was lifted;
    he admitted he assumed the risk that
    the treatment plants would not be improved to the Board’s
    satisfaction in time to permit us to relax the ban by the
    time he was ready to connect.
    He pointed out, however, that
    he did not anticipate
    at the time he began construction that
    the inadequacy of the sewer itself,
    of which he had no
    knowledge,
    would be taken by the Board as a reason for refusing
    to lift the ban insofar as it applied to his part of Waukegan.
    His position with respect to the sewer problem as contrasted
    with the treatment plant problem, was the same as if there
    had been no ban based upon the plant’s inadequacy; and we
    have allowed connections where construction began prior to
    5
    602

    —7—
    the imposition of a ban based on the inadequacy of the
    sewer
    itself.
    Illinois National Bank of Springfield v.
    EPA,
    ~72-3O7,
    5 PCB
    (Oct.
    3,
    1972)
    .
    Bender agreed he
    should be held
    to the risk he voluntarily assumed; but
    that risk,
    he said, was that the plant improvements would
    be delayed, not that an unforeseen sewer problem would
    arise.
    In the case of
    art individaul like Bender, constructing
    his own home in his spare time and contributing only a
    small amount of additional waste to the sewer, we were con-
    vinced by this argument, and the variance was granted.
    It is possible that Cinnamon Creek is in the same
    position as Bender,
    since it too allegedly began construction
    at a time when the sewer ban had been based exclusively
    upon treatment plant problems and since the continuation of
    the ban is based upon a later designation of the sewer it-
    self as inadequate.
    Whether a sophisticated developer with
    millions of dollars at stake and a potential addition of
    multiple thousands of gallons per day of waste should be
    given such benefit of the doubt in determining the precise
    scope of the risk assumed is an question we cannot presume
    to answer in the abstract without a hearing to determine the
    precise facts relating to Cinnamon Creek’s legitimate ex-
    pectations
    at the time and the effect of the discharge on
    the sewer.
    It is worthy of consideration that so
    to hold
    would place those who proceed in the face of an explicit
    sewer ban in more favorable position than those who
    acquiesce in the law.
    4.
    The Effect of
    the Discharge.
    As we have repeatedly held,
    it is an essential part
    of the petitioner’s case to plead and prove facts to demonstrate
    that the adverse effects of a variance grant will be great-
    ly outweighted by the hardships of
    a denial, see,
    e.g.,
    Decatur Sanitary Dist,
    v.
    EPA, #71—37,
    1 PCB 359
    (March
    22,
    1971),
    and our procedural rules are explicit in requiring
    a statement of
    the
    anticipated adverse effects of the
    discharge.
    PCB Regs.,
    Ch.
    1, Rule 401(a) (2)
    ,
    There is
    very little in the petition on this question, although an
    in-depth exploration of the extent to which admitting an
    additional 36,750 gpd to an already overloaded sewer would
    result in more raw sewage in streets and basements is an
    obviously critical part of the balance we must make in this
    case.
    See the
    extensive factual examination of this
    issue in Cook
    v.
    EPA, cited above.
    Cinnamon Creek’s
    allegations on this point revolve around the construction
    of
    a stormwater retention pond that allegedly will avoid
    any worsening of the present problem.
    The extent of that
    problem
    is not discussed.
    5
    603

    —8—
    Paragraph 13 of the amended petition recites that
    “petitioners constructed
    a large water retention basin,
    which functions to contain storm water during peak rain-
    fall periods, consisting
    of about seven acres
    .
    .
    .
    Exhibit C is a consulting engineers’ report indicating
    that this basin will provide retention capacity for “300
    of the additional run-off which will result from the develop-
    ment of this project area,”
    By reducing stormwater run-
    off from the area,
    it is opined, the basin s~ill“reduce
    flooding and the attendant hydraulic load on the City’s
    existing sanitary collection system in the vicinity of the
    development during rainstorms.”
    The report concludes on
    an optimistic note:
    We have no data available which would indicate hydraulic
    loads onthe existing sanitary collection system prior
    to the construction of the project and we know of
    no method of mathematical computation which would
    relate the
    improvement in the storm disposal system
    directly to a reduction of the hydraulic loading
    conditions
    in the sanitary collection system.
    However,
    it
    is not unreasonable,
    in our opinion,
    to assume
    that the volume of storm water not entering the sanitary
    collection system by virtue of the construction of the
    storm retention facilities will exceed the volume of
    additional dry weather flow that will be discharged
    to the system by this development.
    Having asserted that the only problem with the sewer is
    during wet weather,
    the report thus concludes that no
    harm will be done.
    On anything resembling close observation this promising
    conclusion, which is elevated to the status of fact in the
    petitioner’s allegations
    (amended petition,
    11 23(b)),
    reveals itself as no more than a blind guess.
    It should
    be noted at the outset that the basin will not retain
    the sewage generated by the apartments at Cinnamon Creek,
    as was proposed in Mars Devel. Corp.
    v.
    EPA,
    4 71-218,
    2 PCB 689
    (Oct.
    26,
    1971);
    it will retain only stormwater
    that would otherwise run off from the land.
    It
    is being
    built,
    as the report says,
    to capture
    “the additional run-
    off which will result from the development of this project
    area”—— presumably because the paving over of portions of
    the land will make storm runoff greater than it was before.
    The basin is to capture this additional runoff, and some
    of the
    original runoff,
    to aid in flood control.
    If the
    sew~ into which Cinnamon Creek has tapped were
    a combined
    sanitary and strom sewer into which all the captured runoff
    would otherwise have run, the retention of an amount of
    original runoff greater than the amount of sewage dis-
    charged from the project would demonstrate that the net
    effect of construction would be a reduction in the
    5
    604

    —9—
    frequency and quantity of overflows,
    though not of their
    pollutant concentration.
    But there is no such allegation.
    The apartments are to discharge into what the report describes
    as a “sanitary collection system,” not a combined one, and
    the report makes clear the inapplicability of such a sim-
    ple formula
    to the present case.
    It is plainly implied that
    the storm water is expected to go elsewhere,
    and the estimated
    effect of
    the
    retention basin is based upon assumptions
    as to the present degree of accidental infiltration of a
    certain portion of stormwater from this local
    area into
    sewers meant to carry only domestic wastes.
    No facts whatever
    are given to substantiate the “assumption,” which so happily
    coincides with the builder’s wishes, that the reduction in
    infiltration will more than counterbalance the added wastes
    from the apartments themselves.
    For all that is alleged
    or proved,
    the overload problem might be caused entirely
    by illegal connections of stormwater sources directly to
    the sanitary sewer elsewhere in Waukegan, and if that were
    the case stormwater retention at Cinnamon Creek would be of
    no value at all insofar as the sanitary sewer problem is
    concerned.
    Cf. Illinois National Bank of Springfield
    v.
    EPA,
    *72—300,
    5 PCB
    (Oct.
    3,
    1972)
    We think Cinnamon Creek should he given the opportunity
    to prove its contention that no significant net wet-weather
    load would be placed on the sanitary sewer if the variance
    were granted, but we do not have adequate information before
    us today to support either that claim or the clearly relevant
    allegation, see Illinois National Bank of Springfield v.
    EPA, #72—300,
    5 PCB
    (Oct.
    3,
    1972)
    ,
    that the city’s program
    for sewer improvements will soon relieve the situation.
    5.
    Conclusion.
    We are asked to dispense with
    a hearing on the ground
    that time
    is of the essence.
    We have stated at length why
    we believe we do not have the facts to enable us to render
    an informed decision without hearing.
    We think the impor-
    tance of an early decision is
    a consideration that should
    have been taken into account by Cinnamon Creek itself in
    determining when to file its variance petition.
    The sewer
    ban order was entered a year and a half ago,
    the decision to
    continue the ban for overloaded sewers
    in January~ofthis
    year,
    the Glovka decision making clear that a prior permit
    did not afford an exception in February, and the Agency’s
    designation of the inadequate sewers was made in April.
    Yet
    Cinnamon Creek, which now is in such a hurry for a decision,
    waited until August to file its first variance petition.
    Had
    time really been of the essence, Cinnamon Creek could have
    come before us some time ago,
    so that we would have had time
    to ascertain all the relevant, facts before acting on the
    petition.
    5
    605

    —10—
    Instead these proceedings have been pressed at
    the last minute,. according to the petitioner’s own
    estimate,
    in great haste.
    The first response to our
    dismissal for inadequate information,
    on grounds that had
    been made clear in decisions dating back for five months
    (e.g., Robert E. Nilles,
    Inc.
    v.
    EPA,
    #72—97,
    4 PCB 123
    (March 28,
    1972)
    ,
    was the filing of a citizen suit, followed
    within three days by a motion for summary judgment to which
    a response admitting the facts as Cinnamon Creek alleged
    them was filed on the very same day.
    At the developer’s request
    we sought and obtained the Agency’s views within fifteen days,
    and the telephoned, cryptic recommendation we received shows
    the haste with which the Agency was forced to work in preparing
    its response.
    Cinnamon Creek’s counsel appeared before the Board on
    September 26 to urge an immediate decision.
    Informed that the
    law requires passage of
    21 days for citizen comment on the
    variance petition, he offered to withdraw it to enable the
    Board to pass immediately on the issue as raised by the
    acquiescent citizen’s complaint.
    We could not grant Cinnamon Creek the relief it seeks
    on the
    basis of the citizen complaint alone.
    Should we re-
    fuse to order disconnection as requested by the complainant,
    that would not give
    Cinnamon Creek the right
    to use its
    connection, for reasons stated above.
    Nor are there sufficient
    allegations, much less proof, in the.citizen case to indicate
    the hardships claimed to justify the grant of a variance;
    there is only reliance on the Nilles case, which we have held
    cannot help Cinnamon Creek without the proof of additional
    facts at a hearing.
    More important,
    the requirement that we allow
    21 days
    for public comment in variance cases expresses an important
    policy that we not allow deviation from pollution require-
    ments without giving the affected public the right to have
    its say.
    That policy is not lightly to be undermined by
    disposing of the same issues on the basis of
    a friendly
    citizen suit that frustrates the spirit of the rule.
    We
    have already received a comment from the Lake County Health
    Department of possible adverse effects if the connection is
    approved.
    We view this as a statement in opposition to the
    variance, which requires us to hold
    a public hearing under
    section 37 of the Act.
    We think it would be in disregard
    of our obligation under that section to moot the hearing by
    passing on the same issue in the meantime on the basis of
    the citizen complaint.
    5
    606

    —11—
    Finally, although the developer’s factual allegations
    are conveniently admitted by the cooperative Mr.
    Simpson,
    that is by no means the same as having them proved in a
    public hearing.
    Even when the Environmental Protection
    Agency is complainant, our rules require that the Board
    independently evaluate the case rather than blindly accepting
    settlements agreed to by the parties.
    PCB Regs, Ch.
    1,
    Rule 333;
    see GAF Corp.
    v.
    EPA, #71-11,
    5 PCB
    (Oct.
    3,
    1972)
    .
    We can do no less when a citizen is complainant,
    lest a procedure intended to provide for increased enforce-
    ment against polluters be perverted into an instrument for
    whitewashing them.
    For us to accept stipulations uncritically
    in such cases would enable anyone engaged in illegal
    activities
    to insulate himself from prosecution by find-
    ing a complacent citizen to institute a paper complaint
    against him and then to admit away all the facts.
    Be-
    cause of the importance of the present case,
    the haste
    with which it has been pursued, the remarkable harmony
    of action between complainant and respondent, and the
    inadequacy of the agreed facts
    to enable us to make
    a reasoned decision, we think Cinnamon Creek must be put
    to its proof.
    The motion for emergency disposition is hereby
    denied and the two cases are consolidated for a prompt
    hearing.
    Under the authority of EPA v. City of Spring-
    field,
    #70-9,
    PCB_
    (May 26, 1971), we think the
    21-day notice ~T~en for the hearing initially set on the
    citizen complaint satisfies the statutory requirement of
    notice to allow time for citizens to prepare comments
    on the responsive variance petition.
    A hearing may be
    held upon brief public notice of time and place.
    I, Christan Moffett,
    Clerk of the Pollution Control Board,
    certify
    tha’~.the Board adopted the above Opinion
    & Order
    this
    ..S ~
    day of October, 1972, by~avote of
    -.~..
    ~
    (~.
    ~
    !~
    ~,I
    ;//~
    ~
    5
    607

    Back to top