ILLINOIS POLLUTION CONTROL BOARD
November
11,
1971
MT.
CARMEL PUBLIC UTILITY
v.
)
PCB 71—15R
ENVIRONMENTAL PROTECTION AGENCY
Messrs.
Albert A.
Scriber, Albert A.
~arnhard,
and Leonard M.
Koger,
Jr.,
appearing
for
Mt.
Carmel
Public
Utility
Mr. Larry
Ft. Eaton,
Special Assistant Attorney General!
and
Mr. Delbert D. Haschemeyer,
Attorney, appearing for
the
Environmental Protection Agency
Opinion of
the Board
(by Mr.
Kissel):
Mt.
Carmel Public Utility Company
(the
“Utility’)
,
a privately
owned utility which distributes natural gas and electricity to
a
service area in and around
Mt.
Carmel,
Illinois,
filed
a
“Motion
for
Re—Hearing on Petition for Varianceu
with
the Board on July
16,
1971.
The Utility sought
a re-hearing of
a previous case in which the
Board denied the Utility’s Petition for variance,
Mt. Carmel Public
Utility Company
v.
Environmental Protection
:~oency, P03
71-15,
dated April
14,
1971.
The Utility sought permission-in
that case
to use coal—fired boilers over
a period of the next ten years, when
they will
be
phased out.
The Board denied the request generally
on the basis that Board policy is such that one who discharges
in
excess of the regulations,
as
was the
case with
the Utility’s emis-
sions
from the coal-fired boilers,
that person must have
a program
for the installation
of control equipment, where such equipment
is
technically feasible, before
the Board will grant
any variances.
Apparently,
as
a result of that decision,
the Utility has
now come
up
with
a program to halt the emissions from
the coal fired boilers.
A hearing was held on
the Motion for Re-Hearing on September
17,
1971
in Mt. Carmel,
Illinois before Medard Narko, Hearing Officer.
The
Utility
has
three
coal—fired
boilers
which
are
in
omera-
tion
~-
Units
1,
4
and
5.
In
its
new
plan
the
Utility
proposes
to
convert
Boiler
#5
to
an
oil-fired
unit
by
June
30,
.1973,
and
to
burn
#2
oil
in
that
converted
unit.
Boilers
#1
and
#4
will
continue
to
be
used
until
June
of
1974
when
an
additional
transmission
line
will
be
installed
between
the
Mt.
Carmel
facility
and
a
generating
station of Central Illinois Public Service Company
(CIPCo).
After
3
—
25
that Boilers
#1 and
#4 will,
according
to the company plan,
be kept
on cold standby and will
only be used if there is
a failure in the
Utility’s ability to supply power to its customers.
The Agency’s
recommendation given at the hearing was that the Utility be required
to begin installation of
the conversion of Boiler #5 on October
1,
1972,
rather
than January
1,
l97~, as suggested by the Utility,
and that the preliminary work,
like piping and installation
of
a
tank,
be started immediately.
Since the last hearing,
a number of events have occurred, but
certainly the
one with
the most impact on the Utility’s operations
is
the signed contract with the Ayrshire Coal Company which
is con-
structing
a coal mine near Keensburg,
Illinois.
This contract
provides
that the Utility shall provide the mine with electric
power for
the next ten years
(at least),
the present length of
the agreement.
The mine will be completely constructed by December
of
1972 and its
need
for electrical power will reach 10,000 kilo-
watts within
18 months after the completion of construction.
Dur-
ing
the construction period the mine will
use about 1500 kilowatts,
which will be supplied by the Utility.
In order
to be able to get
the anticipated demand to the mine,
the Utility
is planning to con-
struct
a
69
NV line between the Mt. Carmel station and
the Village
of Keensburg.
This
line when completed will
be able
to deliver
the estimated peak demand of the mine which,
as stated,
is antici-
pated
to be 10,000 kilowatts by
the middle of
1974.
The Utility
already has
a 12.4
NV line between the
Mt.
Carmel station and
Keensburq
which
will
be
able
to
deliver
the
needed
electric
power
to
the mine during the construction period.
The
69
NV line to
Keen~burg will be completed
by January,
1973 and will
cost $240,000.
In addition to
the
69 NV line
to Keensburg,
the Utility is
also planning to construct
a 138
NV line from Keensburg to Albion
where CIUCo has
a generating station.
By
the addition of this
line,
which will be completed by June,
1974,
the Utility will be able to
buy power from CIPC0
for all of
its customers,
including
the mine.
The Utility has not yet acquired the
right--of-way
for
this line,
but it e:~pectscompletion
by 1974 at
a total cost
of $260,000.
Also,
when
this line
is
completed,
the Utility says Boilers
*1
ai~d #4 will
no longer be needed except on
an emergency basis
(“cold standby”)
-
Presently,
the Utility buys
power
from CIPC0
and this
is
trans—
mitted over
a 69
NV between
Mt.
Carmel and Lawrenceville.
This line,
plus Boilers
#1
and
#4,
is
sufficient
to supply the power necessary
for the customers
(including the mine)
of the Utility during the time
when Boiler #5
is
down
for
the
conversion.
Now, we must look
at the program suggested by
the Utility.
First,
the Utility plans to shut Boiler
#5 down
in January,
1973,
for
the
conversion
of
that
unit from
a coal-fired furnace to
a
boiler
which
is
capable
of
burninc~ oil
and
gas.
The
cost
of
this
conversion will be $180,000 and will be commieted by
the
Utility’s
contractor,
Babcock and wilcox,
by June
30,
1973.
There seems
to
be
no quarrel with
the amount of time necessary for the conversion,
that
is,
six months from the
time when Boiler
#5
is shut down,
but the Agency did make
the
point,
and recommendation,
that perhaps
Boiler
#5 could be shut down
in
October,
1972,
rather
than
January,
1973.
The Utility admitted
that it could buy sufficient power
from CIPC0 to replace the amount generated by Boiler
#5, but at an
increased cost
if the power
is purchased in October,
rather than
January.
We think
the slight cost of buying
this power earlier
and thereby starting
the conversion earlier is worth
it.
The
Utility
has,
as
the previous record points out
(and this record
does too), been financially
successful.
Total income
for the year
ending June
30,
1971, was almost $180,000.
True,there has been
a
reducing income for t~e last few veers, but
the record
is also
clear
that there has been no increase
in rates
for some time.
The
Utility can afford the slight cost for buying
the additional mower
earlier
so that the peopl2
of Mt.
Carmel
will have three less
months
of excessive particulates
in
the air
as
a result of
the coal—
fired
unit.
We will, therefore,
rec~uirethat the Utility shut down
Boiler
#5
on October
1,
1972 and complete the conversion by March
30,
1973,
rather than June
30,
1973.
The second phase of the proJram is the completion of the
69
NV
line between Mt. Carmel
and
Keensburg.
The schedule
for completion
is January
1973,
and this
seems
from
the testimony the best that the
Utility can do.
The third phase of the program
is
the construction
of the
138
K’! line between Keensburg
and Albion,
connecting the CIPCo plant
to the mine and
the Mt.
CarmeJ
plant.
The
line
is
to be completed
by the middle of
1974, which seems
a
long way
off.
Since
the
Utility
is committed
~
the construction
of this
line,
it would
seem that
they should proceed “post haste” and complete
it.
We recog-
nize that
the
right-of-ne:
oust
be
established
and that the Utility
must
work
closely
‘b
ti:
Cc
in
having
the
line
constructed.
But
we
think
that
it can do built
faster
and
therefore
will
require
that
the Utility exercise
every
effort
to complete the line before June
of 1974.
We wi1
require
reports
from the Utility to both the
Board
and
the
Agency
to
advise
both
groups
of
the
progress
being
made
to
speed
up
construction
Of
this
line.
The
fourth
phase
of
the
Utility’s
program
revolves
around
Boilers
#1
and
#4.
The
Utility
does
not
plan
to
put any control
equipment
on these two remaining boilers.
The plan is to keep
them
in
full
operation
until
the
138
NV line
is
installed and
operating
which,
the
Utility
has
said,
will
not
be
until
June,
1974,
but
which
this
Board
has
required
the Utility to make every
effort
to
complete
earlier.
Thus,
if
the
138
NV
line
is completed
earlier,
Boilers
#1
and
#4
will
be
taken
off
the
line
earlier.
We
agree
that
from
the
testimony
Boilers
#1 and
#4
are necessary to
operate
until
the
138
Ky
line
is
completed,
which
at
the
latest
will
be
June,
1974.
The
concern,
however,
of
the
Board
is
the
Utility’s
use
of
the
boilers
after
the
138
K’!
line
is
completed.
The Utility plans to keep
the boilers on “cold standby”
for
an
indefinite
period
of
time.
This
means
that
the
boilers
will
be
used
in
case
the
Utility
does
not
have
adequate
power,
either
produced or purchasable,
to supply the demands of its customers.
It is possible,
then, under
the Utility’s program that the boilers
will be
used after June of 1974 without any emission controls.
The Utility did state that in
1974 it
“may decide” to install
control equipment
on the boilers.
However,
this Board
feels that
if the boilers are to be operated after June
30,
1974,
or when
the
138
NV
line is completed, whichever occurs first,
for
reason,
including
“cold
standby”,
the
boilers
should
be
operated
so
as not to violate the regulations
governing
the
control
of
air
pollution.
Based upon previous testimony,
this means that control
equipment must be installed and operating at that time to reduce
the
particulate
emissions.
Thus,
we
do
not
prohibit
.the omeration
of the boilers after the aforementioned dates, but we do prohibit
the
illegal operation of those boilers at that
time,
The Utility
has adequate time between now and
1974 to plan
for the installa-
tion of control equipment
if
the Utility feels
that operation of
the boilers, even as reserves,
is
necessary
after
1974.
Thus,
the Utility will be granted
a variance subject to the
conditions
detailed
above.
One
other
point
must
be
dealt
with.
The
Utility
has
con-
sistently taken the position that
its
boilers
do
not
violate
the
existing particulate emission standard.
We
heard this
in the first
variance case
and said
that the Utility did,
in fact,
violate the
regulations.
Again
in
this
proceeding,
the Utility attempted to
prove
that
it
was
not
violating
the
particulate
emission
standard.
The hearing officer denied
the Utility the right
to produce such
evidence and we agree with the hearing officer’s ruling.
The
Utility had already had its opportunity
to raise
the question before,
3
—
28
and we disagreed with
it at that
time.
It was not a proper sub-
ject of this hearing.
The Utility sought
a variance
so that it
could violate the
law.
If
it truly believed that it was not
violating
the regulations,
no variance would be necessary.
Ap-
parently,
the Utility doesn’t want to take
a chance.
This opinion constitutes
the Board’s findings of fact and
conclusions of law.
ORDER
Based upon the testimony and exhibits in the record,
the
Board hereby orders that
the variance requested by
the Utility be
and
is hereby granted from the particulate emission standards and
Section
9(a)
of
the Environmental Protection Act,
subject to the
following terms
and conditions:
1.
This variance shall continue
for
a period of one year
from this date.
If the Utility wants
a continuance
of this variance
it shall file
a petition for renewal
of the variance within ninety
(90)
days prior
to the
date
the variance expires.
The Board may authorize
a
hearing on that supplemental petition and shall make
such further order as it deems necessary at that time.
2.
The Utility shall proceed with
the following program:
(a)
The Utility shall complete the conversion
of Boiler #5 from
a coal-fired boiler to
a
boiler fired by oil
and natural gas by
March
30,
1973;
(b)
The Utility shall complete the
69
K’! line
from Mt.
Carmel to Keensburg by January,
1973;
(c)
The Utility shall exert every effort to com-
plete
the 138
K’! line
from Keensburg to
Albion before June,
1974.
In that respect
the Utility shall
file quarterly reports
with
the Board and
the Agency, beginning on
December
1,
1971, which reports shall detail
the efforts made by
the Utility to expedite
the completion of the 138
K’! line herein des-
cribed;
and
3—29
(d)
The Utility shall not operate Boilers
#1
and
#4
in
violation
of
the
particulate
regulations after the installation of the
138
K’! line referred to
in paragraph
4,
or June
30, 1974, whichever occurs
first.
3.
The
Utility
shall
post
a
bond
in
a form approved by
the
Agency
to
guarantee
performance
of
the
conditions
of the granting of this variance.
Said bond shall be
in the amount of $500,000.
4.
Failure
to
comply
with
any
of
the
conditions
of
this
variance shall result in the revocation of the grant
of this variance.
I,
Christan Moffett, Acting Clerk of
the Illinois Pollution
Control Board, certify that
the Board adopted the above Opinion
and Order on
this
~/
day
of November,
1971.
~
~,
Christan Moffett,
Acting
Clerk
3~)