ILLINOIS POLLUTION CONTROL BOARD
    October
    3,
    1972
    SOUTH SIDE FOUNDRY COMPANY
    )
    #72—105
    v.
    ENVIRONMENTAL PROTECTION AGENCY
    ENVIRONMENTAL PROTECTION AGENCY
    #72-187
    v.
    SOUTH SIDE FOUNDRY COMPANY
    )
    MR. PRESCOTT E.
    BLOOM, SPECIAL ASSISTANT ATTORNEY
    GENERAL,
    ON
    BEHALF OF ENVIRONMENTAL PROTECTION AGENCY
    MR. RICHARD J.
    TROY,
    ON BEHALF OF SOUTH SIDE FOUNDRY
    OPINION AND ORDER OF THE BOARD
    (BY MR.
    LAWTON):
    On March
    21,
    1972,
    in Case #72—105, petition was filed by
    South Side Foundry Company
    (referred
    to throughout this Opinion
    as
    “petitioner”)
    to permit operation of its Peoria foundry in ex-
    cess of permissible particulate limits as provided by Regulation.
    The Agency recommended that the variance be denied,
    or if granted,
    that it be subject to the installation of spark arresters,
    the
    submission of
    a firm compliance program within thirty days of the
    Board’s decision and the posting of a performance bond.
    Waiver
    of the 90—day statutory provision for the rendition of a variance
    order has been received.
    On May 1,
    1972,
    in Case #72-187, complaint was filed by the
    Environmental Protection Agency against South Side Foundry Company
    alleging that on or about July
    21 and July 22, 1971 and between
    January 13, 1972 and the date of filing of the complaint, Peti-
    tioner caused,
    threatened or allowed the discharge of particulate
    matter, gaseous emissions and other contaminants,
    in violation
    of Section 9(a)
    of the Act and Rule 2-2.54 of the Rules and Regu-
    lations Governing the Control of Air Pollution
    (Air Rules), and
    violated Rules
    2-2.3 and 2-2.4,
    in failing to file a Letter of
    Intent and Air Contaminant Emission Reduction Program.
    Penalties
    in the maximum statutory amount are sought.
    5
    563

    On motion of the Agency,
    the two proceedings were consolidated
    by order of the Hearing Officer.
    Hearing was held on August 28,
    1972.
    Petitioner operates a gray iron metal casting plant in Peoria
    employing 25 people.
    Melting is done in a four-ton per hour,
    36” diameter cupola, averaging approximately seven tons per day.
    According to the variance petition, South Side Foundry melts
    1,680 tons of metal per year,
    uses 8,400 tons of sand annually
    in its molding operation and emits 146 pounds per day of parti-
    culates, (82 pounds per day of aerosols
    defined by petitioner as
    containing particulates under
    50 microns,
    and 64 pounds per day
    of suspendable material~.In addition,
    1,930 pounds of carbon
    monoxide are emitted daily.
    All of the foregoing emissions result
    from a seven ton per day liquid iron production purportedly accom-
    plished during a two-hour per day maximum melting period.
    Petitioner has no proposed specific emission control program
    to bring itself into compliance with the relevant statutory and
    regulatory provisions.
    It indicates that it is giving consideration
    to four alternative abatement processes:
    a wet cap attachment
    with baghouse for collecting particulates with afterburners to
    reduce CO emissions,
    a Venturi—type collector and afterburner,
    electric induction-type melters or high efficiency—type gas or
    oil reverbatory melters.
    Petitioner alleges that 15 months will be needed for studies,
    development of casting criteria, choice of method to be pursued,
    ordering of equipment and installation.
    Neither in its petition
    nor in the course of the hearing has petitioner indicated which
    method,
    if any,
    it anticipates adopting,
    or what progress has been
    made in developing
    a program
    of compliance, notwithstanding a period
    of five months having elapsed between the filing of the variance
    petition and the hearing.
    The hearing brought out that the foundry
    was a family—owned business which enjoyed
    a successful operation
    for many years prior to 1960,
    at which time the foundry became
    the victim of severe mismanagement, which it appears to have re-
    mained subject to until September of 1971, when management and owner-
    ship changes took place,
    and petitioner again resumed operation on
    a profitable basis.
    Mary L. McCarthy testified as a witness for petitioner
    (R.8),
    She has been president of South Side Foundry Company since July of
    1971.
    The business had previously been operated by her father and
    upon his death in 1954,
    by her three brothers.
    Ownership of the
    business has been entirely within the McCarthy family and included
    Mary L. McCarthy as a part owner prior
    to her designation as cor-
    poration president.
    Since taking office,
    Miss Mccarthy has sought
    the aid of various professionals in endeavoring to remedy the un-
    satisfactory operation of the plant, but no definitive program of
    pollution control has been embarked upon or as yet proposed.
    This
    —2—
    5—
    664

    witness testified to the mismanagement of the company by her
    brothers,
    including the payment of exorbitant salaries and un-
    authorized diversion of funds.
    Since Miss McCarthy’s assumption
    of the corporate presidency,
    this situation has ceased, the
    company
    is presently solvent and in good standing with the Illi-
    nois Secretary of State.
    Walter E. Walz testified on behalf of South Side Foundry
    Company
    (R.27), describing the condition of the foundry as of
    May,
    1972 as having reached
    “the point of no return”
    (R.30).
    He described the virtual absence of maintenance and housekeeping
    procedures and the general sioppy way in which the foundry had
    been operated.
    In recent months,
    some improvement has re-
    sulted from gas torch firing of the cupola in lieu of the
    previous use of wood firing
    (R..35).
    This witness discussed several
    of the emission control alternatives proposed in the variance peti-
    tion.
    The wet cap attachment to the baghouse
    (R.46,
    Pet.
    Ex.
    2), a
    Brown Bovari Coreless-type Melting Furnace
    (R.52,
    Pet. Ex.
    3)
    and
    a smaller coreless type electric furnace
    (R.55, Pet. Ex.
    4) were
    described in terms of operation and installation.
    According to
    Waiz,
    all proposals would require at least one year for order,
    delivery and installation
    (R.59).
    James
    F.
    Powell, metallurgist consultant employed by petition-
    er, testified on its behalf.
    He stated that no spark arrester had
    been installed in the stack and that sparks were emitted on occa-
    sion from the cupola operation.
    The foregoing was the extent of petitioner’s case in support
    of its variance petition.
    No representation was made that any
    specific abatement program would be pursued or what time schedule
    of installation petitioner anticipated it would follow in order to
    bring its operation into compliance.
    Witnesses for the Environmental Protection Agency,
    in support
    of the enforcement action and in opposition to the variance allow-
    ance, included John W.
    Tomic
    (R.61) who testified that he was the
    operator of a gas station approximately 125 feet from petitioner’s
    foundry
    (R.65),
    that he had observed sparks and smoke emanating
    from the foundry stack between July of
    1970 and July of 1971
    (R.64)
    and that he refrained from filling automobile gas tanks with gaso-
    line during periods when sparks were observed for fear that an explo-
    sion might result
    (R.66),
    During
    .a period of several months prior
    to the hearing, this witness observed similar emissions approximate—
    ly four times per month when particulates dropped on the customer’s
    cars
    (R.67)
    .
    Some improvement was noted shortly prior to the hear-
    ing.
    —3—
    5
    565

    Douglas Winters testified on behalf of the Agency
    (R.
    93).
    He operated a tavern in the vicinity of the foundry, which burned
    down on October 27,
    1971, possibly as a result of sparks emitted
    from petitioner’s operation.
    Exhibits introduced by the Agency included pictures of peti-
    tioner’s stack and alleged emissions from it, ~thich~e~renot
    particularly helpful.
    Agency Exhibit
    7 contains a report of
    inspection of petitioner’s foundry made on April
    3,
    1972 by
    R.
    C. Wennmacher, an agency employee.
    On the basis of standard
    emission factors, computed on a seven—ton per day melt,
    emissions
    were computed at 14.8 pounds per hour against an allowable emis-
    sion maximum of 3.54 pounds per hour.
    This exhibit was received
    without objection and no effort was made to refute it
    (R.104).
    Petitioner’s
    principal defense to the enforcement action was
    the incompetent operation existing prior to Mary McCarthy’s selec-
    tion as corporate president, which she now appears endeavoring to
    improve.
    However,
    it will be noted that notwithstanding Miss Mc-
    Carthy’s assumption of control in 1971,
    and her laudable desire
    to improve
    a bad situation,
    nothing has been done to date by way
    of a definitive program to bring petitioner’s operation into
    compliance, nor has anything by way of defense or extenuating
    circumstances been submitted.
    While the evidence of nuisance and
    particulate violations is somewhat meager, petitioner concedes
    that it has failed to file an approved Air Contaminant Emission
    Reduction Program and has operated for many years without emission
    control equipment of any kind
    (R.22,
    106).
    Likewise, a nuisance
    on the community has been demonstrated resulting from spark and
    particulate emissions affecting the comfort and safety of persons
    and property in the vicinity of the foundry.
    The Agency’s contention that sparks from petitioner’s operation
    may have caused the fire destroying
    a nearby tavern is not complete-
    ly convincing on the state of the record.
    However, there is no
    question that sparks from the foundry have been emitted over a
    long period of time and the company does agree to obtain a spark
    arrester which we will order installed within two weeks of the
    date0f this order.
    Violation of particulate regulations is not
    denied although evidence of specific numerical measurements mani-
    festing violation
    is found only with respect to the April
    3,
    1972
    inspection.
    While we are not unmindful of the efforts being made by Miss
    McCarthy in recent months to correct a bad situation, and are hope-
    ful that her present efforts will be rewarding,
    the
    record does not
    furnish us with any defense or adequate extenuating circumstances
    with respect to the enforcement action.
    —4—
    5
    566

    The
    Respondent
    in
    the
    enforcement
    action
    is
    a
    corporation
    which
    has
    been
    in existence throughout the entire period of the
    alleged offenses.
    There has been a continuity of family ownership
    and control.
    An assessment of penalty against the corporation
    would enable it to take such steps against its former officers
    and others as would be appropriate to receive reimbursement from
    those who have been guilty of the flagrant disregard of pollution
    control regulations.
    While Miss McCarthy has been a corporate
    officer for a relatively short time,
    she has been a stockholder
    for many years and the family has been in ownership throughout the
    entire period of violation.
    The factual situation in the present case is~not like that in
    Environmental Protection Agency v. Lindgren Foundry Co.,
    #70-1,
    1 PCB 11, September 25,
    1970, where we declined to impose penal-
    ties because the corporation, at the time of trial, was owned by
    an entirely different entity than those who were responsible for
    the violations proven.
    Here,
    there has been continuity of owner-
    ship over the entire period of violation.
    With respect to petitioner’s petition for variance,
    the record
    is completely devoid of any substantive testimony or evi4ence
    enabling us to justify a grant of such relief.
    Petitioner has
    present~dno specific program nor plan of installation upon which
    even /alimited departure from the Regulations could be~premised.
    In Øücago-Dubuque Foundry Corporation v. Enviranme~ntalProtection
    Agency,
    #71—130,
    2 PCB 65,June
    28,
    1971; we denied a variance petition
    because of the absence of a definitive compliance program.
    We
    must do the same in the present case.
    On the state of the record, we assess a penalty in the amount
    of $3,000.00 for failure to submit a Letter of Intent and an Air
    Contaminant Emission Reduction Program
    (Rules 2—2.3 and 2-2.4)
    and
    for violation of particulate regulations
    (Rule 2-2.54)
    as well
    as the causing of air pollution in violation of Section 9(a)
    of
    the Environmental Protection Act.
    In arriving at this penalty figure,
    we have given consideration primarily to the company’s long and un-
    justified delay in taking action of any nature to abate its pollution-
    al discharge and its failure to have
    a program of compliance, at this
    late date.
    The
    original petition for variance was filed in March
    of 1972, over six months ago, yet nothing appears in the record to
    indicate that petitioner
    is any further along with an emission abate-
    ment program than it was when the original petition for variance
    was filed.
    We direct the company to submit a program of compliance within
    30 days of the date of this
    Order, expressly setting forth a method
    of abatement control which the company will pursue and the dates
    5
    567

    on which installation will be completed.
    We will require that a
    bond in the amount of $10,000.00 be filed’with the Environmental
    Protection Agency assuring that this program will be submitted.
    We order the installation of a spark arrester within two weeks of the
    date of
    this Order.
    We shall retain jurisdiction of this case for
    such other and further orders as may be appropriate in the pre-
    mises.
    This opinion constitutes the findings of fact and conclusions
    of law of the Board.
    IT
    IS
    THE
    ORDER of the Pollution Control Board:
    1.
    The petition for variance of South Side Foundry Company
    is denied.
    2.
    Penalty in the amount of $3,000.00
    is assessed against
    South Side Foundry Company for violations of Rules 2-2.3,
    2-2.4 and 2-2.54 of the Rules and Regulations Governing
    the Control of Air Pollution, because of South Side
    Foundry Company’s failure to file a Letter of Intention
    and Air Contaminant Emission Reduction Program, and ex-
    ceeding particulate regulations, all as provided in said
    Regulations and for the causing of air pollution in viola-
    tion of Section 9(a)
    of the Environmental Protection Act.
    Penalty payment by certified check or money order shall
    be made payable to the State of Illinois, Fiscal Services
    Division,
    Illinois Environmental Protection Agency,
    2200 Churchill Drive, Springfield,
    Illinois 62706.
    3.
    South Side Foundry Company shall submit to the Board and
    the Agency within
    30 days from the date of this Order,
    a
    specific program for Air Contaminant Emission Control and
    abatement of particulate and carbon monoxide emissions
    from its foundry operation, including a specific program
    of purchase, acquisition and installation of equipment,
    to
    bring its foundry operation into compliance with all rele-
    vant regulations and statutory provisions relative to the
    control of air pollution.
    4.
    South Side Foundry Company shall provide a bond in the
    amount of $10,000 payable to the Environmental Protection
    Agency and mailed to Fiscal Services Division, Illinois
    Environmental Protection Agency,
    2200 Churchill Drive,
    Springfield,
    Illinois 62706.
    The bond shall be in
    form
    satisfactory to the Agency and shall guarantee that the
    program of compliance required by paragr~ph3
    of this
    Order shall be submitted in the time provided and in the
    form required.
    —6—
    5
    568

    5.
    The
    company
    shall
    install
    a
    spark
    arrester
    in
    its
    stack
    preventing
    any
    emission
    of
    sparks
    into
    the
    atmosphere, within two weeks from the date hereof.
    6.
    The Board retains jurisdiction for such other and
    further orders as are appropriate, based upon the
    foregoing provisions of the Order.
    I~christan Moffett, Clerk of the Illinois Pollution Control Board,
    certify that the above Opinion and Order was a~optedon the
    ____
    day of
    ~-~~-~L_
    ,
    1972, by a vote of
    ~
    to
    C’
    ~
    —7—
    5
    569

    Back to top