1. 5 558
      2. F. Definition of Phase U:

ILLINOIS
POLLUTION
CONTROL
BOARD
October
3,
1972
ENVIRONMENTAL
PROTECTION
AGENCY
v.
)
PCB
72-54
UNION
CARBIDE
CORPORATION
OPINION
&
ORDER
OF
THE
BOARD
(by Mr.
Dumelle)
This
is
an
enforcement
action
filed
February
9,
1972
involving
the
allegation
that
Union
Carbide
Corporation
(Carbide),
in the
operation
of its
Films
-
Packaging
Division
in Bedford
Park,
caused
the
discharge
of
gaseous
emissions,
including
hydrogen
sulfide
and
carbon
disulfide,
thereby
causing
air
pollution
as
defined
in Section
3(b)
of
the
Environmental
Protec-
tion
Act
(Act)
in violation
of
Section
9(a) of
said
Act.
The
plant
produces
sausage
casings
and
other
products
composed
of
cellulose
and
empios
1, 300 people.
Hearings
were
first
held
on
May
23
and 24,
1972.
Another
hearing
was
held on
July
18..
lf)72
at which
time
the
parties
presented
a
Stipulation
and
Proposal
for
Settlement
to
the
public.
The hearing
officer1s
report
indicates
that
about
fifty
persons
were
in
attendance.
At
the
conclusion
of
the hearing
the representative
of
a local
citizens
organization
thanked
the parties
for
the
agreement.
The
hearing
was
concluded
with
applause.
No
transcript
was
made
of
the
July
18
hearing.
Carbide
purchased
the
1)1 ant
in
1956,
The
area
immediately
to the
north,
northwest
and
northeast
of
the
plant
is
predominantly
residential.
The
plant
operates
around
the
clock
every
day
of
the year.
The
emission
volume
from
the
two
140—foot
stacks
is
192, 000
cubic feet
per
minute.
The
most
recent
stacks
tests
(during
1971)
showed
the
concentrations
of hydrogen
sulfide
and
carbon
disulfide
to be
25
and
35 parts
per
million
respectively
at
73 percent
of
capacity.
Until
1964,
the
Bedford
Park
plant,
as
was
the practice
in the
industry,
vented
the
gaseous
emissions
of
each
process
line
thru
roof
vents
in the
immediate
vicinity
of each
line.
At
the
present
time
these
individual
emission
sources
are
brought
together
in a
central
ventilating
system
and
discharged
through
the
two aforementioned
140—foot
stacks.
This
system
was
completed
in early
1971
at
a
cost
of
$450,000.

—9—
In
the
fall
of
1970
Carbide
began
to
investigate
and
study
its
problem
on
its
own.
In
the
spring
of
1971
they hired
an independent
consultant.
In
July,
1971
the
consultant
rendered
a report
in
which
it
recommended
an
experimental
unit
to
test
the
carbon
adsorption
process
to remove
the
H7S
and
CS9.
The
unit
was
installed
by
January
1,
1972
but
proved
inadequate.
The
complaint
in
this
case
was
filed
in
February,
1972.
As
stated
above,
hearings
were
held
in
May
and
July,
1972.
In
June
and
July,
1972,
Carbide
conducted
experiments
with
an
alkaline
scrubbing
unit
for
applications
of
the
‘Cataban
chemical
reagent
process
and
also
caustic
scrubbing
using
different
caustic
concentrations.
Carbide
estimates
that
it
has
spent
S200,
000
since
the fall
of
1970
on research
and
development
of
treatment
alternatives,
Carbides
agreed
program
is
as
follows:
PHASE
I
A.
Subject
to
the
qualifications
herein
stated,
on or
before
June
1,
1973,
Carbide
agrees
to have
installed
and
commence
operation
of
a
scrubbing
unit
for
H2S
removal
capable
of utilizing
the
Cataban
process
which
will
have
capacity
for
a
gas
stream
of at least
60, 000
cubic feet
per
minute.
Car-
bide
agrees
to file
applications
for permits
for
this
unit
with
the
ERA
and all
other
governmental
pollution
control
agencies
asserting
jurisdiction
not
later
than
August
24,
1972,
assuming
the
Board
has
approved
this
stipulation
on
or
before
August
18.
If
such
approval
should
occur
after
August
18,
1972,
application
shall
be
made
not
later
than
on the
fourth
business
day
following
the
date
of
such
approval.
Carbide
agrees
to
diligently
pursue
such
applica-
tions.
In the
event
the
Board
does
not
approve
this
stipulation
until
after
August
18,
1982,
or
in the
event
all
necessary
permits
are
not
issued
within
a period
of
two
weeks
following
the
submission
of a
complete
permit
appiica~
tion,
or
both,
the time
for performance
under
this
Paragraph
A
shall
he
extended
for
a period
of time
identical
in length
to the
amount
of
each
such
delay.
A
complete
permit
application
is understood
to
include
information
required
by
law
to the
satisfaction
of
the
EPA.
B.
Carbide
agrees
to
construct
the
scrubbing
unit
so
that
it
shall
also
he
capable
of operating
as
an
alkaline
scrubber
utilizing
a
caustic
soLution
~of
a
concentration
of its
choice) or
some
other
alkaline
mediu:m
of
choice
and
that
it
shall
he
~n
option
of
Carbide
in
its
sole
discretiun
u~~n~nv:nce
operations
with
such
unit
utilizing
an
alkaline
scrubbing
process
oi
rather
than
the
Catahan
process,
Provided,
that
such
operation
sistent
with
the
provisions
of
the
EPA
permit
heretofore
mentionuL.
5
558

-3-
PHASE
U
C.
(1)
If the
Cataban
process
alone or
if the
Cataban
and another
process
is
utilized,
following the
start
up of the Phase
I unit,
there shall
be
a period
of no
more
than
four months
(“test period”)
in
which the per-
formance of the unit shall be
observed,
analyzed
and evaluated by responsible
engineering personnel of both parties.
A test period is
necessary because
this
will be the first
commercial
size
operation of its
kind using the
Cataban process
and
its
successful operation
cannot be assured.
(2)
If Carbide elects to use
an
alkaline
scrubbing process
at the
start
up
of the Phase
I unit,
it shall
have
a period of up to
3
months
in which
the performance of the unit shall
be observed,
analyzed
and
evaluated by
responsible
engineering
personnel of both parties.
Thereafter
it
shall
proceed
with Option
2
of Phase
II as
described
in
paragraph F(2) below.
D.
If the Cataban process is utilized,
at such time
during
said test
period as the EPA
and
the
Vice President-Engineering
of Carbid’s
Films-
Packaging
Division
shall
agree that the performance of the
unit
indicates
that it has
a practical
capability of removing
no less
than
75 percent of
the H9S
in
that
part of Carbide’s stream
which it has
the
capacity to
handle,
then
Carbide shall,
within
the time
specified
in
Paragraph
C below,
con-
struct either Option
1
or Option
2 of Phase
II as defined
In Paragraph F
below.
If
Carbide
contends
that
the operation is
not
practical,
ft will
supply
EPA
a
detailed written
statement of its
reasons,
specifying the
actual
or
projected costs
or test results
upon
which it relies.
E.
Should
the
Cataban process
not meet
the criteria
stated in
Paragraph
D above,
by the end oti the “test period,”
if
and only If,
at
that time there is
a
lawful,
technologically
and
economically reasonable
means available
for
disposal of the liquid
effluent
from
alkaline
scrubber
equipment of the capacity able to handle the entire
gas
stream
of Carbide,
Carbide
agrees to install
Option
2
of
Phase U
as described
in
Paragraph F(2)
herebelow.
It Is specifically
agreed that any disposal method
which
requires
discharge
Into the Metropolitan Sanftary
District
and which is found un-
acceptable to the District as
evidenced in
a
writing
by its
General Superin-
tendent shall
not be
deemed
available
for purposes
of this paragraph.
F.
Definition of
Phase
U:
(I)
Option
1:
Construction of scrubbing equipmeqt
capable of
utilizing the
Cataban process with
sufficient
capacity to remove
1125
from
the
remainder of the
entire gas
stream of Carbide,
the
entire system to
operate
at a
removal efficiency
not less
than the level
as determined
in
Paragraph D hereinabove.
5—569

-4-
(2)
Option
2:
Construction
of
alkaline
scrubbing
equipment,
not
designed
to
utilize
the
Cataban
process,
with
sufficient
capacity
to remove
H9S
from
the
remainder
of
the
entire
gas
stream
of Carbide,
all
alkaline
s6~rubbingequipment
to
operate
at
a removal
efficiency
of
not
less
than
90 percent.
(3)
In the
event
that
the
conditions
herein
specified
giving
rise
to
either
Option
1
or
Option
2
do
not
occur
in the time
herein
specified,
Carbide
agrees
to use
its
best
efforts
to find,
install,
and operate
an acceptable
treatment
method.
Such
efforts
shall
be
described
to
the
EPA
in
writing
no less
than
30
days
from
the
end of the test
period
and the progress
achieved
upon
the performance
of
such
efforts
shall
be reported
in writing
monthly
to
the
EPA by
Carbide.
G.
From the
date of
agreement
under
Paragraph
D,
or
Carbides
written
determination
within that
period
to adopt
Option
2
if it
chooses,
Carbide
shall,
within
three
weeks,
apply
for permits
for
the
Phase
Ii
equipment
from
the
EPA and all
other
governmental
pollution
control
agencies
asserting
jurisdiction.
Carbide
agrees
to
complete
all
Phase
II
construction
within
nine
months
from
the
date
all
necessary
permits
are
issued.
We
are troubled
by the
lack
of
assurance
of
an
adequate
program
for
removal
of
the
H25 nuisance.
Dr.
Howard
E,
Hesketh,
in
a letter
and
calculations
dated
August
24,
1972
points
out
that
his
assumed
nuisance
level
of
H7S
(0. 007 ppm)
will
be
just
met
at
75
H25
control
and atawind
speed
of
uT
mph
and neutral
stability.
Since
the
average
wind
speed
in the
Chicago
area
is
about
11
mph this
means
that
approximately
50
of the
time
or
more
wind
speeds
will
be
below
11
mph
and
ground
evel
H2S
consequently
above
0.
007 ppm.
Since
only half
of
the
wind
directions
will
cause
an
impingement
upon
residences
we
can
say that
the
nuisance
will
continue
to
exist
about
25
of
the time
(half
of a half),
Furthermore
nothing
is
being
done
about
carbon
disulfide
and in
fact
Dr.
Hesketh
points
out
that
this
pollutant
will
help
mask
the
H2S.
The
Agency
is
still
free,
of
course,
to
bring
an action
on
CS2
if
it
computes
dangerous
ground
level
concentrations
and
we
urge
that
they look
closely
at this
pollutant.
But
we
feel
that
75
control
of
112S
is better
than
no
control
as
is
the
present
situation.
And if the
Cataban
process
is
not
used~the
alternate
alkaline
scrubber
can
remove
up
to
90
of the
H2S.
Tt
is
further
stipulated
that
Carbide
will
post
a performance
bond
of
~1, 500. 000
and will
pay a
civil
penalty
not
to
exceed
$10,
000,

-5-
We
find
the
settlement
to
be
acceptable.
The
May transcripts
show
severe
air
pollution
and
annoyance
to
residents
but there
appears
to
have been
steady
progress
made
by
Carbide
during
the
past
two
years.
According
to
the
settlement
agreement,
there
will
be
even more
achievement
within
the
new
few
~‘ears.
We
also
understand
that
since
the
Cataban
process
is
somewhat
new,
the
progress
of
its
application
may proceed
less
quickly
than
desirable.
We
do,
however,
expect that
all
efforts
be
made
to
move
forward
as
rapidly
as
possible
under
the
circumstances.
Furthermore,
the
citizens
who
attended
the hearing
and who are
the
ones
most
directly
affected
by
the problem
seemed
to be pleased
with the
settlement.
This
opinion
constitutes
the
BoardTs
findings
of
facts
and
conclusions
of
law.
OR DER
i.
The
Stipulation
and
Proposal
for
Settlement
are
accepted.
2.
Carbide
shall
post
a performance
bond
of
$1, 500,
000 according
to
the
terms
of
said
Settlement.
3.
Carbide
shall
pay
to the
State
of Illinois
by
October
27,
1972
the
sum
of
$10,
000
as
a
civil
penalty.
Penalty
payment
by
certified
check
or
money
order
payable
to the
State
of
Illinois
shall
be made
to:
Fiscal
Services
i)ivision,
Illinois
Environmental
Protection
Agency,
2200
Churchill
Drive,
Springlield,
illinois
62706,
4,
This
order
does
not
protect
Carbide
from
action
by
the
Agency
if
the
program
still
results
in
air
pollution.
1,
Christan
L.
Moflett,
Clerk
of
the
Illinois
Pollution
Control
Board,
hereby
certify
the
above
Opinion
and Order
were
adopted
on
the ~
~
day of
October,
1 ~)72
by
a
vote
of
/)
:h~’~d~~
Christah
L.
Moffett,
~1~k
Illinois
Pollution
Control
Board
5
561

Back to top