ILLINOIS POLLUTION CONTROL BOARD
    October
    3,
    1972
    ENVIRONMENTAL PROTECTION AGENCY
    v.
    )
    72—50
    GAF CORPORATION
    Opinion
    of the Board
    (by Mr.
    Currie)
    The Agency’s complaint charged GAF with delays
    in the
    implementation of its Air Contaminant Emission Reduction
    Program, which required the installation of fume incineration
    systems on asphalt saturators and oxidizing stills at the
    company’s Joliet roofing plant by May 1972.
    The result,
    it was alleged, was emissions in excess of regulation limits
    (Rules and Regulations Governing the Control of Air Pollution,
    Rule
    3-3.111)
    and interference with the neighbors’ enjoy-
    ment of
    their property, constituting air pollution under
    ~ 9(a)
    of the Environmental Protection Act.
    On September
    25,
    1972, we received ~ stipulation and
    proposed settlement from the parties.
    The stipulation re-
    cited the Agency~scontentions that allowable particulate
    emissions
    from the oxidizing stills were 20.66 pounds per
    hour and actual emissions
    43.5, and both saturators and
    stills had “created a nuisance for the community
    by emitting asphalt odors which citizens have found
    objectionable and by emitting copious amounts of particu-
    late matter which interfere with normal lives of the local
    citizens.”
    GAF
    denied that it committed any violation.
    It
    is further recited
    that
    GAF
    is actively working to
    install the necessary fume incineration systems, which
    “are the most efficient asphalt fume abatement equipment
    presently available,” and which are “contemplated by GAF
    to abate
    the nuisance
    .
    *
    .
    and to bring
    the
    particulate
    emissions from the oxidizing stills into compliance with
    all presently enacted state air pollution regulations”--
    presumably including the newly tightened particulate re-
    gulations we adopted in April of this year
    for future corn—
    pliance
    (PCB Re~s.,Ch.
    2).
    The stipulation states that
    the
    “program is now well under way and proceeding according
    to
    the
    new
    schedule.”
    The company estimates the cost of
    control
    eguiprnerit
    at $1,555,802.
    5
    553

    —2—
    The proposed settlement is that GAF will complete the
    control installation and comply with all applicable laws
    and regulations by January 31, l973~will post a bond in the
    amount of the cost of the program; will file monthly pro-
    gress reports; will be permitted to operate under present
    conditions until the new deadline;
    and will pay a penalty
    of $15,000
    for its alleged delays.
    This agreement is contingent upon the Board’s approval
    of
    a second settlement relating to GAF’s petition for judicial
    review of our penalty order
    in #71-11,
    a water-pollution case
    involving the same plant;
    the water settlement was approved
    by
    the Board on September
    26,
    1972, for reasons stated in
    a separate opinion adopted today.
    GAF Corp.
    v.
    EPA,
    #71-il,
    5 PCB
    —,
    (Sept.
    26 and Oct.
    3,
    1972)
    Board procedure in evaluating proposed settlements is
    detailed in our procedural Rule 333
    (PCB Regs,
    Ch.
    1, Rule
    333)
    and in EPA v. City of Marion,
    #71—25,
    1 PCB 591
    (May 12,
    1971)
    ,
    in which we have made clear that, because of the
    Board’s role as an affirmative instrument for effectuating
    the policy of the Act, Board approval of the merits
    is recuisite
    for any settlement of a pending case.
    See also the dis-
    cussion in GAF Corp.
    v.
    EPA,
    #71-11,
    5 PCB
    ,
    decided to~-
    day.
    As we said in the Marion case,
    the statutory policy o~
    public participation in pollution cases requires that we
    make every reasonable effort to ascertain the views of the
    public upon settlements proposed by the Agency and the res~
    pondent.
    For the Agency is bdt the guardian of the public
    interest;
    it is the public itself that must put up with the
    results of our decisions.
    Consequently,
    as we said in
    Iowa-Illinois Gas
    & Electric Co., #72-216,
    5 PCB
    (August 22,
    1972)
    ,
    It has been our preferred procedure,
    even where a
    stipulation is reached on all factual issues, and in-
    deed even when the parties agree on a proposed dis-
    position,
    to require that the stipulation and proposal
    be presented publicly so that affected citizens have
    a meaningful opportunity to know the terms and to ex-
    press
    their views.
    But we have not felt ourselves bound to hold a hearing
    on a proposed settlement when strong countervailing con-
    siderations indicate we should not.
    In EPA v. Russell,
    Burdsail
    & Ward Bolt
    & Nut Co., #71-369,
    4 PCB 701
    (June
    27,
    1972), the Board noted the desirability of a
    settlement hearing hut decided the case without
    a hearing
    transcript, evidently believing that the completeness
    of
    the stipulation and the large amount of the agreed penalty
    (over $50,000)
    gave considerable assurance that the public
    interest
    would
    be
    protected,
    in light of the further
    delays
    that
    would
    have
    beee
    encountered
    had
    the
    Board
    at
    that
    date

    —3—
    scheduled
    a settlement hearing.
    In Howe
    v. Commonwealth
    Edison Co.,
    #71—333, 5 PCB
    (Sept.
    6,
    1972), the record
    reveals
    that the parties’ i~T~ia1agreement to settle was
    retracted upon notification that
    a hearing on the proposal
    would be necessary;
    the Board after examining the facts and the
    proposed remedy
    (a $2500 penalty for an accidental spillage
    of 150 gallons
    of oil into
    the Mississippi River) concluded
    that “no useful purpose would be served by insisting upon
    a hearing
    on the facts of this particular proceeding.”
    Our
    policy,
    therefore,
    is to hold settlement hearings unless
    extraordinary circumstances indicate otherwise.
    The present case
    is one of such extraordinary circum-
    stances.
    We received both this stipulation and that in
    the GAF water case on September 25, and each depended upon
    approval of the other.
    Oral argument in the water case be-
    fore the Appellate Court was set for October
    3,
    and we were
    informed that postponement
    of our decision would not only
    impose
    a considerable work burden upon attorneys in pre-
    paring for oral argument but would also entail
    a significant
    risk that our approval of the water settlement might come
    too late
    to forestall
    a court decision onthemerits.
    In
    other words,
    if we did not approve both settlements before
    October
    3 we might well lose the opportunity for settle-
    ment
    of
    the water case altogether.
    The desirability of accepting the water settlement is
    spelled out in our opinion in that case,
    adopted today.
    To
    have insisted upon
    a public hearing on the air settlement,
    with
    the requisite 21-days’ notice, would have put an end to
    the water
    settlement.
    Given this important adverse con-
    sequence of postponing the air decision,
    and given our
    evaluation of the air settlement itself, we concluded that
    we should proceed without a settlement hearing,
    and the
    air settlement was
    approved by
    a 4-1 vote,
    Mr. Dumelle
    dissenting,
    on September
    26,
    for reasons that follow.
    For purposes of passing upon the adequacy of the
    oroposal,
    we assume that the Agency’s allegations are true
    and that the Agency would prove them if a hearing on the
    rierits were held.
    These allegatibns would establish that
    ~AF has unjustifiably delayed by eight months the completion
    ut
    necessary pollution control facilities.
    The Agency agrees
    that the
    equipment
    that
    is
    being installed is the best
    available,
    and
    it does not contend
    that,
    given present
    facts
    the installation could
    be
    completed any faster than
    the coenanv
    has
    agreed to complete it.
    Shutting down the
    eLant, ~or
    reasons
    civen in our
    first
    opinion in the water
    case
    (OAF Corp.
    v.
    EPA,
    #71—11,
    1
    PCB
    481
    (April
    19,
    1971)),
    does not aepear a reasonable alternative.
    We are convinced
    the abatement program, seen from today’s vantage point,
    is
    an exec~pLaryone, and it
    is
    to be secured by an adequate bond.
    5
    555

    —4—
    The sole remaining question is the adequacy of the
    $15,000 penalty
    for the eight months’
    delay.
    As we said in
    the companion GAF water case,
    the setting of
    a money
    penalty is not an exact science.
    The penalty agreed upon
    here is in the same ball park as penalties for comparable
    delays
    in
    a
    number
    of
    other
    significant
    air—pollution
    cases.
    See,
    e.g., Marquette Cement Mfg.
    Co.
    v. EPA,
    #71-23,
    1 PCB 145
    (Jan.
    6,
    1971)
    ($10,000, which the opinion writer thought
    low,
    for over a year’s delay in controlling a large cement
    plant); Molex,
    Inc.
    v.
    EPA, #71-200,
    3 PCB 341(January
    6,
    1972)
    ($10,000 for a two-to-three-year delay in controlling
    substantial and offensive emissions from a plastics factory)
    Agrico Chemicals Co. v.
    EPA, #71—211,
    3 PCB 319
    (Dec.
    21,
    1971)
    (10,000
    for a year-and—a-half delay in controlling
    particulate emissions from
    a fertilizer plant).
    See also
    Spartan Printing Co.
    v.
    EPA,
    #71-19,
    2 PCB 19
    (June
    23,
    1971)
    ($10,000 for an 18—month delay
    in abating substantial water
    pollution
    violations
    from
    a
    large
    printing
    plant).
    Cases
    resulting
    in
    substantially
    higher
    penalties,
    by
    and
    large,
    have
    involved
    the
    failure
    to
    take
    any affirmative action
    to abate long-standing and serious nuisances down to the
    date of the complaint.1
    See Hemmerich v. Lloyd A. Fry
    Roofing Co., #71—33,
    2 PCB 581
    (Oct.
    14,
    1971) ($50,000)
    EPA
    V.
    Incinerator,
    Inc.,
    #71-69,
    2 PCB 505
    (September
    30,
    1971) ($25,000)
    .
    We conclude that,
    in view of the relatively
    brief delay in the present case,
    and the absence of Agency
    insistence that the emissions imposed an intolerable burden
    on the
    community,
    the agreed penalty of $15,000
    is a sub-
    stantial one that approximates what we would in all likeli-
    hood impose upon proof of all the violations alleged.
    In the interest of avoiding unnecessary litigation, we
    accept reasonable settlements agreed
    to by both parties.
    See EPA v. Granite City Steel,
    #70-34,
    4 PCB 457
    (May
    3,
    1972)
    *
    On these grounds the settlement was approved September
    26.
    Mr. Dumelle dissents,
    1.
    The
    special
    circumstances surrounding the $149,000
    penalty in the GAF water case,
    #71—li, and our acceptance
    of
    a $50,000 settlement, are described
    in today’s
    opinion
    in
    that
    case.
    I, Christan Moffett, Clerk of the Pollution Control Board,
    certify that the Board adopted the above Opinion this______
    day of October,
    1972,
    by
    a vote of__________
    5
    556

    Back to top