ILLINOIS POLLUTION CONTROL BOARD
October
3,
1972
ENVIRONMENTAL PROTECTION AGENCY
v.
)
72—50
GAF CORPORATION
Opinion
of the Board
(by Mr.
Currie)
The Agency’s complaint charged GAF with delays
in the
implementation of its Air Contaminant Emission Reduction
Program, which required the installation of fume incineration
systems on asphalt saturators and oxidizing stills at the
company’s Joliet roofing plant by May 1972.
The result,
it was alleged, was emissions in excess of regulation limits
(Rules and Regulations Governing the Control of Air Pollution,
Rule
3-3.111)
and interference with the neighbors’ enjoy-
ment of
their property, constituting air pollution under
~ 9(a)
of the Environmental Protection Act.
On September
25,
1972, we received ~ stipulation and
proposed settlement from the parties.
The stipulation re-
cited the Agency~scontentions that allowable particulate
emissions
from the oxidizing stills were 20.66 pounds per
hour and actual emissions
43.5, and both saturators and
stills had “created a nuisance for the community
by emitting asphalt odors which citizens have found
objectionable and by emitting copious amounts of particu-
late matter which interfere with normal lives of the local
citizens.”
GAF
denied that it committed any violation.
It
is further recited
that
GAF
is actively working to
install the necessary fume incineration systems, which
“are the most efficient asphalt fume abatement equipment
presently available,” and which are “contemplated by GAF
to abate
the nuisance
.
*
.
and to bring
the
particulate
emissions from the oxidizing stills into compliance with
all presently enacted state air pollution regulations”--
presumably including the newly tightened particulate re-
gulations we adopted in April of this year
for future corn—
pliance
(PCB Re~s.,Ch.
2).
The stipulation states that
the
“program is now well under way and proceeding according
to
the
new
schedule.”
The company estimates the cost of
control
eguiprnerit
at $1,555,802.
5
—
553
—2—
The proposed settlement is that GAF will complete the
control installation and comply with all applicable laws
and regulations by January 31, l973~will post a bond in the
amount of the cost of the program; will file monthly pro-
gress reports; will be permitted to operate under present
conditions until the new deadline;
and will pay a penalty
of $15,000
for its alleged delays.
This agreement is contingent upon the Board’s approval
of
a second settlement relating to GAF’s petition for judicial
review of our penalty order
in #71-11,
a water-pollution case
involving the same plant;
the water settlement was approved
by
the Board on September
26,
1972, for reasons stated in
a separate opinion adopted today.
GAF Corp.
v.
EPA,
#71-il,
5 PCB
—,
—
(Sept.
26 and Oct.
3,
1972)
Board procedure in evaluating proposed settlements is
detailed in our procedural Rule 333
(PCB Regs,
Ch.
1, Rule
333)
and in EPA v. City of Marion,
#71—25,
1 PCB 591
(May 12,
1971)
,
in which we have made clear that, because of the
Board’s role as an affirmative instrument for effectuating
the policy of the Act, Board approval of the merits
is recuisite
for any settlement of a pending case.
See also the dis-
cussion in GAF Corp.
v.
EPA,
#71-11,
5 PCB
,
decided to~-
day.
As we said in the Marion case,
the statutory policy o~
public participation in pollution cases requires that we
make every reasonable effort to ascertain the views of the
public upon settlements proposed by the Agency and the res~
pondent.
For the Agency is bdt the guardian of the public
interest;
it is the public itself that must put up with the
results of our decisions.
Consequently,
as we said in
Iowa-Illinois Gas
& Electric Co., #72-216,
5 PCB
(August 22,
1972)
,
—
It has been our preferred procedure,
even where a
stipulation is reached on all factual issues, and in-
deed even when the parties agree on a proposed dis-
position,
to require that the stipulation and proposal
be presented publicly so that affected citizens have
a meaningful opportunity to know the terms and to ex-
press
their views.
But we have not felt ourselves bound to hold a hearing
on a proposed settlement when strong countervailing con-
siderations indicate we should not.
In EPA v. Russell,
Burdsail
& Ward Bolt
& Nut Co., #71-369,
4 PCB 701
(June
27,
1972), the Board noted the desirability of a
settlement hearing hut decided the case without
a hearing
transcript, evidently believing that the completeness
of
the stipulation and the large amount of the agreed penalty
(over $50,000)
gave considerable assurance that the public
interest
would
be
protected,
in light of the further
delays
that
would
have
beee
encountered
had
the
Board
at
that
date
—3—
scheduled
a settlement hearing.
In Howe
v. Commonwealth
Edison Co.,
#71—333, 5 PCB
(Sept.
6,
1972), the record
reveals
that the parties’ i~T~ia1agreement to settle was
retracted upon notification that
a hearing on the proposal
would be necessary;
the Board after examining the facts and the
proposed remedy
(a $2500 penalty for an accidental spillage
of 150 gallons
of oil into
the Mississippi River) concluded
that “no useful purpose would be served by insisting upon
a hearing
on the facts of this particular proceeding.”
Our
policy,
therefore,
is to hold settlement hearings unless
extraordinary circumstances indicate otherwise.
The present case
is one of such extraordinary circum-
stances.
We received both this stipulation and that in
the GAF water case on September 25, and each depended upon
approval of the other.
Oral argument in the water case be-
fore the Appellate Court was set for October
3,
and we were
informed that postponement
of our decision would not only
impose
a considerable work burden upon attorneys in pre-
paring for oral argument but would also entail
a significant
risk that our approval of the water settlement might come
too late
to forestall
a court decision onthemerits.
In
other words,
if we did not approve both settlements before
October
3 we might well lose the opportunity for settle-
ment
of
the water case altogether.
The desirability of accepting the water settlement is
spelled out in our opinion in that case,
adopted today.
To
have insisted upon
a public hearing on the air settlement,
with
the requisite 21-days’ notice, would have put an end to
the water
settlement.
Given this important adverse con-
sequence of postponing the air decision,
and given our
evaluation of the air settlement itself, we concluded that
we should proceed without a settlement hearing,
and the
air settlement was
approved by
a 4-1 vote,
Mr. Dumelle
dissenting,
on September
26,
for reasons that follow.
For purposes of passing upon the adequacy of the
oroposal,
we assume that the Agency’s allegations are true
and that the Agency would prove them if a hearing on the
rierits were held.
These allegatibns would establish that
~AF has unjustifiably delayed by eight months the completion
ut
necessary pollution control facilities.
The Agency agrees
that the
equipment
that
is
being installed is the best
available,
and
it does not contend
that,
given present
facts
the installation could
be
completed any faster than
the coenanv
has
agreed to complete it.
Shutting down the
eLant, ~or
reasons
civen in our
first
opinion in the water
case
(OAF Corp.
v.
EPA,
#71—11,
1
PCB
481
(April
19,
1971)),
does not aepear a reasonable alternative.
We are convinced
the abatement program, seen from today’s vantage point,
is
an exec~pLaryone, and it
is
to be secured by an adequate bond.
5
—
555
—4—
The sole remaining question is the adequacy of the
$15,000 penalty
for the eight months’
delay.
As we said in
the companion GAF water case,
the setting of
a money
penalty is not an exact science.
The penalty agreed upon
here is in the same ball park as penalties for comparable
delays
in
a
number
of
other
significant
air—pollution
cases.
See,
e.g., Marquette Cement Mfg.
Co.
v. EPA,
#71-23,
1 PCB 145
(Jan.
6,
1971)
($10,000, which the opinion writer thought
low,
for over a year’s delay in controlling a large cement
plant); Molex,
Inc.
v.
EPA, #71-200,
3 PCB 341(January
6,
1972)
($10,000 for a two-to-three-year delay in controlling
substantial and offensive emissions from a plastics factory)
Agrico Chemicals Co. v.
EPA, #71—211,
3 PCB 319
(Dec.
21,
1971)
(10,000
for a year-and—a-half delay in controlling
particulate emissions from
a fertilizer plant).
See also
Spartan Printing Co.
v.
EPA,
#71-19,
2 PCB 19
(June
23,
1971)
($10,000 for an 18—month delay
in abating substantial water
pollution
violations
from
a
large
printing
plant).
Cases
resulting
in
substantially
higher
penalties,
by
and
large,
have
involved
the
failure
to
take
any affirmative action
to abate long-standing and serious nuisances down to the
date of the complaint.1
See Hemmerich v. Lloyd A. Fry
Roofing Co., #71—33,
2 PCB 581
(Oct.
14,
1971) ($50,000)
EPA
V.
Incinerator,
Inc.,
#71-69,
2 PCB 505
(September
30,
1971) ($25,000)
.
We conclude that,
in view of the relatively
brief delay in the present case,
and the absence of Agency
insistence that the emissions imposed an intolerable burden
on the
community,
the agreed penalty of $15,000
is a sub-
stantial one that approximates what we would in all likeli-
hood impose upon proof of all the violations alleged.
In the interest of avoiding unnecessary litigation, we
accept reasonable settlements agreed
to by both parties.
See EPA v. Granite City Steel,
#70-34,
4 PCB 457
(May
3,
1972)
*
On these grounds the settlement was approved September
26.
Mr. Dumelle dissents,
1.
The
special
circumstances surrounding the $149,000
penalty in the GAF water case,
#71—li, and our acceptance
of
a $50,000 settlement, are described
in today’s
opinion
in
that
case.
I, Christan Moffett, Clerk of the Pollution Control Board,
certify that the Board adopted the above Opinion this______
day of October,
1972,
by
a vote of__________
5
—
556