ILLINOIS POLLUTION CONTROL BOARD
    October
    3,
    1972
    GAF
    CORPORATION
    )
    v.
    )
    #
    71—11
    ENVIRONMENTAL PROTECTION AGENCY
    Opinion of the Board on Proposal for Settlement
    (by Mr. Currie):
    This case began early in 1971 when GAF petitioned
    for a variance to allow more time for construction of waste—
    water treatment facilities at its roofing mill on the
    Des Plaines River near Joliet.
    No complaint seeking money
    penalties for past delays was ever filed.
    Following hear-
    ings, we concluded that GAF had unjustifiably delayed for
    about five months the construction of facilities for
    treating wastes equivalent to the raw sewage of 90,000 per-
    sons.
    Recognizing that immediate shutdown of the plant
    for this violation would impose severe hardships upon
    700 employees and, because of other pollution sources, would
    not render the Des Plaines immediately free from pollution,
    we granted
    a two—months’ variance during which GAF was re-
    quired to demonstrate diligence in completing its program,
    subject to extension in the event satisfactory progress
    was shown.
    On the other hand,
    fearing that “to let the
    company off Scot free”
    for what we termed its “callous
    disregard for its obligations,”
    the Board required
    GAP
    to pay a penalty of $149,000 as a condition of the variance,
    relying upon our statutory authority to impose such
    con-
    ditions
    as may be required to effectuate the policy of the
    Environmental Protection Act.
    GAF Corp.
    v. Environmental
    Protection Agency,
    #71—11,
    1 PCB 481
    (April 19, 1971).
    As anticipated by our first order, GAF submitted a
    petition for extension of the variance to permit completion
    of construction,
    alleging Significant progress and asking
    interim extension pending resolution of the merits of the
    new petition.
    After
    a hearing we concluded that the com-
    pany had “shown sufflcient good faith cot~raitmentto curing
    its pollution problem to
    en~itie it
    to continue operating
    while we pass upon the merits of its program,”
    and
    extended
    the variance pending final decision.
    GAP Corp.
    V.
    EPt7
    #71—11,
    2 PCB 57
    (June
    28,
    1971)
    .
    After full hearings
    we concluded that GAF,
    since our first order, had “elected
    to proceed post haste to abate the pollutional nature of its
    aqueous discharges,” and that the “history in this case

    —2—
    of delay
    .
    .
    .
    is now happily past.”
    We approved the pro-
    gram, providing for continued operation until completion
    of the required secondary treatment facilities April
    30,
    1972.
    GAF Corp.
    v.
    EPA,
    #71—ilS,
    2 PCB 393,
    401
    (Sept.
    13
    and 16, 1972).
    The original penalty provision was not
    impaired by
    these later orders.
    While pursuing its abatement program with what we
    found in the above opinions constituted due diligence,
    GAF
    sought judicial review of our order, especially as it re-
    lated to money penalties,
    in the Appellate Court.
    The com-
    pany’s brief raises far-reaching constitutional and statutory
    questions,
    as yet unsettled by the courts, respecting the
    powers of this Board,
    and challenges certain aspects of the
    particular proceeding as well.
    Oral argument on the petition
    for judicial review was scheduled, we were informed by the
    Attorney General’s office,
    for October
    3,
    1972.
    On September 25,
    1972,
    we received a proposed settle-
    ment agreement endorsed by both GAF and the Environmental
    Protection Agency, the two parties to the proceedings before
    this Board.
    Reciting that GAF has now completed its program
    and is in compliance with the regulations from which it
    originally sought variances,
    the agreement provides for the
    payment of $50,000 by GAF;
    for dismissal of the judicial
    review proceeding with prejudice;
    and for extinguishment
    of any remaining liabilities under prior Board orders.
    A
    condition of the agreement
    is
    B0E’rd approval of a second
    settlement in #72-50, Environmental Protection Agency v.
    GAF Corp.,
    an air pollution case concerning the same plant;
    such approval was given September 26,
    5 PCB
    ,
    for reasons
    stated in a separateopinion
    adopted today
    (5 PCB
    Because the impending oral argument of the appeal from our
    original order would impose substantial work burdens on the
    parties and might eliminate the opportunity for settlement,
    we passed upon the proposal September 26 and approved it by
    a 4-1 vote, Mr. Dumelle dissenting
    (5 PCB
    ),
    for reasons
    that we detail
    in today’s opinion.
    I.
    Jurisdiction.
    Whether the Board’s approval is required for settle-
    ment
    of appeals from its decisions was a threshold question,
    never before resolved,
    that had to be decided before reaching
    the merits of the proposal.
    Were we a conventional trial
    court,
    the disposition of our decisions on appeal would be
    a matter exclusively for the parties, subject to the approval
    of the appellate tribunal; for the trial court is an impartial
    arbiter between adversary litigants and not an interested
    party on appeal.
    In many ways our function in individual
    pollution cases resembles that of a trial court, especially
    5
    526

    —3—
    in enforcement cases.
    The Board takes no part in the in-
    vestigation or presentation of cases but sits to decide on
    the basis of a record made by adversary parties.
    The
    Administrative Review Act, however, explicitly makes the
    Board a party to every proceeding seeking judicial review
    of its decisions.
    Ill.
    Rev.
    Stat.,
    ch.
    110,
    § 271.
    From
    the language of that statute alone it would be open to us
    to view our position, like that of the judge whose decision
    is sought to be reviewed by a writ such as mandamus,
    as a
    purely
    formal one arid to leave the fate of our orders on
    appeal to the parties who appeared before us.
    Consideration
    of our position under the Environmental Protection Act
    arid
    comparison with our accepted role in the settlement of cases
    still pending before us, however, convinces us that we cannot
    view our position on appeal as that of a disinterested trial
    court.
    In setting up the Pollution Control Board as part
    of
    a “unified, state—wide program
    .
    .
    .
    to restore, protect
    and enhance the quality of the environment”
    (Environmental
    Protection Act, ~ 2(b)),
    the General Assembly did not create
    simply another court with limited jurisdiction.
    Board
    members were required to be “technically qualified”
    in matters
    relating to pollution control, ~ 5(a),
    and the Board was
    directed
    to
    “determine,
    define
    and
    implement
    the
    environ-
    mental control standards applicable
    in the State of Illinois,”
    §
    5
    (b)
    .
    As Governor
    Ogilvie stated in recommending adoption
    of the Act (Special Message on the Environment, April
    23,
    1970,
    p.
    5)
    ,
    “the principal job of defining what may or may
    not be done to the environment would be left,
    under the
    proposed act, to the new Pollution Control Board.”
    Thus the
    Board was designed to be the final interpreter,
    subject to
    judicial review, of what is required to effectuate the
    policies of the Environmental Protection
    Act; not merely a
    disinterested arbiter, the Board
    is entrusted with
    affirmative responsibility to see to
    it, through appropriate
    orders
    in
    matters
    brought
    before
    it,
    that
    the
    policies
    of
    the
    Act
    are
    carried
    out.
    The Board is to exercise this
    responsibility
    in
    rule-making
    matters,
    by
    adopting regulations
    defining,
    for
    example,
    prohibited
    levels
    of
    discharge
    as
    re-
    quired “to promote
    the purposes” of the Act
    (e.g., ~ 13).
    It is to do so in enforcement cases, by considering “all
    the facts and circumstances bearing upon the reasonableness
    of the emissions,
    discharges,
    or deposits” and by entering
    “such final order” or making
    “such final determination,
    as
    it shall deem appropriate under the circumstances”
    (~
    33(c),
    33(a)).
    It
    is to do
    so in variance cases, such as this one,
    by determining whether or not compliance “would impose an
    arbitrary or unreasonable hardship” and by imposing ~‘such
    conditions as the policies of this Act may require”

    —4—
    (~635,
    36(a)).
    In all its functions the Board operates
    as an affirmative instrument of the statutory policies of the
    Environmental Protection Act, responsible for entering
    orders on the basis of its own best judgment, form the record,
    as
    to
    what
    “may
    or
    may
    not
    be
    done
    to
    the
    environment”
    con-
    sistent with those policies.
    As a body thus charged with
    carrying out statutory policy,
    the Board has a continuing
    interest in the resolution of matters brought before it that
    we cannot in good conscience delegate to others.
    The special interest of the Board in cases brought
    before it was expressed very early in our history in the
    adoption,
    in October 1970, of our procedural rule 333,
    which provides a special procedure to be followed if the
    parties desire to settle cases pending before us.
    In light
    of our affirmative responsibility under the Act for deter-
    mining what would constitute an appropriate order consistent
    with statutory policy,
    that rule provides that
    “no case
    pending before the Board shall be disposed of or modified
    without an order of the Board.”
    Written statements as to the
    reasons for settlement are required, and the Board may require
    the parties to appear to supply further information to
    guide the Board in making the ultimate decision whether
    or not the proposed settlement is consistent with statutory
    policy.
    PCB Regs.,
    Ch.
    1,
    Rule 333.
    We spelled out these
    requirements in EPA v. City of Marion,
    #71-25,
    1 PCB 591
    (May 12,
    1971)
    Rule 333 requires the parties to submit to the Board
    adequate information on which we can base an intelligent
    evaluation of whether any proposed settlement
    is in
    the public interest.
    After all it
    is the Board and
    not the Agency or its attorneys that is given statutory
    responsibility to determine whether a violation
    exists and what is the appropriate remedy.
    .
    .
    .
    Such
    information must contain a full stipulation of the
    relevant facts pertaining to the nature,
    extent, and
    causes of the violations, the nature of the respondent’s
    operations and control equipment,
    any explanations
    of past failures to comply, and details as to future
    plans for compliance, including descriptions of
    additional control measures and the dates for imple-
    menting them, as well as a statement of reasons why
    no hearing should be conducted.
    Opportunity will also
    be provided by the Board for individual citizens
    to
    express their views as
    is contemplated by the statute.
    In exercising
    this responsibility we have not hesitated to
    reject proposed settlements that we believed were not consis-
    tent with statutory policy.
    E.g., EPA v. Packaging Corp
    of America,
    #72—10
    (consolidated with #71—352)
    ,
    5
    PCB____
    (August
    8 and
    15,
    1972)
    5
    528

    —5—
    Thus even in enforcement cases,
    in which there are
    by definition two adversary parties, our consistent rule has
    been that our special statutory position requires our affirma-
    tive approval of the
    merits of any settlement proposal.
    In variance cases the matter is
    even more clear;
    for al-
    though the statute makes every effort to assure the active
    participation of the Environmental Protection Agency in
    variance cases
    to avoid the undesirability of our having
    to decide upon records made entirely by one party
    (~
    37;
    see Kelberger v.
    EPA,
    #72-177,
    5 PCB
    (September
    26, 1972)),
    the Agency is not a true adversary in every case,
    for it
    may properly recommend that the variance be granted.
    We are
    directed even in such cases
    to examine the record for ourselves,
    and moreover public participation in variance proceedings is
    encouraged,
    in order that the decision wilibe based upon the
    Board’s best judgment and not simply upon the Agency’s agree-
    ment with
    the petitioner.
    In short the statute is quite
    explicit that variances are to be granted only by the Board,
    and not by the Agency;
    complete deference to Agency
    recommendations in variance cases would effectively transfer
    that power to the Agency.
    Thus our position is clear that cases pending before
    us may not be settled without our approval on the merits.
    To hold that we have no concern with the terms on which our
    orders are settled after they are entered would thoroughly
    undermine that position;
    any time we rejected a settlement
    ~ile
    the case was before us the parties could circumvent our
    policy by compromising our order on the basis of their
    original insufficient proposal.
    We do not mean to suggest
    that we anticipate any such action on the part of responsible
    public officials, but only that our authority to review
    proposed settlements after our orders have been entered and
    appealed is an essential safeguard if our authority over
    settlements of pending cases is to have any meaning.
    In-
    deed the case for our evaluation
    of settlements may be even
    stronger after we have entered an order than before,
    since agreement to any modification would appear
    to constitute
    a variance from our order,
    ~ihich only this Board
    is authorized
    to grant.
    We have thus concluded, a~we have been urged
    by
    the Agency and Attorney General to conclude, that our
    approval is necessary to the settlement
    of a petition for
    judicial review of
    a Board decision.
    II,
    The
    Merits of the Settlement.
    The terms
    of
    the settlement are simple:
    GAF will
    drop its appeal and pay $50,000
    if
    the Agency and the Board
    will accept that sum in full payment of the penalty we
    first assessed at $149,000,
    Both GAP and the Agency are
    willing
    to sacrifice
    a $149,000—or-nothing gamble for the
    5
    529

    —6—
    certainty of
    a $50,000 penalty.
    When we set penalties, we do not do so with compro-
    mise in mind; we do not artificially inflate them in hopes
    of precipitating
    a favorable settlement.
    We set them
    in amounts that we think are appropriate to further statutory
    policy,
    after
    considering
    all
    relevant
    factors,
    such
    as
    the
    harm
    done,
    the
    length
    of
    the
    delay,
    the
    difficulties
    facing
    the
    company,
    the
    sums
    saved
    by
    violating
    the
    law,
    and
    so
    on.
    See
    the
    discussion
    in
    EPA
    v.
    CPC
    International,
    #71-338,
    5
    PCB
    ,
    decided today.
    It must necessarily
    be the extraordinary case in which, after entering an order
    on
    the
    basis
    of
    all
    relevant
    facts
    before
    us,
    we
    consent
    to
    a modi~ficationof our decision.
    If it were otherwise there
    would be no finality to our orders, and pollution control
    would be impeded.
    When we enter a penalty order we mean the
    specified sum should be paid,
    not that the figure is
    a basis
    for further negotiations.
    At the same time, we have recognized
    a limited
    power and duty to entertain petitions for rehearing in order
    to correct manifest errors or to consider the impact of
    changed circumstances.
    See,
    e.g., North Shore Sanitary
    District v.
    EPA,
    #71—343,
    3 PCB 697 (March
    2,
    1972)
    Finality is thus not an absolute.
    And,
    in consideration of
    the Board’s special interest in the effectuation of
    statutory policy, we think finality may be forced to yield
    in extraordinary situations
    in which, because the Board
    has been made respondent in a judicial proceeding
    challenging its orders,
    some thodification of those orders
    appears necessary to afford maximum assurance that the
    underlying policy of the Board
    arid of those orders them-
    selves will not be frustrated.
    As an interested litigant,
    in other words,
    the Board must have some flexibility to
    protect the interests of
    the pollution control program.
    This flexibility must he employed rarely and with
    great care,
    lest the mere filing of
    a petition for review
    be
    taken
    the
    occasion
    for
    negotiating
    downward
    any
    penalty
    imposed by the Board.
    We emphatically reject any such
    notion.
    We hold only that, in extraordinary cases in which
    reexamination of a prior order in light of the original
    record and of the risks of reversal strongly indicates that
    pollution control policy would be best served by modification
    of our order,
    it
    is appropriate for us to modify it.
    The facts of the present case led us to conclude
    that this is such a situation.
    First of all, $50,000
    is a
    very considerable penalty, especially for no more than
    five months’
    delay in constructing treatment facilities.

    The
    3oard was
    aware
    that
    additional
    time
    had elapsed
    since
    the deadline first set by the Sanitary Water Board,
    but
    as
    our
    opinion
    recognized
    that
    Board
    had
    granted
    ex-
    tensions
    forgiving
    all but the last
    five
    months
    of
    de-
    lay.
    350,000
    is equal
    to the largest money penalty ever
    imposed
    by the Board in any other fully
    litigated
    case.1
    See
    Bemmerich v.
    Lloyd
    A.
    Fry
    Roofing
    Co.,
    #71-33
    (con-
    solidated with 471—4)
    ,
    2
    PCE
    581
    (October
    14,
    1971)
    ,
    in
    which asphalt plant emissions estimated at seven times
    those
    cermitted
    by
    the regulations since
    1967
    had
    “caused headache, nausea, burning to the
    eves,
    nose
    and
    throat, ccu~hinc,u~setstomach,
    and,
    in many
    instances,
    foreclosed
    outdoor activities.”
    In
    Incinerator,
    Inc.,
    471—69,
    2
    ?CB
    505
    (Sectember
    30,
    1971),
    a
    penalty
    of
    S25,000
    was
    imoosed
    for
    unexcused
    failure
    since
    1967
    to
    ccntzcl odors and
    carticulate
    emissions
    at
    least
    three
    times
    those
    allowed from
    a
    large
    incinerator,
    which
    we
    found
    “with its frecuent, almost
    daily,
    shower
    of
    marticulate
    matter emd the
    accomoanvinc
    odors,
    constitutes
    nothing
    short
    ci a nuisance to the
    neighborhood.’
    The penalty in the
    present
    case
    was
    computed
    at
    the statutor7 maximum rate of
    $10,000
    for
    the initial offense
    and
    81,005
    a day thereafter.
    To
    have
    applied
    such
    a
    formula in
    the
    Fry
    or
    Incinerator
    cases
    would
    have
    resulted
    in
    penalties
    of
    over
    half
    a
    million
    dollars
    from
    the
    date
    the
    Act
    took
    effect,2
    Comparing
    the
    seriousness
    of
    GAF’s
    I.
    in
    two
    instances
    we
    have
    approved
    settlements
    providing
    for
    the
    ~ayment of larger
    sums
    under
    special
    cir—
    cumstances:
    EPA
    v.
    Granite
    City
    Steel
    Co.,
    #70-34,
    4
    PCI
    347
    (April
    25,
    1972)
    ,
    in
    which
    the
    company
    agreed
    to
    establish
    a
    $150,000
    scholarship
    fund
    (presumably
    tax-deductible
    at
    least
    in
    part,
    unlike
    a
    straight
    ~enalty)
    as
    a
    result
    of
    a
    complaint
    alleging
    severe
    and
    long-standing
    air-pollution
    violations
    from
    multiple
    oom~cnents
    of
    a
    large
    steel
    mill;
    and
    EPA
    V.
    Puasell,
    Burd.sall
    &
    Ward
    Bolt
    and
    Nut
    Co.,
    #71—369,
    4
    PCI
    751
    (Tune
    27,
    1972)
    ,
    in
    which
    the
    company
    agreed
    to
    nay
    040,000
    in
    addition
    to
    the
    $13,449.96
    estimated
    -;alue
    of
    nealiy
    100,000
    fish
    killed
    by
    a
    large
    cyanide
    discharge.
    2.
    We
    do
    not
    say
    the
    use
    of
    that
    formula
    can
    never
    be
    ~u~tified,
    for
    it
    was
    put
    in
    the
    ~atute
    to
    be
    used
    when
    necessary.
    5
    531

    —8—
    violations with that of Fry’s
    is no exact science, but we
    do not think it immediately apparent that the one case was
    three times more serious than the other.
    Roughly equal
    treatment of persons similarly situated is fundamental to
    our law,
    and the Fry case is an important part of the develop-
    ing experience of this relatively new Board in determining
    the appropriate penalty to be assessed.
    Our experience
    in
    that regard,
    especially in serious cases, was severely limit-
    ed at the time GAP was first decided; the largest penalty
    we had previously imposed was $10,000, and that in a case
    involving well over a year’s unexcused delay in controlling
    particulate emissions from a giant cement plant
    (Marquette
    Cement Mfg.
    Co.
    v.
    EPA,
    #70-23,
    1 PCB 145
    (January
    6,
    1971).
    We do not say that the penalty we initially imposed
    in this case was too high.
    It represented our best judg-
    ment at the time on the basis of the facts that were before
    us and on the basis of our experience.
    We adhere to the
    conviction that GAP’s violation,
    like Fry’s, was a very
    serious one, and that it
    is important to the credibility
    and success of the pollution control program that a sub-
    stantial money penalty he paid.
    As we said in setting the
    penalty, for the company to
    go
    scot free would encourage
    future violations,
    The point we make today
    is simply that
    there
    is
    room
    for
    a
    significant degree of variation in the
    amount of penalty without materially affecting the purposes
    that
    the
    penalty
    serves.
    ifl
    a
    case
    like
    this
    one
    it
    is not
    so much the dollar amount of the
    penalty
    as the fact of a
    substantial
    penalty
    that serves as notice to GAP and to
    others
    that
    the
    State
    is serious about enforcing the pollution
    laws.
    The
    company’s
    savings as
    a result of delay, offset
    perhaps to a degree we cannot ascertain by rising con-
    struction costs, are a matter of speculation, not of
    proof
    in
    this
    case.
    The effect
    on
    the
    public
    was
    to in-
    sult
    further
    a
    stream
    already
    badly
    polluted
    by
    others.
    Either $50,000 or $149,000, we believe, would substantially
    promote the statutory deterrent policy underlying our
    original decision, and the lesser figure appears to he
    in the range of subseouent Board decisions
    in other serious
    cases.
    Second, while the filing of a petition for review
    by no means automatically justifies the reduction~ofa
    penalty once imposed,
    it
    poses
    the
    risk
    that
    the
    entire
    order
    may be overturned by an
    appellate
    court,
    The
    likelihood
    of
    5
    532

    —9—
    reversal, and the consequences of possible reversal, are
    of legitimate concern to the Board in assessing how best to
    effectuate
    statutory
    policy.
    Even
    though
    we
    are
    not
    con-
    vinced that an order was erroneous,
    it may be proper to accept
    a modification that will still carry out statutory purpose
    in
    order
    to
    avoid
    a
    significant
    risk
    of
    a
    court
    decision
    that would seriously frustrate the program.
    GAP raises on appeal
    a
    number
    of
    constitutional
    objections
    to
    the
    essential
    features
    of
    the
    Environmental
    Protection
    Act.
    While
    we
    are
    firmly
    convinced
    that
    those
    contentions
    should
    be
    rejected,
    see
    EPA
    v.
    GraniteCity
    Steel Co.,
    #70—34,
    1 PCB 315
    (March 17, 1971); EPA v.
    Modern
    Plating
    Corp.,
    #70—38,
    1
    PCB
    531
    (May
    3,
    1971)
    ,
    and
    while
    we
    believe
    the
    courts
    will
    reject
    them, we see no
    reason
    to
    provoke
    unnecessary
    court
    challenges
    if
    a
    company
    agrees
    to
    pay
    a
    penalty
    substantial
    enough
    to
    serve
    the
    statutory
    purpose.
    Nor
    do we believe, for numerous reasons,
    that the present case is theideal one in which such issues
    should be presented
    to the courts.
    The amount of the penalty
    is
    quite
    high
    in
    comparison
    to
    other
    Board
    decisions,
    and the company has raised questions concerning
    the adequacy of notice.
    We believe we correctly
    construed our authority and correctly
    interpreted the
    record in entering our initial order, but
    we recognize the risk of reversal, and the consequences of
    reversal would be quite severe.
    Possibly, GAF would get
    off without penalty for its serious violations, contrary to
    the policy underlying our original decision; at best a
    penalty might be imposed after still another hearing, long
    after the events in question took place, subject to further
    judicial review and exhausting the resources of the control
    agencies as well as of thecompany.
    Moreover, an adverse
    decision might have consequences far beyond this case,
    by
    affecting
    the authority of the Board to take vigorous
    action against others found in violation.
    We prefer to
    face
    that
    possibility
    in
    a
    case
    less
    complicated
    by
    extraneous
    arguments than this one, where the merit of our position can
    he
    made
    unconfusedly clear to the court and attention
    focused on the central issues.
    Finally,
    for reasons in-
    dicated
    above, we think that the significant dangers to
    pollution control policy both
    in the present case and in the
    long run posed by judicial review of our initial order
    can be avoided without substantially impairing the force of
    our icoision by approving the payment of $50,000
    in full
    sat:Lsfeo~:ionof the penalty in consideration of the dismissal
    of the ru~titionfor review.
    5
    53:3

    —10—
    Had
    the
    Board not conditioned the original variance on
    the payment
    of a penalty, GAF might indeed have gone “scot
    free,” as we then observed,
    since no complaint was ever filed.
    By
    the
    same
    token,
    had
    the
    Board
    insisted
    upon
    collection
    of
    the
    entire
    $149,000
    originally
    assessed,
    GAF
    might
    have
    ended
    up
    scot
    free
    and
    the
    Board
    might
    have
    been
    crippled
    in
    its
    future
    efforts
    as
    a
    victim
    of
    the
    maxim
    that
    hard
    cases
    have
    a tendency to make bad law.
    Aesop
    summed
    it
    up
    some
    years
    ago:
    It
    happened
    that
    a
    Dog
    had
    got
    a
    piece
    of
    meat
    and
    was
    carrying
    it
    home
    in
    his
    mouth
    to
    eat
    it
    in
    peace.
    Now
    on
    his
    way
    home
    we
    had
    to
    cross
    a plank lying across
    a running brook.
    As he
    crossed,
    he
    looked
    down
    and.
    saw
    his
    own
    shadow
    reflected
    in
    the
    water
    beneath.
    Thinking
    it
    was
    another
    dog
    with
    another
    piece
    of
    meat,
    he
    made
    up his mind to have that also.
    So he made a snap
    at the shadow in the water, but
    as
    he
    opened
    his
    mouth
    the
    piece
    of
    meat
    fell
    out,
    dropped
    into
    the
    water
    and
    was
    never
    seen
    more.
    Beware
    lest
    you
    lose
    the
    substance
    by
    grasping
    at
    the
    shadow.3
    3.
    J.
    Jacobs, the Fables of Aesop
    (MacMillan,
    1943),
    p.
    7.
    I, Christan Moffett, Clerk of the Pollution Control Board,
    certify
    that
    the
    Board
    adopted
    the
    above
    Opinion
    on
    Proposal
    for Settlement this
    day of October, 1972,
    by a vote
    of
    5
    534

    Back to top