ILLINOIS ~LLUT1ON
CONTROL BOARD
September 26. 1P72
)
IOWA-ILLINOIS GAS AND ELECTRIC COMPANY)
)
)
v.
)
PCB 72-279
)
)
ENVIRONMENTAL PROTECTION AGENCY
)
)
SUPPLEMENTAL STATEMENT (by Mr. Dumeile)
On November 15, 1971 in PCB 71-20. 3 PCB 95, the Board by a 3-1
vote granted a permit to the Iowa-Illinois Gas & Electric Company and to
Commonwealth Edison Company to operate Quad-Cities nuclear units 1
and 2. The majority opinion of that date contains these words in its opening
paragraph:
We note that there are environmental considerations on
both sides in this case. Petitioner Iowa-Illinois operates
an old, smoky coal-fired power plant in Moline that cannot
be retired until Quad-Cities is in operation. Every day’s
delay in bringing Quad-Cities on line means another day
of dirty air in Moline.
My dissent on the Quad-Cities permit (which has since been vacated by
the Board because of a U. S. Supreme Court ruling) was based on concern for
people’s lives because of inadequacies in the emergency core cooling system
design; the unnecessary radiation dose to the public because of neglect to
install in advance of startup a radioactive gas cleaning system; and lack of
information on the effects of the jet diffuser in terms of fish passage.
The implication of the Board’s majority statement quoted above is that
the “old, smoky coal-fired power plant” in Moline will be retired when
Quad-Cities 1 is in operation. The question here then is “When is Quad-Cities
a reliable source of power?” There is no magic in the June 1. 1974 date
proposed by Iowa-illinois so far as Quad-Cities 1 is concerned. Refueling
of boiling water reactors takes place every year and 25 of the core is
repkced each time.
5—501
—2—
The McGraw—Hill Publication Nucleonics Week publishes monthly figures
oi nuc’ear power generation, The past two months of available data show the
following generation in gross
Mwh.
MONTh
QUAD-CITiES 1
QUAD-CITIES 2
July
199, 025
194, 760
August
291,597
246,483
Using 850 Mw as each units gross capacity, a load availability of
31.8 and 46,6 for Quad-Cities 1 for July and August respectively and
31,1 and 39. 5 for the same months for Quad-Cities 2 was computed. In
normal base load operation, figures around 85 would be expected. We can
say then, that as of the end of August, neither Quad-Cities unit was yet
delivering power at an expected rate and the variance therefore appears to be
justified.
There is a new complication. The September 7, 1972 issue of Nucleonics
Week tells of a shutdown of Quad-Cities 2 due to a jet pump” being displaced
from its normal position’ and attributes this to seven parts of the pump--
mostly various bolts --had inexplicably worked loose. One of the bolts has
not been found......
A General Electric spokesman said the problem was
caused by incomplete’ installation.’ Will other instances of ‘incomplete
installation be discovered in either Quad-Cities units 1 or 2? Will other
parts inexplicably work loose’? We do not know and can only hope that a
major construction defect does not appear. Loose bolts in the interior
of a nuclear reactor do nothing to gain public confidence in the safety of
nuclear power plants.
The August 1972 recommendation by the AEC’s prestigious Advisory
Committee on Reactor Safeguards that Commonwealth Edison’s Zion-i
nuclear plant (a different type) be derated to 85 of full capacity for its
first core life (3 years) because of lack of operating experience in large
reactors and the recently discovered fuel degradation problem is proof
positive that all is not yet known about nuclear power generation. The
Zion derating is expected to cost Edison some $6 million per year in lost
revenue (Nucleonics Week, October 5, 1972).
A second complication is the pending Atomic Energy Commission ruling on
the adequacy of emergency core cooling systems. The AEC may not rule
in this matter until March 1973 or later and may then ordac a derating until
retrofitting is done.
5 —
502
—U—
Iowa—Illinois and Moline may have to endure the old, smoky plant
for a while longer depending upon developments in the inst—changing nuclear
power field. I would urge Iowa—Illinois to now fully investigate possible
low ash doai usage in order that particulate emissions be kept to a minimum.
I, (:hrjstan L. Moffett, Clerk of the Illinois Pollution Control. Board,
hereby certify the above Supplemental Statement was submitted on the
-~
day of October, 1972.
~
~
//~1~
/
/
Christan L. Moffett,’~(4erk
Illinois Pollution Control Board
/1
)
Jacob I). Dumelle
Board Member
5
—
503