1. (Aug. 29, 1972), can be a very ~erious matter, as it may
      2. result in raw sewage not only in streams but also in streets
      3. and in basements, with obviously unsavory implications for
      4. public health, The Agency!s recommendation tells us that
      5. the sewer in question “is subject to excessive flows from
      6. on the basis of precedent the hardships alleged by Mrs.
      7. Kelberger, since they fall short of the commencement of
      8. construction, would probably be insufficient to justify a
      9. variance even if her actions had all taken place before the
      10. sewer ban was imposed. Cf. Wagnon v. EPA, #71-85, 2 PCB 131
      11. (July 26, 1971). There are several reasons, therefore, why
      12. this petition ought to be dismissed or denied.

ILLINOIS POLLUTION CONTROL BOARD
September 26,
1972
ELSIE
M. KELBERGER
)
v.
)
#72—177
ENVIRONMENTAL PROTECTION AGENCY
)
Opinion
& Order of the Board
(by Mr. Currie):
Mrs. Kelberger’s initial pet:Ltion seeking
a variance
to permit connection of a new home to Waukegan sewers des-P
pite the ban in League of Women Voters
v,
North Shore
Sanitary District,
#70—7,
I PCB 369
(March 31,
l97i~,was
dismissed because,
in light of our decision permitting
additional connections tributary to the Waukegan and Clavey
Road treatment plants
(North Shore Sanitary District v.
EPA, #7l~343, 3 PCB 697
(March
2,
1972)),
there appeared
to be no nee! for a variances
Keiberger v.
EPA,
~72~i77,
4 PCB 477
(May
3,
1972),
An amended petition was filed
with the Agency June 5 and with us on June 14, reciting that
the Sanitary District had refused to issue
a permit for
the connection, notwithstanding the relaxation of our
ban, because the sewer into which the new home would
discharge
had
been
designated
as inadequate to transport
its existing waste load
to the treatment plant and there~
£
ore
was
ineligible
for
additional
connections,
We
scheduled
no
hearing,
believing
the
case
was
simple
enough
to
be
subject
to
decision
upon
the
petition
and
the
Agency’s
recommendation.
See
Minutes
of
Regular
Board
Meeting,
June
20,
1972.
We received the Agency’s
recommendation September
19,
1972,
106 days after the amended petition had been filed
with the Agency and 97 days after
it
had been filed with
us,
The addition of still more wastes to overloaded sewers,
as we pointed out at length in Cook v.
EPA,
#72-178,
.5 PCB
(Aug.
29, 1972), can be a very ~erious matter, as it may
result in raw sewage not only in streams but also in streets
and in basements, with obviously unsavory implications for
public health,
The Agency!s recommendation tells us that
the sewer
in question “is subject to excessive flows from
5
477

—2—
storm water runoff
during periods of wet weather
(which)
have resulted in the past
in illegal bypassing
of untreated wastes and now result in sewer backups sending
untreated wastes into the homes of individua1s.~ The
petition says nothing at all about these adverse effects
of granting the requested variance, although our procedural
rules
clearly require
“a description of the injury that
the grant of the variance would impose on the public,”
PCB Regs,
Ch.
1, Rule 401
(a) (2).
This information is
necessary because to determine whether or not compliance
with the law would impose an “arbitrary or unreasonable
hardship,”
the statutory test for variance, we must
balance the benefits as well as the costs of insisting upon
compliance, and because the burden of proof is on the
petitioner.
See EPA v. Lindgren Foundry Co.,
#70-1,
1 PCB
11
(Sept.
25,
1970).
This failure to plead facts constituting
an essential part of the petitioner’s case would justify
dismissal of the petition as inadequate, see Decatur Sanitary
District v.
EPA,
#71—37,
1
PCB 359
(March 22,
1971)
On the merits, the Agency recommends that we deny the
petition,
inasmuch as many of the actions relied upon to
demonstrate hardship--the purchase of a lot, the signing
of a contract and making of a deposit relative to building
the home,
the sale of her former home,
and
the
storage of
her furniture——were undertaken with knowledge that the sewer
ban was still in effect.
Even though these actions were
taken on the basis of assurances by the ~ayor of Waukegan that
the ban
would soon be lifted, we have held that persons
relying on promises by officials plainly lacking authority
to repeal our orders act at their own risk;
if
the rule were
otherwise any municipal official could effectively repeal
our orders by announcing
a belief that we will repeal them.
Cook v.
EPA,
#72—178,
5 PCB
(Aug.
29, 1972).
Beyond this,
on the basis of precedent the
hardships alleged by Mrs.
Kelberger, since
they fall short of the commencement of
construction, would probably be insufficient
to justify a
variance even if her actions had all taken place before the
sewer ban was imposed.
Cf. Wagnon v.
EPA,
#71-85,
2 PCB 131
(July 26,
1971).
There are several reasons,
therefore, why
this petition ought to be dismissed or denied.
The statute, however,
is quite clear that
“if
the Board
fails to take final action upon a variance request within
90 days after the filing of
the petition,
the petitioner
may
deem the request granted.”
Environmental Protection Act,
section 38.
Although the statute itself requires only that
a
petition
be filed with the Agency,
(section
37)
,
our
procedural
rules,
adopted pursuant to
the
statutory authority
to
adopt “such procedural
rules as
may
be
necessary to
accomplish
the purposes of this Act,” section
26,
require
filing with the
Board
as
well
(PCB
Reas.,
Ch.
1, Rule 401
(a).
As we said in our opinion adopting the rules,
filing a
S
47~

—3—
petition
with
the
Board
at
the
outset
of
the
period
in
which
we
must
act
upon
it
is
indispensable
to
our
proceeding
intelligently.
In
the
Matter
of
Procedural
Rules,
#R
70-4,
1 PCB 43
(Oct.
8,
1970).
Section
26 clearly embraces the
power to prescribe the method of filing in the interest of
providing adequate notice to all interested persons, in-
cluding
the Board that must make the decision.
We believe
that under section 38 of the Act a petition should not be
deemed to have been filed,
for purposes of the running
of the 90—day period,
until it has been filed with both the
Agency and the Board as required by our procedural rules.
Nevertheless, 104 days have elapsed since the amended
petition was filed with the Board, and the statutory period
has passed.
The petition has therefore been granted by
the
passage
of
time;
it
remains
for
us
only
to
confirm what
has already occurred.
The 90—day rule reflects the salutary policy that
government agencies must be made to act with reasonable speed
upon
citizen
petitions
legitimately
brought
before
them.
So
far
as
we
know,
there is no dissent from
this
policy;
there
has
been
considerable
debate
over
the
appropriateness
of
the
draconian
remedy
of
permitting
violations
of
the
pollution
laws,
with
consequent
injury
to
the
innocent
public,
if
govern-
ment
is
slow
to
act,
This
Board,
without
taking
sides
in
that
dispute,
has
several
times
requested
legislation
extending
the
decision
period
to
120
days,
on
the
:hasis
of
extensive
experience
indicating
that
90
days
is
simply
too
short
a
time
to
permit
us
in
many
cases
to
obtain
the
facts
necessary
for
an
intelligent
decision.
When
petitions
come
to
us
they
are
placed
on
the
agenda
for
the
next
weekly
meeting
for
a
decision
whether
or
not
to
authorize
a
hearing.
If
a
hearing
is
authorized,
a
hearinq
officer
must
be
ap~ointed,
a
hearing
date
set
after
consultation
with
the
parties,
and at
least
21
days’
notice of the hearing given
to
parties
and
public.
The
Agency
is
required
by
statute
to
investigate
the
petition
and
file
with
us
its
recommendation.
Although
we
have
required
by
rule
that
this
be done
within
21
days
after
the
petition
is
filed,
the
Agency
has
regularly
been unable
to
meet
the
deadline.
We have
often
urged the Agency to
act
more
quickly,
see,
e.g.,
Metropolitan
Sanitary
District
v.
EPA
#72—110
(5
PCB
)
,
decided
today,
but
the
21—day
period
may be unrealistically short.
Once the recommendation is
filed
a
reasonable
time
should
in
fairness
be
given
the
petitioner to respond, whether in writing or in the hearing.
After the hearing we must await receipt of the transcript,
which we have in most cases been unable to obtain in less
than two or three weeks at best because of the heavy
workload our cases impose upon court reporters.
If the
5
479

—4--
parties wish to file briefs, as is their right,
they
cannot very well do so until after they have received the
transcript.
At each weekly meeting we place on the next
week’s discussion agenda all cases in which final transcripts
and
briefs have been received during the preceding week.
After discussion a Board
member
is assigned to draft an
opinion
and
order
for decision,
in the usual course, the
following week.
Given this schedule of events,
the 90-day rule has
proved impossibly tight in actual practice.
If all goes
well a hearing
can
be held within the first
40 days and
transcripts
and
briefs be received in another month,
leaving us
20 days
to study and decide the case.
With
that we could live reasonably well.
But all too often
matters are not that simple.
An inadequate petition
must be amended.
A recommendation is not ready in time
to
give notice before the hearing.
The parties are not
available or ready for hearing at the desired time.
Additional hearings must be held,
and the hearing officer,
who
is fully employed elsewhere,
cannot sit this week.
The transcript is not received on schedule.
Reply
briefs are required.
The case is a difficult one requiring
extensive Board deliberation.
The list of complicating
factors could go on.
Suffice it to say that in a very
substantial percentage of petitions filed, perhaps
approaching 50,
the case is not ready for considered
decision within 90 days after filing.
Requests for legislative relief have so far founder-
ed upon the unrelated debate over whether
the result of
our
inaction should be a grant or a denial of the variance.
Though all seem to concede that we need an extra
30 days
to perform our duties adequately, we are forced to make
do with
the 90-day rule.
We have in general met with
considerable cooperation from petitioners, recognizing the
desirability of our deciding on an adequate record rather
than
on whatever materials might be before us at the end
of 90 days, who have been willing to waive for a reason-
able period their right to a decision within 90 days.
Whenever possible we have avoided requesting such
waivers, for we do not think it-desirable for the Board
to be put in the position of begging
a party for special
consideration.
To avoid grants by the passage of time we
have in a number of cases rendered decisions prior to the
writing of opinions,
a practice that is not conducive
to intelligent judgment since our understanding of
a case
is often sharpened by the discipline
of explaining our
decision.
On occasion we have been required to render
decisions on the very day on which a transcript or
recommendation was received, which obviously dOes
not
afford adequate time for thoughtful
consideration
of
difficult cases.
Too often,
as in today’s Metropolitan
5
480

—5—
Sanitary District case,
cited above, we have had to decide
without benefit of the Agency’s recommendation,
on the basis
of
a record made by only one party.
By dint of these
unpleasant and unsatisfactory com-
promises with good judicial practice, we have until today,
so far as
we
are aware, managed
to avoid the ultimate
public misfortune of having variances granted by default
without consideration of the merits.
We have done so only
at considerable risk to the soundness of our decisions,
and we once again reiterate our urgent request to the
General Assembly to put aside the unrelated debate over
the
effect of our inaction and give us
a reasonable time period
in which to decide cases.
Notwithstanding the above excursion,
the present case
is not one in
which
there was any reasonable need for more
than the allotted 90 days for decision.
The time often
consumed by a hearing was saved, since no hearing was
scheduled.
The
case was and remains
a simple one that
could and should have been disposed of within less than
half the statutory time.
We cannot fathom how the Agency
and Attorney General managed to take over 100 days after
receiving this petition to prepare and file the two—page
recommendation in this case, especially since the
recommendation consists solely of a recitation of
the
allegations in the petition,
a statement drawn from Agency
records
as to why the sewer was designated inadequate, and
a one-paragraph opinion, without so much as citation of
authorities, as to why the petition should be denied.
Perhaps an hour’s work was involved in preparing it.
Some-
thing simply must be done about the late filing of
recommendations.
It was within the Board’s power, as we have done on
other occasions,
to decide the case without the recommendation.
Although this
is contrary to the strong statutory policy
favoring independent evaluation of the facts,
it is better
than granting a variance by default.
Our process of
discussion and decision is triggered by receipt of the final
materials on which we are to decide,
such as transcripts,
briefs,
and recomraendations, which it is the parties’ res-
ponsibility
to provide in time for us to act.
We.
have
supplemented this trigger with independent searches of the
docket by both the Clerk and the Chairman to discover
petitions on which
the 90 days are about to elapse.
Unfortunately,
it
has not been the Board’s consistent practice
to assign new docket numbers to amended petitions filed after
dismissals or denials, and with its old number this case
escaped notice in ascertaining cases requiring an early
September decision.
We have directed that new numbers be
5
481

—6—
assigned in such situations,
and
that petitions as filed be
placed upon tentative agendas for decision just before the end
of
the
90-day
period,
to
minimize
the
risk
that
cases
will
slip past us in the future.
It would also help if
recommendations
were
filed
in
time
to
be
considered.
ORDER
Ninety days and more having elapsed since the filing
of
the
petition
without
final
action
by
the Board,
the
petition
is
declared
to
have
been
granted
by
default,
and
Mrs.
Kelberger
may
be
issued
a
permit
to
connect
the
pro-
posed
home
in
the
600
block
of
Frolic
Avenue
to
the
adjacent
sewer
notwithstanding
this
Board’s
ban
on
sewer
connections.
I,christan
Moffett,
Clerk
of
the
Pollution
Control
Board,
certif~
that
the
Board
adopted
the
above
Opinion
&
Order
this
~
.~
day
of•~•’
~
‘.
.,,,
,
1972,
by
a
vote
of
L
A~:
•vt’o:,.
-
~1.’./.
6—482

Back to top