ILLINOIS
    POLLUTION
    CONTROL
    BOARD
    June
    6, 1972
    CITY
    OF
    MATTOON
    #72-64
    v
    ENVIRONMENTAL PROTECTION AGENCY
    MR. JOSEPH SPITZ, ATTORNEY FOR CITY OF MATTOON
    MR.
    THOMAS
    J.
    IMMEL, ASSISTANT ATTORNEY GENERAL, ATTORNEY FOR
    ENVIRONMENTAL
    PROTECTION
    AGENCY
    OPINION
    AND
    ORDER
    OF
    THE
    BOARD
    (BY
    SAMUEL
    T.
    LAWTON,
    JR.)
    Pursuant
    to
    Opinion
    and
    Order
    of
    the
    Board
    in
    case
    entitled
    “City of Mattoon v.
    Environmental
    Protection
    Agency,
    #71-8”,entered
    April
    14,
    1971,
    a sewer connection ban was imposed against the City
    of Mattoon in consequer~ceof the city’s failure to have complied with
    the provisions of Regulation SWB-l4, resulting
    in an extreme overload
    of the city’s sewage treatment facilities and the serious and unabated
    pollution of Kickapoo Creek.
    (Prior thereto,
    on November 20,1970,
    the
    Environmental Protection Agency had issued a letter stating that no
    new
    sewer
    connections
    would
    be
    permitted
    until
    effluent
    requirements
    of
    Technical
    Release
    20-22
    had
    been
    met,
    in accordance with the time
    schedule stated
    in
    SWB-14.)
    Our
    April
    14,
    1971 Order provided as follows:
    “1.
    The
    City
    of
    Mattoon
    is
    hereby
    ordered
    to
    submit
    to
    the Environmental Protection Agency, on or before
    September 1,
    1971, final plans and specifications
    for
    the
    facilities required to bring
    its sewage
    collection and treatment facilities into compliance
    with Rules and Regulations
    SWB-14.
    2.
    The City of Mattoon
    is hereby ordered to complete
    the construction of the facilities specified in para—
    graph
    1
    of
    this
    Order
    no
    later
    than
    July
    1,
    1972.
    3.
    The City of Mattoon shall post with the Environmental
    Protection Agency,
    on or before May 14,
    1971,
    a bond
    or other security in a form to be determined by the
    Agency,
    in the amount of $10,000,
    such
    sum
    to be for-
    feited to the State of Illinois in the event that the
    City does not comply with the provisions of this Order,
    as found by the Pollution Control Board in a supplemen-
    tary proceeding.
    4
    653

    4.
    The
    City
    of
    Mattoon
    shall,
    on
    or
    before
    July
    15,
    1971,
    issue without referendum such revenue bonds and/or general
    obligation
    bonds
    as
    may
    be
    necessary
    to
    finance
    the
    design
    and
    construction
    of facilities specified in paragraph
    1
    of this Order.
    5.
    The City of Mattoon shall complete the construction of
    the primary sedimentation tanks for reduction of bypasses
    by September
    1,
    1971.
    ?.
    The City of Mattoon shall not permit the connection of any
    new sewers or other sources of waste to its facilities,
    or any increase in the strength or concentration of wastes
    discharged to its facilities, until it demonstrates to the
    Agency that’~itis in full compliance with the requirements
    of SNB-14 with respectto overloads, bypasses, and the
    provision of advanced waste treatment.
    7.
    The City of Mattoon shall pay to the State of Illinois,
    on or before May 14, l97l~the sum of $1000 a~a penalty
    for violation of the water pollution regulations specifying
    dates for the submission of plans and the letting of contracts
    for construction of sewage treatment facilities.
    On April 10,
    1972, an amended petition for variance was filed with
    the Board requesting that the November 20,
    1970 Environmental Protection
    Agency Order and paragraph
    6 of our Order be varied “so as
    to permit the
    connection of new customers to the City Sewer System”.
    The petition alleges that subsequent to the April
    14, 1971 Order,
    the City has made the following improvements and modifications in its
    sewage treatment facility:
    1.
    Construction of a 60
    foot diameter sedimentation tank used
    for storm water treatment;
    2.
    Construction of a
    60 foot sedimentation tank used for
    secondary
    treatment;
    3.
    Improvement
    of
    all
    primary
    sewage
    pumps
    to
    a
    total
    capacity
    of
    8.4
    million
    gallons
    per
    day.
    All three of the foregoing facilities are installed and presently opera-
    tional.
    The following items of aeration equipment have been added
    to the
    Cityts sewage treatment facilities:
    1.
    Three
    25
    tiorse
    power
    mechanical
    aerators;
    and
    4
    *
    654

    2.
    One
    75
    hoi~e~
    power centrifugal
    blower.
    As
    a
    result
    of
    the
    foregoing
    installations,
    the
    City
    now
    has
    capacity
    for
    providing
    primary
    and
    secondary
    treatment
    for
    4.4
    million
    gallons
    per
    day
    instead
    of
    3.2
    mg/d
    existing
    when
    the
    sewer
    bans were
    imposed
    and
    has
    capacity
    for
    an
    additional
    4,000,000
    gallons
    per
    day
    of combined waste water which can receive primary treatment as compared
    with~~
    7~a±~blewhen the bans were
    imposed.
    On~April
    1,
    1972,
    a referendum was approved by
    the
    voters
    of
    Nat-
    toon providing
    for the issuance and sale
    of
    general
    obligation
    bonds
    in
    the amount of 1.6 million dollars to pay the municipality’s share of
    a
    proposed
    six
    million
    dollar
    improvement
    program
    for
    expansion
    and
    modernization of the City’s sewer system,,
    the
    balance
    of
    the
    funds
    an-
    ticipated to come
    from State
    and Federal grants.
    The program contem-
    plated would bring the program of development within the time schedules
    and effluent standards for tertiary and advanced treatment as provided
    in
    our
    newly
    adopted
    Regulations,
    Chapter
    3,
    Water
    Pollution,
    Part
    IV,
    Sec.
    404.
    The
    petition
    represe~its
    that
    during
    the
    months
    of
    January
    and
    February,
    1972,
    tests made of BOD and suspended solids of the City’s
    effluent show that the treatment plant now produces an effluent of an
    average
    20 mg/l for BOD and 40 mg/l for suspended solids
    (except during
    periods of storm water overflow, which condition has presumably been
    corrected).
    These numbers satisfy BOD limits and approach suspended
    solids limits established for these contaminants by our Regulation
    for the current period prior to the deadline of December 31,
    1973 for
    compliance with tertiary treatment standards of
    4 BOD and
    5 Suspended
    Solids.
    Hardship resulting from the imposition of the sewer connection ban
    is asserted, based on the economic impact on the community consequential
    to the inability to accomodate new industrial and residential uses so
    long as the ban remains in effect and the severe unemployment of
    tradesmen
    and
    building
    personnel
    resulting
    therefrom.
    Testimony
    received
    at the September 22,
    1971 hearing “In Matter of Sewer Connection Bans,
    #R71-19”
    is
    referred
    to
    in
    the
    petition
    and
    incorporated
    by
    stipulation
    in
    the
    present
    record.
    We
    acknowledge
    the
    presence
    of
    hardship
    without
    further proof.
    The remaining problem is what,
    if anything,
    should be
    done
    with
    respect
    to
    the
    lifting
    of
    the
    ban
    in
    consideration
    of
    the
    impact of such removal on the public welfare.
    The petition for variance states that all by-passing of untreated
    sewage
    has
    been
    completely
    eliminated
    and
    that
    the
    City
    now
    has
    a
    total pumping capacity of 8.4 million gallons per day.
    The City’s
    primary and secondary treatment capacity
    is now 4.4 million gallons
    per day, reflecting an increase of 1.4 million gallons per day, and the
    ability to give primary treatment to
    4 million gallons of storm water
    per day, an increase of 3.2 million gallons per day over what was the
    rapacity on the date of the sewer ban Order.
    4
    655

    Petitioner represents that its anticipated constructien prograi~
    will meet the newly established requirements of Chapter III for ter-
    tiary
    treatment
    before
    the
    December
    31,
    1973
    deadline.
    The
    Agency
    recommendation
    confirms
    the
    pumping
    capacity
    figures
    above
    set
    forth
    with
    respect
    to
    primary
    and
    secondary
    treatment
    and
    the character of
    the effluent during the testing period resulting in
    a BOO of 20 and a Suspended Solids average of 40.
    The recommendation
    notes that presently no chlorination facilities have been installed
    which
    will
    be
    required
    pursuant
    to
    Rule
    405
    of
    the
    new
    regulations
    by
    July
    31,
    1972.
    The
    recommendation
    observes
    that
    a
    BOO
    of
    4
    and
    a
    Suspended
    Solid
    limit
    of
    5
    will
    be
    met
    prior
    to
    the
    December
    31,
    1973
    deadline,
    and
    that
    with
    the
    exception
    of
    the
    lack
    of
    chlorination
    and suspended solid content of the plant’s effluent, petitioner will
    be in compliance with the July, 1972 deadliness
    completion dates will be met by December 31, 1973 with respect to all
    tertiary
    and
    advanced
    treatment.
    The
    recommendation
    of
    the
    Agency
    states,
    in
    part,
    as
    follows:
    “14.
    In view of the new Regulations and the facilities which
    the petitioner has provided since the Board Order,
    the
    Agency
    would
    recommend
    that
    the
    Board
    completely
    remove
    the
    ban
    and
    relinquish
    jurisdiction
    over
    the
    case,
    if
    it
    were
    not
    for
    the
    chlorination
    and
    suspended
    solids
    problems.
    15.
    Once
    these
    problems
    have
    been
    resolved
    and
    approved
    final
    completion
    schedules
    have
    been
    submitted,
    regular
    Agency
    permit
    procedures
    can
    be
    resumed
    and
    will
    assure
    that
    new
    connections
    will
    not
    overload
    the
    treatment
    facilities and cause pollution of Kickapoo Creek.”
    The
    ultimate
    recommendation
    of
    the
    Agency
    is
    as
    follows:
    “16.
    Based
    on
    the
    improved
    facilities
    and
    enlarged
    capacity,
    and
    the
    Water
    Pollution
    Control
    Regulations
    adopted
    March
    7,
    1972,
    the
    Agency
    recommends
    that
    the
    Board
    retain jurisdiction and grant a variance subject to
    the
    following
    conditions:
    1.
    The operation of the new facilities
    is improved to
    meet the suspended solid standard of
    25
    (based on a
    30
    consecutive
    day
    average),
    2.
    The
    petitioner
    installs
    and
    operates
    chlorination
    facilities and,
    4
    656

    3.
    The
    Petitioner
    files
    an
    approved
    project
    comple-
    tion
    schedule
    according
    to
    Rule
    1002-b-u.
    17.
    The Agency requests that it be authorized to issue
    conditional installation permits
    (construction allowed
    but connection prohibited)
    but that no connections be
    allowed until condition #1
    and
    2 are satisfied1
    and
    petitioner can show to the satisfaction of the Agency
    that additional connections will not violate the Act
    or
    any
    applicable
    Regulations.
    18.
    The Agency further requests that the Board retain juris-
    diction only until the Agency.notifies it that conditions
    1,
    2 and
    3 have been satisfied.
    19.
    The Agency reserves the right to modify or revoke its
    recommendation prior
    to
    the
    close of the Record on this
    matter.”
    Hearing was held on the petition and recommendation in Mattoon
    on April
    17,
    1972.
    Testi~monyconfirmed
    the
    capacities for primary
    and secondary treatment and for storm water treatment
    (R,
    14),
    and
    the installation of additional pumping systems,
    sedimentation tanks,
    aeration facilities and blower.
    At
    the present time there is no
    storm water by-passing of the sewage treatment plant nor the main out-
    flow approximately 300 feet upstream of
    the
    sewage treatment plant
    (R.
    15).
    Total cost to date for the improvements installed has been
    approximately $326,000.00.
    (R.
    16).
    Since receipt of the Agency
    recommendation, plans and specifications for the purchase of chlorina-
    tion equipment have been prepared and a new pump is being installed
    which will bring suspended solids down to the 25 mg/I limit.
    Chlorina-
    tion facilities will be installed by July
    31,
    1972.
    The new sewage treatment plant facilities to be constructed and
    in operation by approximately September
    1,
    1973 are designed to increase
    the present capacity to accommodate a peak flow of 12,000,000 gallons
    per day with complete tertiary treatment and chlorination, and will pro-
    vide an additional 12,000,000 gallons per day for storm water retention
    and treatment.
    Chlorination will be provided for all flows
    (R.
    46).
    It is anticipated this will accommodate a fifteen-year period
    of growth and will cost $6,040,000.
    Interim chlorination will cost
    between $10,000
    and $12,000.
    (R. 47).
    The new facilities, when
    completed, will entirely eliminate the possibility of non-treated storm
    water reaching Kickapoo Creek.
    4
    ci~ci

    Tests introduced by the Agency confirm the great iiüprovement
    in BOD and suspended solid limits but disclosed the presence of high
    fecal coliform readings,
    the abatement of which requires the chiorini-
    ation
    process.
    (R.
    58 through
    64, Agency Exhibits
    I through
    5).
    In the opinion of the Agency witness, the installation of a new sludge
    pump would enable compliance with the 25 MG/I Suspended Solids limits~
    A witness from the Mattoon League of Women Voters recommended
    the lifting of the sewer ban subject to the City complying with the
    construction deadlines and effluent limits,
    as well as the conditions
    proposed by the Environmental Protection Agency.
    The witness also
    recommended
    the
    adoption
    of
    a
    sewer
    surcharge
    ordinance
    to
    “assure
    a
    system
    of
    equitable
    cost
    recovery
    for
    the
    citizens
    of
    Mattoon.”
    (R.
    79)
    On March
    28,
    1972,
    the
    Board
    granted
    a
    partial
    lifting
    of
    the
    sewer
    ban
    to
    permit
    connection
    by
    Kraft
    Food
    Division
    of
    Kraftco
    Corporation,
    (#7l~388),
    subject:
    to certain specified terms
    and
    con~
    ditions,
    including
    pre-treatment
    and
    the
    installation
    and
    operation
    of in-plant facilities to minimize the hydraulic
    and
    organic
    impact
    on
    the
    Mattoon
    sewers.
    We
    believe
    that
    petitioner’s
    program of
    improvement
    since
    the
    imposition
    of
    the
    sewer
    ban
    to
    bring
    its
    effluent
    to
    tolerable
    limits
    approximating
    those
    which
    are
    required
    by
    regulation,
    together
    with
    the
    installation
    of
    chlorination
    facilities
    and
    a
    new
    sludge
    pump,
    as well
    as
    its
    overall
    program
    of
    improvement
    to meet the December,
    1973 deadlines for tertiary treatment,
    justify a lifting of the
    sewer ban,
    subject
    to
    the
    terms and conditions set forth in our Order~
    The
    hardship
    imposed
    on
    the
    community
    and
    its
    citizens
    resulting
    from
    the
    suspension
    of
    construction
    is
    manifest,
    and
    we believe
    the
    public
    interest
    will
    be
    protected
    upon
    suspension
    of
    the
    sewer
    ban
    by
    what
    the
    City
    has
    already
    achieved
    and
    by
    what
    it
    will be obliged
    to
    do
    in
    the
    future.
    We
    adopt
    the
    conditions
    proposed
    by
    the
    Agency
    with
    the
    exception
    that
    we
    do
    not
    require
    the
    installation
    of
    all
    necessary
    facilities
    for
    chlorination
    and suspended solids improve-~
    ments
    prior
    to
    lifting
    the
    ban,
    but
    will
    require
    that
    these
    conditions
    be
    met
    as
    a
    basis
    for
    the
    continuation
    of
    the
    sewer
    ban
    suspension.
    As
    we
    did
    in
    the
    original
    case,
    we
    must
    again
    recognize
    the
    valuable
    input
    of
    the League of Women
    Voters
    of
    Mattoon.
    Its state-
    ment in
    this case recommended granting of the relief to the City
    on
    three
    conditions:
    1.
    That the City meet the conditions recommended by the
    Agency;
    4
    658

    2.
    That the City file monthly progress reports to the
    Board; and
    3.
    That the City write a sewer surcharge ordinance to
    comply with Federal regulations.
    The substance of
    the
    first
    two
    suggestions
    will
    be
    incorporated
    in our Order although not precisely in the form proposed.
    The third
    suggestion, of a sewer surcharge ordinance,
    is indeed a good one.
    In
    order to obtain Federal funds, the City must, among other things, make
    sure that industry
    is paying its fair share of the treatment costs.
    A sewer surcharge ordinance is on~way to assure compliance with the
    Federal regulations and we strongly suggest that the City give con-
    sideration to its adoption.
    This opinion constitutes the findings of fact and conclusions
    of law of the Board.
    IT
    IS THE
    ORDER of the
    Pollution
    Control
    Board
    that
    the
    sewer
    connection ban orders en~eredby the Environmental Protection Agency
    on November 20, 1970 and by the Pollution Control Board on April
    14,
    1971 be and the same
    are
    hereby
    terminated, subject to the following
    terms
    and
    conditions:
    1.
    Facilities shall be installed to assure compliance
    with
    a suspended solids standard of 25 mg/l by
    July
    31,
    1972.
    2.
    Chlorination facilities shall be installed by~July31,
    1972
    that
    will
    bring
    fecal-coliform
    counts
    into
    com-
    pliance with existing regulations.
    3.
    The
    project
    completion
    schedule
    shall
    be
    filed
    in
    accou~ancewith
    Rule
    1002—b-u
    for
    all
    construction
    required to be completed to meet secondary and tertiary
    sewage
    treatment
    standards
    as
    provided
    by
    Regulation.
    4.
    The Board retains jurisdiction for such other and further
    Ordersas shall be appropriate, including the right to
    reinstate the sewer ban when hydraulic or organic effluent
    limits are shown
    to have been exceeded, pursuant to
    hearing
    by
    the
    Pollution
    Control
    Board.
    4
    659

    5.
    The City of Mattoon shall post with the Environmental
    Protection Agency, on or before July
    6,
    1972,
    a bond or
    other security in a form to be determined by the Agency,
    in the amount of $25,000.00,
    such
    sum
    to be forfeited
    to the State of Illinois in the event that the City does
    not
    comply
    with
    the
    provisions
    of
    this
    Order,
    as
    found
    by
    the
    Pollution
    Control
    Board
    in
    a
    supplementary
    proceeding.
    I,
    Christan Moffett,
    Clerk of the Pollution Control B a
    ~,
    certify
    that
    the
    above
    Opinion
    and
    Order
    was
    adopted
    on
    the
    ‘Iday
    of
    June,
    1972,
    by
    a
    vote
    of
    to
    4
    660

    Back to top