ILLINOIS POLLUTION CONTROL BOARD
September 6, 1972
RICHARDSON CO.
)
V.
)
##72—41,72—l44
3
ENVIRONMENTAL PROTECTION AGENCY
Mr. Douglas T. Moring, Assistant Attorney General, for
Environmental Protection Agency
Mr. Alan Abrams, for the Richardson Co.
Opinion of the Board (by Mr. Currie)
Richardson applied to us for a variance to permit
continued operation of its ~henolic laminate plant in DeKalb
until December, 1972 while completing an emission control
program approved by our predecessor the Air Pollution Control
Board. We granted the variance only until September 9 be-
cause of doubts as to whether the company should have
accelerated the purchase of the last incineration equipnent, requir-
ed by the program, expressly inviting further proceedings in which
if our doubts were answered the variance could be extended
to December. Richardson Co. v. EPA, #72—41 (May 3, 1972).
The Agency had in the meantime filed a complaint against
the company alleging particulate violation
(#
72-14 4)
,
the
company filed a request for extensionof the variance, the
two matters were consolidated, and a hearing was held.
The original compliance program contemplated installation
of afterburners to reduce solvent and other emissions from
phenolic laminate treaters. The first unit was installed but
proved defective (see Stipulation, p. 4)
.
The initial
variance petition contemplated the rebuilding of the defective
unit by July 1972, which has since been accomplished (id.,
p. 7)
,
and the ordering of the remaining equipment in time
for completion by the end of 1972 “if granted sufficient time.”
We indicated that this seemed to imply that Richardson was
delaying in curing its pollution problems until it obtained
a variance and made clear that this would be no excuse.
We asked for an explanation of why the equipment was not
ordered earlier.
The record does indicate that Richardson was motivated
at least in part by the desire to get approval of continued
operation before making the necessary commitments to clean
up (R. 30). To the extent that such was the case, it does
5
—
345
—2—
not represent diligent action to abate pollution as rapidly
as is practicable as the law requires. We appreciate the
company’s reluctance to spend substantial sums only to dis-
cover later that it must shut down its plant and make the
expenditures in vain. But such a prospect misconceives
what actually happens when variances are denied. The in-
stances in which this Board has ordered going businesses
closed for polluting are few indeed; the almost invariable
practice, in the absence of a most considerable nuisance or
health hazard or utter disregard of the law, is to leave
the petitioner open to money penalties commensurate with the
seriousness of the delay but to permit continued operation.
See, e.g., Marquette Cement Mfg. Co. v. EPA, *70-23 (Jan.
6, 1971). We emphasize once more that we expect those who
petition for variances approving deferred compliance to
proceed posthaste, as many have done, see, e.g., A.E. Staley
Mfg. Co. v. EPA, #71-174 (Sept. 30, 1971), to achieve com-
pliance as soon as possible while their petition for variance
is being considered.
We find, however, that in the present case the delay was
to a significant extent mitigated by the company’s legitimate
concern that the bugs should be taken out of the first
incinerator before substantial sums were committed for the
purchase of more of the same equipment (R. 39—42). The
timetable Richardson was following, moreover, was such as
to achieve compliance, despite the delay, within the period
approved by the predecessor Board. (See Exs. 7, Il)
Finally, the remaining equipment was promptly ordered upon
entry of our earlier order (R. 42)
.
Under these facts we
think no great purpose would be served by requiring the
payment of a penalty for this relatively brief delay or by
leaving the company open to a further prosecution on that
account. The variance will therefore be extended to
December 1972, the earliest date on which the program can
now be completed (R. 51-52).
The Agency’s complaint is based upon a different matter.
Agency evidence brought out, and the company conceded, that
the incinerators as presently designed will control emissions
only from the curing ovens and not from other sources such
as dip trays and recirculation tanks, from which the evidence
is clear certain gaseous contaminants are emitted. (R. 18—19,
42-43, Ex. 28). The Agency asks us to require control of
these sources as well. The company responds that from
preliminary sniffing at vents on the roof it believes
these emissions will not independently cause any odor problem
but declares itself willing and able to connect these sources
to the incinerators if a problem should be found to exist in
lhe future (R. 42-43). Ascertaining whether or not there
will be such a problem is complicated by the fact that the
more obvious oven emissions have not yet all been brought
under control.
5
—
346
—3—
The principal difficulty with the Agency’s case is that
the only violation charged is under the process weight table
of Rule 3—3.111 of the old air regulations, which expressly
applies only to particulate emissions. The evidence is that
the only particulate emissions from the plant come from the
curing ovens (Ex. 28)
,
which are covered by the company’s
existing program. Emissions from the dip trays and re-
circulating tanks, so far as the evidence shows, are entire-
ly of gaseous solvents (Id.) and therefore not covered by
the rule in question. There was no allegation ‘of statutory
air pollution, and indeed no adequate proof that existing
odors were caused even in part by these sources rather
than by the ovens themselves (R. 21). But the basic princi-
ple that governs here is that the Agency may not allege one
violation and prove another, for to do so deprives the res-
pondent of the notice indispensable to a meaningful oppor-
tunity to defend. See EPA v. McHugh, Healy & Keeny Con-
struction Co. & City of Chicago, (# 71—291) (May 17, 1972).
We therefore find the EPA has failed to prove any violation it
has alleged.
The evidence does establish, however, that there are possibly
significant odor sources within the plant that are not be-
ing controlled by the present program, even though the
original compliance program (See Ex. 3) did indicate an
intention to deal with emissions from the “coating head
and oven combination.” We think it appropriate, therefore,
to ma’Ke it a condition of the variance that the Intent of
the original program be carried out insofar as is necessary
to prevent an odor nuisance. If such a nuisance continues
to exist as a result of other sources after the ovens are
fully controlled, the company will be required to connect
those sources expeditiously to the afterburners and to take
any other steps necessary to eliminate the problem. Cf.
Greenlee Foundries v. EPA, #70-33 (March 17, 1971).
ORDER
1. The complaint in #72—144 is hereby dismissed for want
of proof of the violation alleged.
2. The variance granted to Richardson Co. (#72-41) May 3,
1972 is hereby extended to December 31, 1972, subject
to all conditions
of the order of May 3, 1972 and to the
following additional condition:
3. In the event that an odor problem continues to exist
after completion of the installation of afterburners on
the curing ovens, Richardson shall expeditiously take
such steps as are necessary and practicable to abate
such problem, including the duct~ing of emissions from
the dip trays and recirculating tanks to the afterburners.
5
—
347
—4—
I, Christan Moffett, Clerk of the Pollution Control Board,
certify that the Board adopted the above Opinion this
__________day of September,
1972, by a vote of
d/_C~
4’
7/
5
—
348