ILLINOIS POLLUTION CONTROL BOARD
August
29, 1972
ILLINOIS POWER CO.
v.
)
#72—297
ENVIRONMENTAL PROTECTION AGENCY
Preliminary Order of the Board
(by Mr. Currie)
This petition seeks a modification of the variance we
granted September 30,
1972,
allowing Illinois Power to operate
its Hennepin generating station while completing a program
approved by the old Air Pollution Control Board to bring its
particulate emissions into compliance with that Board’s
regulations
(Illinois Power Co.
v. EPA,
#71—193).
Under
that program Hennepin Unit #2 was to be controlled
by
a high-
ly efficient precipitator by June 30,
1972,
and Unit #1, which
was not to be as effectively controlled, was to be operated
on such fuels and at such capacities
that emissions from the
two units through
a common stack would not exceed regulation
limits after the June 1972 date.
The company now informs
us that
a deteriorating natural gas supply situation and
increasing potential for electric supply problems may make
it necessary in “very
limited situations”
to operate the
poorly-controlled Unit #1 by itself,
in violation of the
regulations, when #2
is out of service.
At the same time,
the
company has decided to install a 99.5
precipitator on
#1 in order to eliminate this problem and to comply with our
new and more restrictive regulations.
A variance is sought
to allow occasional operation of Unit #1 in excess of regu-
lation limits until June 30,
1974, when the new precipitator
is to be completed.
We scheduled no hearing,
believing that the issue re-
lating to this substantially improved control program could
probably be resolved on the basis of the petition and the
Agency’s recommendation.
That recommendation,
however, raised
a significant factual issue on which we should appreciate
the company’s response.
The Agency maintains that Illinois
Power stated, after filing the petition,
that construction
of the precipitator was expected to be completed no later
than February of 1974,
and that in another communication to
the Agency the company declared that bids had been sent out
some six months in advance of the date contemplated even by
5
—
309
—2—
the February 1974 completion schedule.
Consequently EPA
asks that the terminal date for construction be placed at
September,
1973, with compliance by November 1,
1973 rather
than June 30, 1974 as requested by
the company.
This
difference is important,
as the law requires compliance
as
soon as
is practicable.
We invite the Agency to submit within twenty days written
or sworn documentation of these facts so they may be con-
sidered as in evidence and request the company to respond
within twenty days with whatever additional argument or
factual material, supported by affidavid or documentation,
may be necessary to our decision.
We also call the com-
pany’s attention to the other specific conditions the Agency
asks us
to impose on the grant of any variance and invite its
response.
Should the company desire the opportunity to
present evidence in a formal hearing in support of its
petition, we shall be glad to authorize such
a hearing pro-
vided an appropriate waiver is filed extending the 90-day
period in which otherwise we are required to render a
decision.
It
is
so ordered.
I, Christan Moffett, Clerk of the Pollution Control Board,
certify that the Board adopted
the above Prelimin~ryOrder
this
~
day of August,
1972 by a vote of
~
C
5
—
310