ILLINOIS POLLUTION CONTROL BOARD
    August
    29, 1972
    ILLINOIS POWER CO.
    v.
    )
    #72—297
    ENVIRONMENTAL PROTECTION AGENCY
    Preliminary Order of the Board
    (by Mr. Currie)
    This petition seeks a modification of the variance we
    granted September 30,
    1972,
    allowing Illinois Power to operate
    its Hennepin generating station while completing a program
    approved by the old Air Pollution Control Board to bring its
    particulate emissions into compliance with that Board’s
    regulations
    (Illinois Power Co.
    v. EPA,
    #71—193).
    Under
    that program Hennepin Unit #2 was to be controlled
    by
    a high-
    ly efficient precipitator by June 30,
    1972,
    and Unit #1, which
    was not to be as effectively controlled, was to be operated
    on such fuels and at such capacities
    that emissions from the
    two units through
    a common stack would not exceed regulation
    limits after the June 1972 date.
    The company now informs
    us that
    a deteriorating natural gas supply situation and
    increasing potential for electric supply problems may make
    it necessary in “very
    limited situations”
    to operate the
    poorly-controlled Unit #1 by itself,
    in violation of the
    regulations, when #2
    is out of service.
    At the same time,
    the
    company has decided to install a 99.5
    precipitator on
    #1 in order to eliminate this problem and to comply with our
    new and more restrictive regulations.
    A variance is sought
    to allow occasional operation of Unit #1 in excess of regu-
    lation limits until June 30,
    1974, when the new precipitator
    is to be completed.
    We scheduled no hearing,
    believing that the issue re-
    lating to this substantially improved control program could
    probably be resolved on the basis of the petition and the
    Agency’s recommendation.
    That recommendation,
    however, raised
    a significant factual issue on which we should appreciate
    the company’s response.
    The Agency maintains that Illinois
    Power stated, after filing the petition,
    that construction
    of the precipitator was expected to be completed no later
    than February of 1974,
    and that in another communication to
    the Agency the company declared that bids had been sent out
    some six months in advance of the date contemplated even by
    5
    309

    —2—
    the February 1974 completion schedule.
    Consequently EPA
    asks that the terminal date for construction be placed at
    September,
    1973, with compliance by November 1,
    1973 rather
    than June 30, 1974 as requested by
    the company.
    This
    difference is important,
    as the law requires compliance
    as
    soon as
    is practicable.
    We invite the Agency to submit within twenty days written
    or sworn documentation of these facts so they may be con-
    sidered as in evidence and request the company to respond
    within twenty days with whatever additional argument or
    factual material, supported by affidavid or documentation,
    may be necessary to our decision.
    We also call the com-
    pany’s attention to the other specific conditions the Agency
    asks us
    to impose on the grant of any variance and invite its
    response.
    Should the company desire the opportunity to
    present evidence in a formal hearing in support of its
    petition, we shall be glad to authorize such
    a hearing pro-
    vided an appropriate waiver is filed extending the 90-day
    period in which otherwise we are required to render a
    decision.
    It
    is
    so ordered.
    I, Christan Moffett, Clerk of the Pollution Control Board,
    certify that the Board adopted
    the above Prelimin~ryOrder
    this
    ~
    day of August,
    1972 by a vote of
    ~
    C
    5
    310

    Back to top