ILLINOIS POLLUTION CONTROL
    BOARD
    August
    29, 1972
    MARK E.
    COOK
    v.
    )
    #72—178
    ENVIRONMENTAL PROTECTION AGENCY
    )
    COMMUNITY UNIT SCHOOL DISTRICT NO.
    60
    LAKE COUNTY,
    ILLINOIS
    v.
    )
    #72-223
    ENVIRONMENTAL PROTECTION AGENCY
    #72-178 JOHN R. SLOAN APPEARED FOR PETITIONER
    RICHARD W.
    COSBY, ASSISTANT ATTORNEY GENERAL, APPEARED FOR THE ENVIRONMENTAL
    PROTECTION AGENCY.
    #72-223 FREDERICK D. RAWLES AND DANIEL M. LONCHER,
    JR. APPEARED FOR PETITIONER.
    RICHARD W.
    COSBY, ASSISTANT ATTORNEY GENERAL, APPEARED FOR THE ENVIRONMENTAL
    PROTECTION AGENCY.
    OPINION AND ORDER OF THE BOARD
    (BY SAMUEL T.
    LAWTON,
    JR.)
    This opinion
    is
    in support of our order of August
    28,
    1972 in #72-223
    granting the variance sought and our order of August 29,
    1972 in #72-178
    denying the petition for variance.
    Both cases are variance requests seeking permission in each instance
    to connect a single family residence structure to facilities tributary to
    the Waukegan Sewage Treatment Plant of the North Shore Sanitary District.
    In both cases
    the sewer to which the house would be connected has been
    classified as over—loaded by the E.P.A.,
    and the sewer connection permit
    accordingly denied, notwithstanding our recent partial lifting of
    the
    sewer connection ban, with respect to the Waukegan plant originally imposed
    in our decision of March
    31,
    1971
    in case
    LWV
    vs.
    NSSID 70-7.
    Both homes were constructed subsequent
    to the imposition of the
    March
    31,
    1971 sewer connection ban.
    In both cases petitioners have con-
    tended that denial of the variance will impose upon
    them
    unreasonable and
    arbitrary hardship, justifying an allowance of the connection sought.
    While
    there are some similarities in the two proceedings there are
    also substantial differences justifying the reaching of different conclu-
    sions
    in each case.
    The variance petition with respect to Mark E. Cook
    is denied.
    The variance petition with respect to Community Unit School
    District No.
    60, Lake County is granted.
    The reasons for what might appear
    to be inconsistent conclusions are discussed below.
    Mark E. Cook filed his original petition for variance on April
    24,
    1972,
    simply asking permission to connect the house built by him to facili-
    ties tributary to the Waukegan plant.
    On May 3,
    1972, we entered an order
    referring to our partial lifting of the sewer connection ban of March
    2
    1972 statinci that,
    for all that appeared in the petition, Cook would be
    5
    287

    entitled to a sewer connection permit as a result of the March
    2,
    1972
    order.
    The petition was dismissed as moot.
    On
    June
    2,
    1972 Cook sent
    to the Board a letter from H.
    W.
    Byers, General Manager of the North
    Shore Sanitary District dated May 11,
    1972, advising him that the sewer
    to which connection was sought had been designated inadequate by the
    E.P.A., and that a connection permit would be denied.
    The variance peti-
    tion was redocketed and hearing held July 13,
    1972.
    No recommendation has been filed to date by the E.P.A., although
    Agency counsel appeared at the hearing in opposition to the petition.
    Cook’s position can best be summarized in the language of his
    attorney:
    “He relied basically upon information received from City
    of Waukegan officials and newspaper accounts relating to the
    the removal of the sewer ban in Waukegan, and built a house
    that was completed after the sewer ban was partially lifted
    in Waukegan, requested a hook-up from the North Shore Sani-
    tary District and was denied based on the fact that the E.P.A.,
    had declared this sewer area as being incapable of transport-
    ing waste.”
    CR5).
    The subject property located at 513 Baldwin in Waukegan was im-
    proved for use by petitioner’s daughter.
    Construction appears
    to have
    started around January
    1,
    1972.
    (RlO)
    .
    Petitioner acknowledged that at
    the time of construction he knew the sewer ban was
    in effect but relied
    on statements made by the Mayor of Waukegan, the City Building Com-
    missioner, petitioner’s plumbing contractor and newspaper accounts all
    to the effect that the sewer ban would be terminated.
    (Rll).
    Apparently
    other properties not the subject of this proceeding are also proposed
    for development by the petitioner in reliance to the foregoing representa-
    tions.
    At no time did petitioner make inquiry of either the North Shore
    Sanitry District or the E.P.A.,
    with respect to the status of the
    sewer ban or the condition of the sewer to which the connection was
    sought.
    Some inquiry was made of the North Shore Sanitary District
    after March 11,
    1972,
    when the partial lifting of the sewer ban took
    place, but only after the house had been erected.
    Petitioner represents that the fair cash market value of the house
    as completed will be $30,000,
    and that approximately $13,550.00 remains
    owing by petitioner to the seller of the lot and to sub-contractors.
    Contracts for other properties
    to be improved by petitioner were
    introduced
    in evidence although it
    is not clear whether these lots
    would be subject to the same prohibition as the subject property.
    In any
    event petitioner contends that the capital tied up in the Baldwin propert~j
    and the jeopardy placed on his credit standing prevents him from pursuing
    his trade.
    Mrs. Cook has been subject to hospitalization and surgery in
    recent months, which has imposed additional financial burden on petitioner
    On crr,ss examination Cook acknowledged that the property was pur-
    chased in October of 1971,
    and that at that time he was aware of the im-
    position of the comprehensive sewer ban pursuant to our order of March
    31,
    5
    2
    88

    1971.
    (R27)
    .
    At the time petitioner received his building permit from
    the Waukegan Building Department he was advised that a sewer hook-up
    could not be granted, although Building Department officials stated on
    that date that the sewer ban would be lifted.
    According to Cook the City
    Officials stated with respect to
    the
    sewer ban,
    “What are you waiting for?
    Go ahead,
    it’s all going to be rolled up.
    We1re going to throw the whole
    thing over.
    Go ahead, Cook.”
    (R3l).
    Installation of a septic tank on the property was considered un-
    acceptable
    by the Lake County Health Department and installation of
    a
    holding tank, while physically possible was deemed unduly expensive both
    in cost of installation and servicing.
    Alsq difficulties would be en-
    countered in the ultimate disposal of wastes.
    Evidence was introduced
    that the subject property would generate 200 gallons of effluent per day and
    possibly less,
    (R60)
    which in the judgment of the witness would have a
    trivial effect on the over-all hydraulic flow handled by the sewer.
    In
    dry weather no over-flow problem would exist, but some adverse effect might
    result in periods of wet weather flow.
    (R62).
    However,
    in the judgment
    of the same witness the sewer is not adequate to serve as a combined sani-
    tary and storm sewer if excessive amounts of storm water infiltrated into
    it.
    (R63)
    Complaints were noted from residents connecting to the subject sewer
    during periods of heavy rainfall, presumably resulting in back—up of sewer
    connections into their homes.
    CR65).
    Testimony was received in the record
    indicating the basis on which sewers subjected to overload were determined.
    Those which could not accommodate normal flow during wet weather without
    by-pass or back-up were “black listed” by the E.P.A.
    On the particular sewer in question manholes
    were bolted down in an
    effort to eliminate over-flow which nevertheless became cracked and enabled
    sewer discharge of fecal and other matter.
    CR80).
    Observations of this
    sort were made in the vicinity of the sewer between April 18 and July
    10,
    1972.
    The particular sewer in question is designed as a sanitary sewer only
    and is not built to accommodate storm
    water
    flow, although storm water in-
    filtrates
    into the sewer during periods of wet weather.
    No effort was made
    to determine what impact the waste from petitioner’s residence would have
    on the environment, beyond that previously mentioned.
    The Community Unit School District No.
    60
    is also located in Waukegan.
    As a part of its Vocational Building Trades program students participating
    in the program have constructed single family residences on property pur-
    chased by The Board of Education.
    Construction takes place over
    a one to
    two year period.
    The home
    is worked on by students enrolled in the building
    trades classes, the vocational electric class,
    the interior design class,
    and the agriculture and biological occupation classes.
    Approximately 100
    students engage in the construction of the home.
    Upon its completion, the
    home is placed on the market and sold.
    Proceed~of the sale are used to
    finance the purchase of land and materials .~orturther construction of future
    homes as part of the Building Trades program.
    The subject property of the present petition was purchased on July
    8,
    1971 for $5,475.00, and was the eighth such project of the program.
    Con-
    struction was started in September of 1971 and is substantially completed.
    At
    the time of the purchase a sewer connection had already been
    stubbed
    by
    the
    prior owner into the Waukegan Municipal Sanitary System, but was not hooked up
    5
    289

    and no permit for connection or use had been issued.
    While the
    lot in question would otherwise be eligible for a sewer conneàtio~~r:t.
    pursuant to our partial lifting of the sewer connection ban on
    March
    2,
    1972,
    the property would connect to a sewer found to be
    overloaded which again precludes the granting of a permit.
    Petitioner alleges that if the sewer connection is denied
    the house cannot be sold.
    Funds for continuation of the program
    from other sources are not available and the entire Vocation
    Building Trades program would be terminated.
    In addition the
    District will incur a substantial monetary loss resulting from
    the investment
    in materials.
    The petition concludes that denial of
    the permit will have
    a substantial detrimental effect on the public
    welfare, disproportionate with the detriment caused by the addi-
    tional sewage
    flow generated from the house.
    The E.P.A. recommends that the variance be allowed subject
    to proof that the sale of the structure
    is necessary to the con-
    tinuation of the Building Trades program and that
    the
    petitioner
    obtain
    one
    of
    the
    connection
    permits
    previously
    authorized
    for
    the
    Waukegan
    plant.
    A
    stipulation
    of
    facts
    was
    entered
    into
    with
    respect
    to
    the
    essential allegations of the petition.
    Hearing was held on the
    petition on July 22,
    1972,
    at which time the Vocation Building
    Trades program and the method of financing were described in de-
    tail.
    The testimony supported the contention of the District that
    the sale of the house was necessary to assure continuation of the
    program and that no funds were available in the education fund to
    pursue this program in the absense of such sale.
    The educational
    fund is presently operating at a deficit.
    Approximately $24,000
    has been expended for land and materials and the fair market value
    of the house is considered to be approximately $30,000.
    Land has
    been purchased for new residences
    to be constructed pursuant to
    the program and students have been registered for the coming fall
    classes in this respect.
    In addition to the inability to proceed
    with the program the testimony indicates that failure to hold the
    class will entail some loss of State revenue.
    CR15).
    Testimony indicated that 400 gallons per day of effluent
    would be generated by the house.
    The sewer could accommodate 624,000
    gallons per day.
    In
    the
    judgment of the witness the effluent flow
    from the house would be “nil”
    so far as its effect on the sewer system.
    While the sewer has been classified as overloaded there is no evi-
    dence that the proposed connection would create over—flow, back—up
    or by-pass.
    CR22).
    The District’s business manager testified that a deficit in
    the education fund in excess of a million dollars
    is
    anticipated.
    (R29’
    Inability to sell the subject property would cause termination of
    the Building Trades program,
    as funds would not be available from
    any other source, other than the money received on sale of the oremi~cs.
    —4--
    5
    290

    The
    two
    cases
    present
    obvious
    difficulties
    of
    reconciliation.
    In
    Cook
    the
    petitioner
    got
    bad
    advice
    and
    followed
    it.
    In
    Community
    Unit School District, for all that appears on the record,
    no advice
    was sought or received.
    In both cases the land was purchased and
    construction begun subsequent to the imposition of the sewer ban.
    In both cases the properties are located in areas that would be
    eligible for permits as a consequence of our partial lifting of
    the sewer ban with respect to the Waukegan plant.
    However,
    in
    each case the effluent from the particular house would be directed
    to a sewer that has been classified by the E.P.A.
    as overloaded and
    a permit denied for this reason.
    The condition of overload is the
    fault of the City of Waukegan which has failed to keep its sewers
    in satisfactory condition,
    and whose officials told Cook to ignore
    our sewer ban order.
    In
    both
    cases
    hardship
    exists
    so
    far
    as
    the petitioner is
    concerned.
    However, the central issue in both cases,
    as in all
    variance cases,
    is whether hardship is of
    a degree sufficient to
    justify
    a variance.
    Stated otherwise,
    the issue
    is whether the
    hardship on the petitioner if denied the variance substantially
    outweighs the burden on the public if the variance is allowed.
    (See WACHTA
    & MOTA
    v. EPA #71-77).
    Within this frame of reference we believe the cases are
    distinguishable.
    Our denial of variance to Cook does not deny
    him his investment.
    At most, his enjoyment of the property or
    its income has been suspended.
    Cook bought land and built in the
    face of the sewer connection ban, gambling on the availability
    of a sewer connection permit, which because of the overloaded
    condition of the sewer has been denied, notwithstanding partial
    lifting of the ban for the Waukegan plant.
    Cook sought advice
    from all those except the ones from whom he should have sought
    it, the E.P.A.
    His hardship is clearly self-imposed.
    Further,
    the
    records
    support
    the
    conclusion
    as
    to
    the
    sewer
    there
    involved
    that
    even
    a
    small
    increase
    in
    effluent
    will
    worsen
    an
    already
    bad
    situation,
    where
    back-up,
    by—pass,
    and
    over-flow
    have
    already
    resulted in demonstrated damage to the public welfare.
    An allowance
    of this petition would be a virtual repudiation of the ban allowing
    anyone to build in defiance of it and then claim hardship on the
    basis of self-imposed burdens, giving local officials the power to
    repeal the sewer connection ban order in effect.
    The instant case
    is a particularly good example- where petitioner stands ready to
    proceed with two more construction programs as soon
    as
    he
    gets
    a
    go-ahead.
    The School District is not without fault and should be
    rebuked for its actions in the face of the sewer ban.
    However,
    the hardship imposed in that case goes beyond the single project
    involved and has consequences not only detrimental to the school
    District itself but also to the students, faculty and public at
    large.
    (see Congregation
    lun Echod v. EPA #72-202).
    Prevention
    of ability to di’pose of the structure would require termination
    of the Vocation Building Trades Program,
    a program of obvious
    value not only to the many students now involved but to all those
    in the future, who would be participants.
    The over-all benefit
    5—291

    to the community
    in such a program is obvious
    as
    is the detriment
    consequental to its abandoment.
    In Congregation Am Echod
    (supra)
    we granted
    a sewer connection to a home occuped by a rabbi,
    in
    order that the entire congregation might be served.
    We there held
    that a denial would constitute a hardship not only on the rabbi
    himself but on the entire congregation which would be deprived of
    the religious leadership of its pastor.
    Similarily, termination
    of the Vocational Trades Program would inflict an unwarranted hard-
    ship on the entire community in addition to all affected students,
    present and future,
    if this worthwhile program was curtailed.
    Furthermore the evidence does not demonstrate the same
    detrimental consequences from the connection that would maintain
    in the case of Cook.
    Lastly, the loss of educational fund revenue
    resulting from a suspension of the program to a district already
    operating in a deficit position is
    a further factor
    to consider
    We find the cases sufficiently distinguishable, notwith-
    standing certain factual similarities,
    to justify a difference
    in ruling.
    Every variance case and particularly those involving
    a waiver of a sewer connection ban order requires
    a balancing of
    equiti~s.
    We
    have
    endeavored
    to
    reconcile
    these
    balances
    in
    every
    case
    on
    its
    individual
    merits.
    As
    we
    said in WACHTA
    &
    MOTA
    v.
    E.P.A.
    (supra):
    “Notwithstanding the profound implications
    of this decision and the pervasiveness of the problem,
    it
    is still necessaryto decide the matter before us on
    the facts set forth in the record.
    Whether a variation
    is premised on constitutional considerations of denial
    of property without due process of law or uncompensated
    taking
    Ca doctrine frequently employed in challenging the
    validity of restrictive zoning ordinances, See Bauske
    v.
    City of Des Plaines,
    13
    Ill.
    2d 169,
    148, N.E.
    2d 584
    (1958))
    on the principle of estoppel, resorted to where vested rights in
    permits
    are
    asserted
    (See
    Deer
    Park
    supra),
    or
    on
    the
    statutory
    basis
    of
    unreasonable
    hardship,
    the
    more
    traditional
    basis
    for the granting of a variance, the legal result is
    in direct
    consequence of the magnitude of the hardship imposed,
    as
    compared with the burdens on the public welfare.
    No
    hard
    line can be drawn and each element must be evaluated on the
    facts of the particular case.”
    In
    denying
    a
    petition
    for
    variance
    for
    sewer
    connection
    in
    Feige
    v.
    E.P.A.
    #72-192
    we
    said:
    “On this state of the record, we must deny the
    petition for variance.
    We do not believe that the char-
    acter and degree of the hardship alleged by petitioner out-
    weighs the hardship likely to result to the community from
    the additional hydraulic and organic load entering an al-
    ready overloaded sewer.
    The specific hardships alleged
    are insufficient for the granting of
    a variance, and we
    have so held in cases involving similar facts.
    Petitioner’s
    use and enjoyment of the property is at most suspended,
    —6—
    5
    292

    and not terminated and his plight
    is characteristic
    of virtually every property owner in an area affected
    by
    a sewer ban.
    As we said in Monyek v. Environmental
    Protection Agency #71—80, dated July
    1
    1971:
    ‘Undeniably, petitioner is confronted with
    some measure of inconvenience in this case.
    We
    cannot, however, view petitioner’s plight a singu-
    lar and therefore arbitrary nor can we commiserate
    to such a degree that we grant rather than deny
    this
    request.
    In
    cases
    where
    a
    house
    has
    been
    completely
    built
    before
    the
    date
    of
    the
    order
    (March
    31,
    1971)
    or where substantial steps toward
    completion have been taken we can clearly judge
    the hardship of non—connection to be unreasonable.
    In fact we have done so in the recently decided
    case of Wachta and Mota,
    d/b/a Belle Plaine Sub--
    division v.
    E.P.A.,
    #71-77.
    There the petitioner
    had seven units completely built, and the Board
    granted a variance to permit the sewer connections.
    For the remaining lots
    in the subdivision the Board
    ordered the builders to present
    a program to the
    Board demonstrating the feasibility of alternatives.’”
    Cook’s situation is distinguishable from that of Nilles,
    Inc.,
    a
    respondent
    in Glovka v.
    NSSD #71-269.
    There we did not order Nilles
    to disconnect the sewer tie-in made shortly after the date of the ban.
    Nilles had relied on the representations
    of the NSSD’s attorney made
    a few weeks after the imposition of the ban to the effect that the
    ban was not applicable
    to Nilles because of Nilles’
    possession of
    a pre-existing state sewer installation permit.
    Cook,
    on the other
    hand,
    was told expressly by city officials that
    the ban was in effect
    and applicable to him but urged to proceed in defiance of it, which
    advice he followed.
    In allowing a variance for sewer connection in Congregation
    Am Echod
    (supra) we said:
    “The Agency recommendation
    is
    that the variance be
    granted.
    Even though there is no direct financial hard-
    ship
    being suffered, we feel
    that the rabbi, his wife,
    and
    all those who benefit from his services will suffer in a
    special way if the rabbi becomes unable to attend.
    As
    we
    stated in McAdams
    v. Environmental Protection Agency,
    PCB 71—113:
    The additional pollution that variances
    in extreme cases
    like this will cause will prob-
    ably be small, for such cases are likely to be
    rather rare;
    and it must be borne because the
    hardship of denial is too great.’”
    —7—
    5
    293

    We believe the rationale of the Feige case applicable to Cook,
    whereas the rationale of Congregation Am Echod
    is applicable to the
    Community School District No.
    60, whose circumstances are unique and
    not likely to be repeated.
    Our grant of variance to the School District should not be
    construed as an invitation to the District or others similarly
    situated to repeat the events giving rise to our order.
    What
    might be considered
    a hardship on the basis of past events will
    not give rise
    to
    a similar holding in the future.
    Those buying
    land or erecting structures in the NSSD are cautioned to ascertain
    not only the applicability to the sewer ban order but also the
    suitability of any local sewer to which connection
    is sought.
    We reiterate the manifest need for the City of Waukegan to
    take affirmative steps
    to ameliorate the overloaded condition of
    its sewers which will continue to cause grief and agony to all
    concerned until the condition is abated.
    Repair of defective
    sanitary sewers to prevent infiltration of storm water in periods
    of wet weather will eliminate the overloaded conditions requiring
    the E.P.A. ‘s determination of inadequacy.
    This opinion constitutes the finding of facts and conclusions
    of law of the Board.
    Mr. Dumelle dissents believing that the variance should be
    granted in both cases.
    I, Christan Moffett, Clerk of the Pollution Control Board, certify
    that the above Opinion was adopted on the
    7”Jday
    of
    byavoteof
    ~/
    to
    /
    —8—
    5— 294

    Back to top