ILLINOIS POLLUTION CONTROL BOARD
August 22, 1972
THE VILLAGE OF DE SOTO
v.
)
PCB 72—224
ENVIRONMENTAL PROTECTION AGENCY)
William G. Ridgeway for The Village of DeSoto;
Thomas J.
Inixuel, Assistant Attorney General, for
the Environmental Protection Agency.
OPINION AND ORDER OF THE BOARD
(by Mr.
Parker):
By letter to the Agency dated May 18,
1972 the Village of
De Soto in effect seeks a variance from the requirement of Rule 405
of Chapter
3 of the Water Pollution Control Regulations requiring
that after July 31, 1972 no effluent shall exceed 400 fecal coliform
per 100 ml.
Petitioner says it will be able to comply with the
effluent standards for fecal coliform by July of 1973 when it
hopes to install and have in operation an upgraded sewage treat-
ment plant.
The petition asserts that to provide temporary
chlorination facilities pending completion of the upgraded plant
would be “most uneconomical and unwise” and that “there is inade-
quate space facilities
to provide for chlorination at the present
site.”
Petitioner presently treats its wastewater by means of a
single cell lagoon having an area of
8.7 acres and a
3 foot
water level.
The effluent which is the subject of this petition
is discharged to the Little Muddy River.
At the public hearing, held July 21, 1972, Petitioner waived
the statutory 90 day period for
Board
decision under Section 38
of the Act
(R.5),
and the parties stipulated that the following
levels of fecal coliform were present in samples taken by the
Agency on the dates indicated
(R.
2-3,
5):
March
16, 1970
260/100 ml
May 19, 1970
180/100 ml
April
28, 1971
100/100 ml
March
8, 1972
100/lOt., ml
June 2,
1972
400/100 ml
and
June 23, 1971
4000/100 ml
December
9, 1971
4000/100 ml
January 12, 1972
6000/100 ml
May
3,
1972
11000/100 ml
As will be apparent, the fecal coliform levels for the last
four listed samples exceed the 400 limit permitted by the regula-
tions.
In its recommendation, filed on July 13, 1972 before the
5
—
233
hearing,
the Agency characterized these excessive coli.form levels
as
“not outrageously high”,
a reference no doubt to the fact that
even the highest measured level of 11,000 is far below the est-
imated average
5 to 10 million level which may be attributed to
the feces from a single person.*
The Agency’s recommendation
also acknowledged that the effluent was not presently causing any
violations
of the fecal coliform standards set for the Little
Muddy River.
A consulting engineer for the Village testified at the hearing
that pursuant to request made by the Village in May of 1970
he prepared an engineering report and layout calling for installing
two additional lagoon cells and a chlorination tank
(R.
10),
which would have permitted the effluent to meet all standards
(R.
11).
The original construction cost was estimated to be
$56,000.
When land and administrative costs were added to this,
the total
was $96,500.
(R.
12).
But the Village was unable to purchase
the necessary land
“for a reasonable price”
(R.
12).
The engineer said that he is now studying the possibility of
using a different type treatment plant
(contact stabilization with
filtration and chlorination) which could be built on the existing
lagoon ground
(R.
13).
A rough cost estimate of $211,000. has
been made, and the Village is proceeding with
a preliminary design
to be submitted to the Agency for approval
(R.
14).
Estimated
time of completion of the project is about one year after letting
of the contract
(R. 14-15)
.
Applications have been made for
Federal and State grants
(R.
15), which applications are still
pending.
The witness said it was doubtful that such an upgraded
plant could be built and in operating condition by July
1,
1973
(R.
15).
The difficulty we have with this case is that the record
fails to show why it is that temporary chlorination facilities
cannot be installed now,
or how such an immediate installation
might work an arbitrary or unreasonable hardship on Petitioner.
Aside from the conclusory statement of the engineer for the
Village that “the only place that they can chlorinate at the pre-
sent location is right adjacent to the road which is going to be
very very difficult and cause
a hardship”
(R.
19), we find nothing
in the record on the point.
The only cost data in the record has
to do with the ultimate costs of providing permanent treatment
facilities.
As Petitioner is well aware, our Board Procedural Rule 401
(a)
(2)
requires
a
petition
for
variance
to
set
forth
“a
description
of
the
costs
that
compliance
would
impose
on
the
petitioner
and
others”.
While the instant petition as filed in this case is
conclusory and therefore deficient in this respect, this short-
*A Practical Guide to Water Quality Studies of Streams by
F.W.
Kittrell, U.S. Department of the Interior,
1969, pp. 97,
127.
5—
234
coming in no wise excuses the failure of proof.
The situation
is
particularly
aggravating
because
Petitioner
was
warned
by
the
Agency
of
this
problem
of
proof
in
advance
of
the
hearing,
viz:
“Petitioner has provided no cost estimates nor
precise technical reasons as to why it is actually
unfeasible
to install the necessary facilities to
consistently produce an effluent of 400 or less fecal
coliform per 100 ml by the July 31, 1972 deadline
date.”
(par.
6 of Agency Recommendation)
Yet the record is silent as to what the costs would be of com-
pliance on a temporary basis pending completion, of permanent
upgraded sewage treatment facilities.
Because of Petitioner’s failure to prove its costs of
temporary compliance we must deny the petition as unsupported by
a showing of the requisite arbitrary or unreasonable hardship.
Petitioner may prepare and file
a new petition for variance,
if it
S(
desires, accompanied by a verified showing
(e.g.
by affidavit)
of the necessary cost information.
In this event we will await
the Agency recommendation and then decide whether any further pub-
lic hearing is necessary.
This Opinion constitutes the Board’s findings of fact and
conclusions of law.
ORDER
The petition for variance is denied without prejudice to
the filing of a new petition in
accordance
‘with the Act and
Procedural Rules and as deslcribed
in the above opinion.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, certify that the Board adopted the above Opinion and Order
this
~
day of August, 1972,
by a vote of_________
ristan
L. Moffe~ Clerk
Illinois Pollution Control B
5
—
235