ILLINOIS POLLUTION CONTROL BOARD
    March
    28, 1972
    DEERE
    & COMPANY
    v.
    )
    PCB 71—353
    ENVIRONMENTAL PROTECTION AGENCY
    Opinion of the Board
    (by Jacob D.
    Dumelle)
    Deere
    &
    Company
    (Deere)
    filed
    a petition for variance on
    November
    8,
    1971 asking the Board to allow its gray-iron foundry
    located
    at the John Deere Plow
    &
    Planter Works,
    501 Third Avenii~,
    Moljne,
    Illinois
    to oDerate
    in violation of
    air oollution reaulations
    until December
    31,
    1972 at which
    time air pollution control equipment
    would be fully installed and operational.
    The company,
    at the time
    it submitted its amended ACERP
    in 1968, had planned to close the
    foundry and
    two other implement factory foundries
    by December
    1972.
    The company’s original ACERP submitted in April of
    1968 outlined
    a
    program of retirement
    for the foundries by December
    1973 and after
    further study the closing date was advanced to December
    1972.
    The
    ACERP included the proviso that “If future planning should find it
    desirable
    to indefinitely continue the operation of any one of the
    existing gray iron foundries beyond the dates indicated for closing,
    then
    equipment will be installed which will meet
    the emission Stan-
    dards.”
    The company now asks us
    to approve
    its exercise of its option
    to continue operation of its gray-iron foundry
    at the John Deere
    Plow
    & Planter Works.
    On March
    13 Deere submitted
    a Motion to Grant the Variance
    Without Hearing.
    Based on the sworn statements of
    the company and
    the favorable recommendation of the Environmental Protection Agency
    we grant the requested variance subject to the conditions enumerated
    in the attached order.
    In its motion the company detailed the circumstances of the
    inadvertence which caused the delay in filing this petition for
    variance.
    Although the formal petition for variance was not
    a
    timely filing the company had in fact been proceeding
    for some
    time
    with
    its plans to control the foundry emissions and had kept the
    EPA
    fully informed of its plans.
    Until sometime after
    the filing of
    the variance the company was proceeding on the basis that it was
    operating under
    a valid ACERP covering the foundry.
    Deere was sub-
    sequently informed by the EPA that,
    under the precedent of EPA v.
    Commonwealth Edison Co., PCB
    70-4, February
    17,
    1971, all ACERPs
    4
    ~O9

    approved under the old Air Pollution Control Act would
    expire one year
    after the effective date of the Act.
    The Commonwealth
    (PCB
    70-4)
    case
    therefore declared that all
    holders of approved compliance programs
    must seek
    extensions after July
    1,
    1971.
    The company was informed
    on October 29,
    1971 that a variance should
    be filed and they
    1~romptly
    did so.
    The foundry
    has two cupolas which have
    a process rate of 18,750
    pounds per hour each.
    Both are presently equipped with wet cap
    collectors stated to be operating at an efficiency of about 50
    (weight)
    Only one cupola is operated at any
    given time with emissions estimated
    at
    29 pounds per hour.
    The present standard limits emissions
    to
    about
    18 pounds per hour.
    Without the wet caps and with
    no other
    control the emissions are estimated to be
    58 pounds per hour.
    The company plans to control the foundry emissions with a
    bag—house collection system from which the emission rate of parti-
    culate matter will be
    3 pounds per hour.
    Prior to passing into
    the bag—house the cupola off-gases will pass through an afterburner
    where any residual combustibles will be incinerated.
    Installation of
    the afterburners and other “in—line” equipment is scheduled for the
    month of July when the tactory is shut down.
    Some time after the
    installation
    is required to start up and “de—bug” the control system.
    It is our hope that in this instance as in several earlier situa-
    tions Deere will be able to complete its pollution control project
    before the scheduled operating date of December 31, 1972.
    As a condition to the grant of this variance we shall require
    the posting of a security in the amount of $20,000 to assure the
    satisfactory completion of the job.
    We have little or~noinformation
    in the record to guide us in setting the amount of the bond in this
    case although we are confident that the cost of control
    is very
    considerably in excess of the figure we have
    set.
    Nonetheless $20,000
    may be as appropriate as any amount since the compliance program is
    well advanced and heading toward completion.
    The rationale of setting
    the bond in the approximate amount of the cost of the control project
    is not apt in this case.
    The security shall be conditioned upon the
    operation of the foundry with inadequate control facilities after
    December 31,
    1972.
    This Opinion constitutes the Board’s findings of fact and
    conclusion of law.
    4
    110

    ORDER
    The Board hereby grants
    a variance to Deere
    & Company to allow
    the discharge of particulate matter from the John Deere Plow
    &
    Planter Works gray—iron foundry in excess of the limits prescribed
    by
    the
    existing rules and the Environmental Protection Act.
    This
    variance is granted to allow Deere
    &
    Company to acquire and install
    air pollution control equipment to meet the particulate discharge
    limitations.
    This variance shall extend until December 31,
    1972 and
    is subject to the following conditions~
    1.
    Deere
    & Company shall post with the Environmental Protection
    Agency on or before April 20, 1972 a bond or other adequate
    security in the amount of Twenty Thousand Dollars
    ($20,000)
    and in such form as
    is satisfactory to the EPA, which sum shall
    be forfeited to the State of Illinois in the event the foundry
    shall be operated after December 31,
    1972 without adequate
    air pollution control equipment.
    2.
    Deere
    & Company shall not increase the intensity of its
    foundry emissions during the period of the variance.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the Board adopted the above Opinion and Order
    on the ~Lday
    of March,
    1972 by a vote of
    ~-
    O
    C ristan L. Moffét~7C1erk
    Illinois Pollution Control Board
    4—
    111

    .
    .

    Back to top