ILLINOIS POLLUTION CONTROL BOARD
January 30, 1973
MONTEBELLO MANOR CORP.
v.
)
PCB 72—429
ENVIRONMENTAL PROTECTION AGENCY
OPINION AND ORDER OF THE BOARD (by Mr. Dumelle):
This is a petition for variance to allow connection to a
sanitary sewer in the
City
of Hamilton. Hearing was held on
December 27, 1972. Petitioner, a closely held corporation
consisting of three individual shareholders, has undertaken
the building of a nursing care facility for the residents of
Hamilton, Hancock and surrounding counties. There is no other
such facility in Hamilton. The facility will contain eighty-
two beds and would discharge approximately 8,200 gallons of
waste water per day containing 15 pounds BOD. Around sixty of
these beds will be taken by current Hamilton residents, thus
providing for a net increase of only twenty persons to the
sewage system.
The total cost of the facility is $585,000. Petitioner’s
president has advanced $50,000 of his personal assets and his
two associates have advanced $30,000 and $20,000 each toward the
project. In addition, a loan in the amount of $454,000 has been
approved by a Springfield bank. As of October 1, 1972, $170,000
of that loan was advanced at 8-1/4 interest with an additional
$50,000 being advanced as of November 1, 1972. They have also
borrowed another $20,000 at 7-1/2 interest from a bank in
Hamilton. Should the variance be denied they would suffer a
loss of $300,000 to $400,000.
Petitioner applied to the Agency on August 10, 1972 for a
permit to connect up to the sanitary sewer. The Agency denied the
permit on September 1, 1972. The reason for the denial was
because the Hamilton Sewage Treatment Plant does not have ade-
quate capacity to accept any additional waste load. The plant
was designed to serve 1,640 persons at a design flow of 164,000
gallons per day. The plant presently serves around 2,488 persons
with an average flow of 270,000 gallons per day. The plant
provides primary settling treatment only with bar screens, sludge
digestion and sludge drying beds. Plans and specifications for
upgrading the plant were approved by the Agency on August 31, 1972.
The City is attempting to obtain federal clearance essential for
both federal and state grant funds but has a low priority rating
6
—
667
———.-~u~
jt~c~LL
~~iiy
could be arranged, the earliest
completion date for the plant would be around July, 1974.
The Hamilton plant discharges to the open Hamilton Slough
which drains into the Mississippi River. The plant is currently
discharging an effluent which on October 30, 1972, measured
600 mg/i BOD, 110 mg/i suspended solids and 7,900,000/100 mg/i
fecal coiiforrn. Other BOD values have been recorded at 420 and
180 mg/i.
The petitioner entered into construction contracts around
February, 1972 with actual construction beginning around April.
The Water Regulations requiring permits were adopted by the
Board in March, 1972. It appears, then, that the obligations
were entered into with the full expectancy that the sewer con-
nection would be forthcoming~
The Agency indicates that while the granting of this petition
would permit some increase in the pollution load to Hamilton
Slough and then to the Mississippi River, it would not be expected
to noticeably change the present outfall conditions in the
Slough. The Agency also indicates that the increase would not
likely alter the biota and fish life measurably and also that
due to the Mississippi River dilution ratio, the increase would
not be expected to make a measurable difference in the quality
of river water entering the intake of the Warsaw Public Water
Supply which is six miles downstream from the Hamilton discharge.
Based upon the facts and the Agency’s recommendation we will
grant the variance. The need for this nursing care facility
outweighs the harm which will
occur as a
result of the additional
discharge volume. We should note, however, that we are far more
persuaded in this case by the fact that a nursing facility (the
only one in Hamilton), is involved than by its financial aspects.
If the proposed facility were not intended for the general benefit
of the community our decision may well have been different.
This opinion constitutes the Board1s findings of fact and
conclusions of law.
ORDER
The Petition for Variance is granted. Petitioner shall be
allowed to connect up to the Hamilton sewer system in conformity
with all applicable laws and regulations except as excused by
this variance.
I, Christan L. Moffett, Clerk of the Pollution Control Board,
certify tiat the Board adopted the above Opinion and Order this
~
day of
______________,
1973, by a vote of
3
to ~
__
~ ~
—2—
6
—
668