ILLINOIS POLLUTION CONTROL BOARD
    December
    12, 1972
    ENVIRONMENTAL PROTECTION AGENCY
    1—300
    v.
    GEORGE E. HOFFMAN
    &
    SONS, INC.,
    a Cor’oration
    PRESCOTT E. BLOOM, ASST. ATTORNEY GENERAL, APPEARED ON BEHALF
    OF
    ENVIRONNENTAL PROTECTION AGENCY
    MICHAEL
    0. GARD, OF SWAIN, JOHNSON &
    GARD, APPEARED ON BEHALF
    OF RESPONDENT
    OPINION AND ORDER OF
    THE
    BOARD (BY SAMUEL T. LAWTON, JR.)
    Complaint was filed by the Environmental
    Protection
    Agency
    against George E. Hoffman, Inc., a corporation,
    Respondent,
    alleging
    that
    Respondent owns
    and operates a Heatherington and Berner mobile-
    tyoe asphalt plant, Model No.
    1770, and that on or about July 1,
    1970, Respondent constructed, installed and operated the mobile
    asphalt plant near Little America, Fulton County, Illinois, and
    that on or about May 13, 1971, Respondent constructed, installed
    and operated the same mobile asphalt plant near Princeville, Illi-
    nois, both installations having been made without obtaining permits
    from the Agency, in violation of Section 9(b) of the Act. The com-
    plaint further alleges that since July 1, 1970, Respondent has
    operated the asphalt plant in violation of process weight limitations
    as provided by Rule 3-3.111 of the Rules and Regulations Governing
    the Control of Air Pollution and that on August 6, 1971, Respondent
    constructed, installed and operated a Washer-Tubulaire scrubber, which
    equipment is designed to prevent air pollution, without obtaining a
    permit in violation of Section 9(b) of the Act and Rule 3—2.110 of
    the Rules. Lastly, the complaint alleges that since operations began
    at the Princeville location on or about May 31, 1971, Respondent
    has operated the asphalt plant so as to cause, threaten or allow the
    discharge of contaminants so as to cause air pollution, in violatio±~
    of Section 9(a) of the Act.
    Hearing was held on the complaint in Peoria on September 26,
    1972. There is no dispute that Respondenti.nstalled its mobile
    asphalt plant at the Little America and Princeville
    locations
    with-
    out a permit as
    required by Section 9(b) of the Act, nor is there
    any dispute that the scrubber was installed
    without a permit in
    violation of Section 9(b) of the Act and Rule 3-2.110. The operation
    and installation without a permit is admitted by counsel for Respondent
    (R.5, 6 and 7) and conceded by Respondent’s Executive Vice-President
    (R.l14, 116) and its comptroller (R.l57). Respondent endeavors to
    6 —417

    .~e relieved of liability for violation of these sections on the
    basis of conversations had with representatives of the old Air
    Pollution Control Board before passage of the Act and with
    Agency personnel after its passage. It is not clear from the
    record precisely what these conversations consisted of, or why
    they would constitute a defense to any of the violations charged.
    In several conversations with Air Pollution Control Board personnel,
    information was sought with respect to scrubbers and permit proce-
    dure (R. 108—114). In another conversation with Agency personnel,
    the matter of forms for permits was discussed (R.l40-41). In another
    conversation with Agency personnel, the possibility of seeking a
    variance to enable operation at the Princeville site without con-
    trol equipment was considered (R. 86, 143)
    .
    With respect to the
    latter conversation, it appears to be Respondent’s suggestion
    that Agency personnel implied that the variance would be favorably
    considered (R.l43-l44). The variance discussed related only to the
    possibility of operating without control equipment and in no way
    would serve as a defense for operations at either of the locations
    without a permit. Furthermore, the records of the Board disclose
    that a variance was sought by Respondent in case George E. Hoffman,
    Inc. v. Environmental Protection Agency, #71-204, with respect to
    operation at Princeville without installation of control equipment.
    This variance petition was withdrawn on motion of Respondent, by
    our Order of September 2, 1971. In the present proceeding, Respon-
    dent admits that the installation of the abatement equipment when
    made was done without a permit and no variance was granted for any
    period of operation without one.
    We find that Respondent, by its operations at Little America
    and Princeville without a permit, violated Section 9(b) of the Act.
    We find that Respondent’s installation of the Washer-Tubulaire
    scrubber without a permit, being equipment designed to prevent air
    pollution, violated Section 9(b) and Rule 3-2.110 of the Rules.
    Respondent’s contentions by way of defense to these violations
    are singularly unpersuasive. The record does not disclose any decep-
    tion or misleading by personnel of the old Air Pollution Control
    Board or the Environmental Protection Agency that could in any way,
    estop the Agency from pursuing its complaint, or which would consti-
    tute a defense to the violations asserted. Respondent was advised
    of the relevant regulations and statutory provisions concerning the
    granting of variances and the processing of permits. Respondent
    chose to pursue the variance route as to the Princeville operation
    and then withdrew the petition, once filed. Discussion with Agency
    representatives can in no way be equated to the granting of a variance
    nor serve as a defense for failing to fulfill the legal requirements
    of the statute and the regulations.
    —2—
    6
    41~

    The record contains no evidence upon which we could find
    Respondents to have violated Section 9(a) of the Act with respect
    to causing, or tending to cause air pollution, nor does it appear
    that the Agency made any effort to prove this allegation. What
    little evidence is in the record discloses that the Princeville
    area is sparsely settled and there is no evidence of nuisance or
    impact on the community from the emissions caused by Respondent’s
    operation.
    The only issue in dispute is whether Respondent has violated
    the particulate emission regulations of Rule 3-3.111. Proof of
    violation was made by Agency witnesses based upon standard emission
    factors contained in Public Health Service Publication No. 999-AP42
    (R.3l-34). In determining particulate emissions from Respondent’s
    operation, two different process weight rate figures are used in com-
    putation. A figure of 480 tons per hour was used in the first in-
    stance, based upon a statement made by Respondent’s plant superin—
    tendant to an Agency witness that this figure represented the process
    weight rate of the asphalt plant (R.15)
    .
    Later permit applications
    filed by Respondent with the Agency for the Princeville operation,
    specified the process weight rate of the plant to be
    360
    tons per
    hour. (EPA Ex. 2(e)). With a process weight rate of 480 tons per
    hour, 384 pounds per hour of particulates would be emitted against
    an allowable maximum hourly emission contained in the Regulations
    of 68.4 pounds per hour. With a process weight of 360 tons per
    hour, emissions would be 288 pounds per hour against an allowable
    emission of 64.5 pounds per hour. Both compilations presuppose
    the absence of a scrubber (R.48-49, EPA Ex. 2(e)). It is manifest
    that with either process weight rate, that which the superintendent
    indicated to be appropriate or that which was used by Respondent in
    the permit application
    form, substantial
    violations
    of the particulate
    regulations are demonstrated.
    Respondent endeavors to counter this finding by contending
    that the plant only operated at 60 of its maximum capacity
    (R. 163—
    168). It is not clear what Respondent is endeavoring to show by this
    testimony, whether the plant only operated 60 of a normal working day
    or whether the plant operated at only 60 of its rating. In either
    event, the evidence is inadequate to refute the conclusions reached
    on the basis of the use of standard emission factors. To the extent
    that the evidence would have any probative value, it was refuted by
    the testimony of Environmental Protection Agency witness Otto Klein
    (R.2l4) who stated that when the plant was in operation,
    it
    was
    operating at a rate of 360 tons per hour.
    Respondent appears to misunderstand the interrelation of the
    process weight rate and the use of standard emission factors when a
    stack test is not utilized. Allowable emissions are not computed
    on the basis of totality of emissions over a given period of time
    —3—
    6—419

    on a subjective basis, but what the rate of emissions are at the
    time the facility is actually in use. If, when operating the
    asphalt plant is in fact, operating at a rate of 360 tons per hour,
    the
    duration of this operation is irrelevant. Process emissions are
    premised on the rate during the period of operation and compliance
    or violation is based on this computation and not on the total length
    of time the operation has taken place or the total weight of particu-
    lates that have, in fact, been emitted, absent a stack test. Any
    other rule would enable an emitter to cease operation every 59 minutes
    and contend that he never violated an hourly rate.
    In the first case to come before the Board, we held that the
    use of standard emission factors was a proper method for determining
    violation or compliance with process weight limitations. Environ-
    mental Protection Agency v. Lind.gren Foundry Co., #70-1, 1 PCB 11,
    (September 25, 1970). In so holding, we stated:
    “...it is standard practice to prove a violation
    by the use of emission factors recognized by experts
    on the basis of experience with similar equipment.
    To
    require an expensive stack test in the absence of any
    testimony suggesting that the standard emission factors
    are inaccurate
    or that the equipment in question is
    unique
    would be to impose an unreasonable
    burden on the
    enforce-
    ment process. The respondent is free to introduce stack
    test results to rebut the evidence of estimated emissions.
    But in the absence of any rebuttal, the Agency has proved
    its case...”
    In Environmental Protection Agency v. Norfolk & Western Railway,
    #70-41, 1 PCB
    ,
    (May 26, 1971), we held that when a violation was
    based upon the use
    of standard emission factors, the Respondent could
    rebut this finding by introduction
    of evidence showing that the cir-
    cumstances relating to Respondent’s operation, were different from
    those which were assumed to maintain under the conditions when the
    standard emission factors were used. In the Norfolk and Western
    case, Respondent successfully demonstrated that the standard emission
    factors did not give an adequate picture of the particular operation
    because of demonstrated differences in fuel and actual test results
    performed on equipment similar to that involved in the case. No
    comparable showing has been made by Respondent in the present case
    nor has any showing been made at all to rebut the conclusion of vio—
    lation based on the use of emission factors. Respondent’s unsupported
    speculation that it was operating at 60 of maximum capacity is in-
    sufficient to rebut the finding of violation by the use of standard
    emission factors. We do not by this holding say that there could neve
    be any circumstances when definitive proof of a derated operation
    might not serve to counter a violation based on the use of standard
    emission factors, although allowable emissions generally decrease
    —4—
    6
    420

    with a decrease in actual process weight rate What we do say is
    that Respondent in the present case has failed to meet its burden
    in this respect. Cf. Environmental Protection Agency v. Central
    Illinois Light Co., #72—83, 5 PCB
    ,
    (November 8, 1972).
    We find that Respondent has violated Section 9(b) of the
    Act by failing to obtain permits for its operations at the Little
    America and Princeville
    locations as alleged in the complaint and has
    violated Section 9(b) of
    the Act and Rule 3-2.110 of the Rules and
    Regulations Governing the Control of Air Pollution by installing and
    operating a Washer-Tubulaire scrubber without a permit as alleged in
    the complaint. We find that Respondent’s operations at the two loca-
    tions involved prior to the installation of the scrubber constitute
    a violation of the process weight limitations of Rule 3-2.111 of the
    Rules aforesaid.
    We find the Agency has failed to sustain proof of violation
    by Resnondent of Section 9 (a) of the Act by causing, or tending to
    cause, air pollution, and hold Respondent not liable for violation
    of this section.
    We impose a penalty against Respondent in the amount of $4,000
    for violation of the provisions of the statute and rules above set
    forth. While express proof of air pollution as defined in the statute
    is lacking in the present case, there is no question that an asphalt
    plant is one with a high degree of potential in this respect, and it is
    inexcusable that Respondent should have operated during the years
    involved without obtaining permits from the Agency. It is only by
    the permit process that the proper location and operation of a plant of
    this character can be determined and adequate equipment be installed
    to achieve compliance with the law. Cf. Environmental Protection
    Agency v. Southern Illinois Asphalt Company, #7l~3l, 1 PCB 665
    (June 9, 1971).
    This opinion constitutes the findings of fact and conclusions
    of law of the Board.
    IT IS THE ORDER of the Pollution Control Board:
    1. Respondent shall cease and desist the operation of its
    mobile—type asphalt plant and all equipment installed
    in conjunction therewith, without obtaining proper
    permits for such operations from the Environmental
    Protection Agency.
    2. Penalty in the amount of $4,000 is. assessed against
    Respondent for violation of Section 9(b) of the
    Environmental Protection Act and Rule 3-2,110 of
    the Rules and Regulations Governing the Control of
    Air Pollution, both with respect to failure to obtain
    permits as charged in the complaint and for violation
    6
    421

    o~R-.le 3-3.111 of
    the
    Rules anC Regulations Governing
    the Control of Air Pollution for causing particulate
    ~ssions
    in violation of
    the process weight limitations
    ccnoa:nei in said Rule, as charged in the complaint.
    Penalty shall be naid by certified check or money order
    no t~e State of Illinois by January 16, 1973, and
    sent to: Fiscal Services Division, Environmental Pro-
    neccion Agency, 2200 Churchill Drive, Springfield,
    :~±nois62706.
    :,
    Chr:snan ~cffenn, Cleth of the Illinois Pollution Control Board,
    the acove Oninion and Order was adopted on the
    I
    1
    ecen~ber, ~72,
    b~a vote of
    ~
    to
    ~
    —1—
    6—
    422

    Back to top