ILLINOIS POLLUTION CONTROL BOARD
December
12, 1972
ENVIRONMENTAL PROTECTION AGENCY
1—300
v.
GEORGE E. HOFFMAN
&
SONS, INC.,
a Cor’oration
PRESCOTT E. BLOOM, ASST. ATTORNEY GENERAL, APPEARED ON BEHALF
OF
ENVIRONNENTAL PROTECTION AGENCY
MICHAEL
0. GARD, OF SWAIN, JOHNSON &
GARD, APPEARED ON BEHALF
OF RESPONDENT
OPINION AND ORDER OF
THE
BOARD (BY SAMUEL T. LAWTON, JR.)
Complaint was filed by the Environmental
Protection
Agency
against George E. Hoffman, Inc., a corporation,
Respondent,
alleging
that
Respondent owns
and operates a Heatherington and Berner mobile-
tyoe asphalt plant, Model No.
1770, and that on or about July 1,
1970, Respondent constructed, installed and operated the mobile
asphalt plant near Little America, Fulton County, Illinois, and
that on or about May 13, 1971, Respondent constructed, installed
and operated the same mobile asphalt plant near Princeville, Illi-
nois, both installations having been made without obtaining permits
from the Agency, in violation of Section 9(b) of the Act. The com-
plaint further alleges that since July 1, 1970, Respondent has
operated the asphalt plant in violation of process weight limitations
as provided by Rule 3-3.111 of the Rules and Regulations Governing
the Control of Air Pollution and that on August 6, 1971, Respondent
constructed, installed and operated a Washer-Tubulaire scrubber, which
equipment is designed to prevent air pollution, without obtaining a
permit in violation of Section 9(b) of the Act and Rule 3—2.110 of
the Rules. Lastly, the complaint alleges that since operations began
at the Princeville location on or about May 31, 1971, Respondent
has operated the asphalt plant so as to cause, threaten or allow the
discharge of contaminants so as to cause air pollution, in violatio±~
of Section 9(a) of the Act.
Hearing was held on the complaint in Peoria on September 26,
1972. There is no dispute that Respondenti.nstalled its mobile
asphalt plant at the Little America and Princeville
locations
with-
out a permit as
required by Section 9(b) of the Act, nor is there
any dispute that the scrubber was installed
without a permit in
violation of Section 9(b) of the Act and Rule 3-2.110. The operation
and installation without a permit is admitted by counsel for Respondent
(R.5, 6 and 7) and conceded by Respondent’s Executive Vice-President
(R.l14, 116) and its comptroller (R.l57). Respondent endeavors to
6 —417
.~e relieved of liability for violation of these sections on the
basis of conversations had with representatives of the old Air
Pollution Control Board before passage of the Act and with
Agency personnel after its passage. It is not clear from the
record precisely what these conversations consisted of, or why
they would constitute a defense to any of the violations charged.
In several conversations with Air Pollution Control Board personnel,
information was sought with respect to scrubbers and permit proce-
dure (R. 108—114). In another conversation with Agency personnel,
the matter of forms for permits was discussed (R.l40-41). In another
conversation with Agency personnel, the possibility of seeking a
variance to enable operation at the Princeville site without con-
trol equipment was considered (R. 86, 143)
.
With respect to the
latter conversation, it appears to be Respondent’s suggestion
that Agency personnel implied that the variance would be favorably
considered (R.l43-l44). The variance discussed related only to the
possibility of operating without control equipment and in no way
would serve as a defense for operations at either of the locations
without a permit. Furthermore, the records of the Board disclose
that a variance was sought by Respondent in case George E. Hoffman,
Inc. v. Environmental Protection Agency, #71-204, with respect to
operation at Princeville without installation of control equipment.
This variance petition was withdrawn on motion of Respondent, by
our Order of September 2, 1971. In the present proceeding, Respon-
dent admits that the installation of the abatement equipment when
made was done without a permit and no variance was granted for any
period of operation without one.
We find that Respondent, by its operations at Little America
and Princeville without a permit, violated Section 9(b) of the Act.
We find that Respondent’s installation of the Washer-Tubulaire
scrubber without a permit, being equipment designed to prevent air
pollution, violated Section 9(b) and Rule 3-2.110 of the Rules.
Respondent’s contentions by way of defense to these violations
are singularly unpersuasive. The record does not disclose any decep-
tion or misleading by personnel of the old Air Pollution Control
Board or the Environmental Protection Agency that could in any way,
estop the Agency from pursuing its complaint, or which would consti-
tute a defense to the violations asserted. Respondent was advised
of the relevant regulations and statutory provisions concerning the
granting of variances and the processing of permits. Respondent
chose to pursue the variance route as to the Princeville operation
and then withdrew the petition, once filed. Discussion with Agency
representatives can in no way be equated to the granting of a variance
nor serve as a defense for failing to fulfill the legal requirements
of the statute and the regulations.
—2—
6
—
41~
The record contains no evidence upon which we could find
Respondents to have violated Section 9(a) of the Act with respect
to causing, or tending to cause air pollution, nor does it appear
that the Agency made any effort to prove this allegation. What
little evidence is in the record discloses that the Princeville
area is sparsely settled and there is no evidence of nuisance or
impact on the community from the emissions caused by Respondent’s
operation.
The only issue in dispute is whether Respondent has violated
the particulate emission regulations of Rule 3-3.111. Proof of
violation was made by Agency witnesses based upon standard emission
factors contained in Public Health Service Publication No. 999-AP42
(R.3l-34). In determining particulate emissions from Respondent’s
operation, two different process weight rate figures are used in com-
putation. A figure of 480 tons per hour was used in the first in-
stance, based upon a statement made by Respondent’s plant superin—
tendant to an Agency witness that this figure represented the process
weight rate of the asphalt plant (R.15)
.
Later permit applications
filed by Respondent with the Agency for the Princeville operation,
specified the process weight rate of the plant to be
360
tons per
hour. (EPA Ex. 2(e)). With a process weight rate of 480 tons per
hour, 384 pounds per hour of particulates would be emitted against
an allowable maximum hourly emission contained in the Regulations
of 68.4 pounds per hour. With a process weight of 360 tons per
hour, emissions would be 288 pounds per hour against an allowable
emission of 64.5 pounds per hour. Both compilations presuppose
the absence of a scrubber (R.48-49, EPA Ex. 2(e)). It is manifest
that with either process weight rate, that which the superintendent
indicated to be appropriate or that which was used by Respondent in
the permit application
form, substantial
violations
of the particulate
regulations are demonstrated.
Respondent endeavors to counter this finding by contending
that the plant only operated at 60 of its maximum capacity
(R. 163—
168). It is not clear what Respondent is endeavoring to show by this
testimony, whether the plant only operated 60 of a normal working day
or whether the plant operated at only 60 of its rating. In either
event, the evidence is inadequate to refute the conclusions reached
on the basis of the use of standard emission factors. To the extent
that the evidence would have any probative value, it was refuted by
the testimony of Environmental Protection Agency witness Otto Klein
(R.2l4) who stated that when the plant was in operation,
it
was
operating at a rate of 360 tons per hour.
Respondent appears to misunderstand the interrelation of the
process weight rate and the use of standard emission factors when a
stack test is not utilized. Allowable emissions are not computed
on the basis of totality of emissions over a given period of time
—3—
6—419
on a subjective basis, but what the rate of emissions are at the
time the facility is actually in use. If, when operating the
asphalt plant is in fact, operating at a rate of 360 tons per hour,
the
duration of this operation is irrelevant. Process emissions are
premised on the rate during the period of operation and compliance
or violation is based on this computation and not on the total length
of time the operation has taken place or the total weight of particu-
lates that have, in fact, been emitted, absent a stack test. Any
other rule would enable an emitter to cease operation every 59 minutes
and contend that he never violated an hourly rate.
In the first case to come before the Board, we held that the
use of standard emission factors was a proper method for determining
violation or compliance with process weight limitations. Environ-
mental Protection Agency v. Lind.gren Foundry Co., #70-1, 1 PCB 11,
(September 25, 1970). In so holding, we stated:
“...it is standard practice to prove a violation
by the use of emission factors recognized by experts
on the basis of experience with similar equipment.
To
require an expensive stack test in the absence of any
testimony suggesting that the standard emission factors
are inaccurate
or that the equipment in question is
unique
would be to impose an unreasonable
burden on the
enforce-
ment process. The respondent is free to introduce stack
test results to rebut the evidence of estimated emissions.
But in the absence of any rebuttal, the Agency has proved
its case...”
In Environmental Protection Agency v. Norfolk & Western Railway,
#70-41, 1 PCB
,
(May 26, 1971), we held that when a violation was
based upon the use
of standard emission factors, the Respondent could
rebut this finding by introduction
of evidence showing that the cir-
cumstances relating to Respondent’s operation, were different from
those which were assumed to maintain under the conditions when the
standard emission factors were used. In the Norfolk and Western
case, Respondent successfully demonstrated that the standard emission
factors did not give an adequate picture of the particular operation
because of demonstrated differences in fuel and actual test results
performed on equipment similar to that involved in the case. No
comparable showing has been made by Respondent in the present case
nor has any showing been made at all to rebut the conclusion of vio—
lation based on the use of emission factors. Respondent’s unsupported
speculation that it was operating at 60 of maximum capacity is in-
sufficient to rebut the finding of violation by the use of standard
emission factors. We do not by this holding say that there could neve
be any circumstances when definitive proof of a derated operation
might not serve to counter a violation based on the use of standard
emission factors, although allowable emissions generally decrease
—4—
6
—
420
with a decrease in actual process weight rate What we do say is
that Respondent in the present case has failed to meet its burden
in this respect. Cf. Environmental Protection Agency v. Central
Illinois Light Co., #72—83, 5 PCB
,
(November 8, 1972).
We find that Respondent has violated Section 9(b) of the
Act by failing to obtain permits for its operations at the Little
America and Princeville
locations as alleged in the complaint and has
violated Section 9(b) of
the Act and Rule 3-2.110 of the Rules and
Regulations Governing the Control of Air Pollution by installing and
operating a Washer-Tubulaire scrubber without a permit as alleged in
the complaint. We find that Respondent’s operations at the two loca-
tions involved prior to the installation of the scrubber constitute
a violation of the process weight limitations of Rule 3-2.111 of the
Rules aforesaid.
We find the Agency has failed to sustain proof of violation
by Resnondent of Section 9 (a) of the Act by causing, or tending to
cause, air pollution, and hold Respondent not liable for violation
of this section.
We impose a penalty against Respondent in the amount of $4,000
for violation of the provisions of the statute and rules above set
forth. While express proof of air pollution as defined in the statute
is lacking in the present case, there is no question that an asphalt
plant is one with a high degree of potential in this respect, and it is
inexcusable that Respondent should have operated during the years
involved without obtaining permits from the Agency. It is only by
the permit process that the proper location and operation of a plant of
this character can be determined and adequate equipment be installed
to achieve compliance with the law. Cf. Environmental Protection
Agency v. Southern Illinois Asphalt Company, #7l~3l, 1 PCB 665
(June 9, 1971).
This opinion constitutes the findings of fact and conclusions
of law of the Board.
IT IS THE ORDER of the Pollution Control Board:
1. Respondent shall cease and desist the operation of its
mobile—type asphalt plant and all equipment installed
in conjunction therewith, without obtaining proper
permits for such operations from the Environmental
Protection Agency.
2. Penalty in the amount of $4,000 is. assessed against
Respondent for violation of Section 9(b) of the
Environmental Protection Act and Rule 3-2,110 of
the Rules and Regulations Governing the Control of
Air Pollution, both with respect to failure to obtain
permits as charged in the complaint and for violation
6
—
421
o~R-.le 3-3.111 of
the
Rules anC Regulations Governing
the Control of Air Pollution for causing particulate
~ssions
in violation of
the process weight limitations
ccnoa:nei in said Rule, as charged in the complaint.
Penalty shall be naid by certified check or money order
no t~e State of Illinois by January 16, 1973, and
sent to: Fiscal Services Division, Environmental Pro-
neccion Agency, 2200 Churchill Drive, Springfield,
:~±nois62706.
:,
Chr:snan ~cffenn, Cleth of the Illinois Pollution Control Board,
the acove Oninion and Order was adopted on the
I
1
ecen~ber, ~72,
b~a vote of
~
to
~
—1—
6—
422