ILLINOIS POLLUTION CONTROL BOARD
November 14, 1972
ENVIRONMENTAL PEOTECTION AGENCY
v.
)
#72—342
CITY OF RUSUVILLE et al,
Opinion
&
Order of the Board (by Mr. Currie)
The respondents stipulate, as charged, that construction
was commenced without a permit on facilities to connect. the
Bartlow Bros. effluent discharge pipe to the City~s sewers
tributary to its
sewage treatment plant. Construction has
since been halted and the sewer connection plugged.
It will
not be used unless and until a permit is issued, and we so
order. The complaint seeks no money penalties, so nothing
remains for us to do.
The basic problem, however, remains unsolved so far as
the present record shows. Some time ago Bartlow petitioned
us for a variance from applicable effluent standards pending
completion of this connection; the Agency responded that the
plant had insufficient capacity to accept such a discharge;
we dismissed the petition without prejudice, Bartlow Bros.,
Inc~
V.
EPA, #72-222, 5 PCB
—
(Aug. 28, 1972). We have
heard nothing further. If the excessive discharge continues,
we urge that it be abated as quickly as possible. We are of
course prepared to entertain such further proceedings on
that score as the parties may wish to bring before us.
I, Christan Moffett, Clerk of the Pollution Control Board,
certify that the Board adopted the above Opinio~
&
Order
this 14th day of November, 1972, by a vote of
3—3