ILLINOIS POLLUTION CONTROL BOARD
    November
    8,
    1972
    ENVIRONMENTAL PROTECTION AGENCY,
    Complainant,
    vs.
    )
    PCB 72—81
    TEE-PAK INC.,
    Respondent.
    Thomas J.
    Irnmel, Assistant Attorney General for the EPA
    John B.
    Jenkins, Attorney for Respondent
    OPINION AND ORDER OF THE BOARD
    (by Mr. Henss)
    The Environmental Protection Agency alleges that Respondent
    Tee—Pak Inc.
    has continually allowed the discharge of carbon
    disulfide,
    hydrogen sulfide and foul and obnoxious odors
    into
    the environment in violation of the Environmental Protection Act
    and has failed to submit an Air Contaminant Emission Reduction
    Program to control the emissions.
    Respondent states that it
    has
    in fact been operating under a program to reduce emissions
    and has recently installed additional equipment for that purpose.
    Tee-Pak is
    a manufacturer of cellulose casings which are
    used in the meat packing business.
    A major part of its production
    is from its Danville, Illinois plant which employs 800 persons
    and has operated since 1957.
    During the manufacturing process
    hydrogen sulfide gas
    (H2S)
    is
    released.
    Some of this gas is
    eventually vented to the atmosphere through a 160
    ft.
    stack
    along with other wastes.
    The odor caused by the hydrogen
    sulfide emission has resulted in
    a number of citizen complaints.
    The parties agree that hydrogen sulfide is the principal
    cause of the odor and the discussion has concentrated on methods
    for abatement of this type of emission.
    No standard has been set for hydrogen sulfide emissions
    in
    the State of Illinois.
    The EPA complaint is based upon the
    theory that
    a sufficient quantity of hydrogen sulfide is being
    emitted from Respondent’s plant to cause a nuisance in the
    community.
    Whether a nuisance exists will depend largely upon
    the reaction of citizens in the community to the odors emitted
    from Respondent’s plant.
    Tee-Pak states that it considered the possible nuisance
    problem as far back as 1966 and started planning for the reduction
    of hydrogen sulfide emissions.
    The first cor~.rolequipment,
    however, was not installed until 1969.
    This equipment
    consisted
    of two small scrubbers and did not achieve
    a total reduction of
    6
    141

    —2—
    hydrogen sulfide emissions since production of the plant was
    greatly
    increased at that time.
    With the increase of production
    the number of citizen complaints greatly increased.
    Scrubber
    #3 was installed in
    July
    1971.
    This was a large scrubber with
    a capacity of 30,000 cubic feet per minute and achieved a
    98 or
    99
    reduction of hydrogen sulfide in the gas
    it was scrubbing.
    The Environmental Protection Agency
    has acknowledged
    that
    the
    number of complaints from citizens subsided substantially
    following
    the installation of scrubber #3.
    Following installation
    of scrubber #3 total reduction of hydrogen sulfide emissions was
    27 1/2 percent.
    Tee--Pak began construction of scrubbers
    #4
    and #5 but prior
    to the
    time they were put into operation
    the EPA filed its
    complaint charging the company with creating
    a nuisance by emitting
    hydrogen
    sulfide and foul and obnoxious odors into
    the environment.
    Subsecuent
    to the filing
    of the complaint construction was com-
    pleted
    on scrubbers
    #4 and
    #5.
    When this matter was called
    for
    a hearing on the merits
    the
    parties submitted their Stipulation
    and Proposal
    for Interim
    Settlement stating that emission reductions of 27.6
    had been
    achieved through
    the use of three fully operational scrubbers
    and that
    the addition
    of scrubbers
    #4 and #5 would increase
    scrubbing capacity
    by approximately
    60,000 cfm and should achieve
    a
    total H2S emission reduction of approximately
    55,
    It was
    estimated that the
    two newer scrubbers would be fully operational
    by August
    4,
    1972.
    Monitoring euuipment,
    however, had not yet
    been ordered.
    The parties now propose that we
    authorize
    a period of about
    ten months for the purpose
    of monitoring
    and adjusting the
    emission control
    eouiprnent which has already been installed
    and
    making various tests
    to determine
    if this added scrubbing
    capacity solves
    the nuisance problem.
    Respondent
    estimates
    that
    it will need 140 days
    to install
    the monitoring
    equinment following
    our approval
    of
    the testing program.
    The
    EPA,
    Attorney General
    and Tee-Pak will then conduct tests
    for
    a
    180 day period promptly
    after
    the scrubbers
    and monitoring equipment have been installed
    and are operating efficiently.
    The tests will consist
    of stack
    analysis,
    continuous measurement
    of stack emissions,
    ground
    level measurements
    and other means of determining odor in the
    community.
    Within sixty days after
    the conclusion of the test
    period
    the parties will either submit
    a Proposal
    for Final
    Settlement or
    a hearing shall
    he held
    for determination
    of
    the
    matters raised
    in
    the complaint.
    It
    is requested that
    the
    Interim Settlement be considered
    a variance
    for the duration of
    the test period.
    As
    a part of the Interim Settlement
    the EPA
    agrees not to seek
    a monetary penalty against Respondent
    unless
    6
    142

    —3--
    the Respondent has failed to exercise good
    faith and cooperation
    in the procedures during the settlement period.
    Both parties
    recognize that this Board is not bound by any action taken
    by
    the Agency with regard to monetary penalty and that the Board
    may impose
    a monetary penalty even without the recommendation
    of the Agency.
    The parties do not,
    of course, guarantee that the untested
    scrubbers will solve the nuisance problem.
    They state, however,
    that the control equipment already installed “may” be sufficient
    to abate
    the nuisance and ask for a period of time to learn if
    that result has been achieved.
    (With the addition of the two
    recently completed scrubbers Respondent calculates that total
    emissions will be reduced to between
    36 and 38 lbs. of hydrogen
    sulfide per hour.
    This
    level of stack emission is below the
    company’s stack emission in the year 1965——a year when the
    company received no citizen’s odor complaints.)
    Scientific data is sorely lacking in this area.
    No emission
    standard for H2S has been established and it would seem worth-
    while
    to go through a testing period which will correlate the
    subjective reaction of citizens to the odor
    with
    the scientifically
    determined emission levels and air quality.
    Neither the Agency
    nor anyone else has really determined a nuisance level for H2S.
    Indeed there
    is
    some debate as to what is
    the threshold at which
    persons can recognize the odor,
    One article would indicate that
    the odor determination level
    for the hydrogen sulfide similar to
    that produced by Respondent is
    .0047 ppm.
    See:
    Leonardos,
    “Odor Threshold Determinations of
    53 Oxidant Chemicals’t,
    JAPCA,
    19
    (2)
    pp.
    91—95, February 1969.
    Dr. Howard Hesketh in the
    Union Carbide case PCB 72—54 also suggested a nuisance threshold
    involving
    a specific concentration of the gas for a determined
    time period.
    In that case Dr.
    Hesketh suggested that
    .007 ppm
    for 30 minutes would he the appropriate nuisance threshold.
    These suggested threshold levels from Dr. Hesketh’s calculations
    are apparently among the lowest suggested anywhere and the
    Agency
    is not ready to rely upon them in this case.
    The Agency
    has filed
    a statement terming Dr. Hesketh’s calculations as
    ‘highly tentative”.
    The Agency states “We are unwilling to
    predict a nuisance threshold for H2S.
    We can only propose to
    measure reduction of
    H2S
    emissions and correlate said reduction
    with
    known reduction in citizen complaints.
    In the Union Carbide case Dr.
    Howard Hesketh used
    .00047 ppm
    as the
    H2S
    odor threshold and then increased it
    15 times to
    arrive at
    a “nuisance” level of 0.007 ppm in the presence of CS2.
    In the absence of CS2 he would only increase it
    8 times to 0.004
    ppm.
    It appears, however, that
    1125 made from NA2S has a
    6
    143

    —4—
    threshold at least
    10 times higher or .0047 ppm.
    Multiplying
    this higher odor threshold by
    15 or
    8 as the case may he would
    give
    a substantially higher nuisance level
    than the figure
    mentioned in the Union Carbide case.
    We are unwilling at this point to accept any of these
    figures.
    To do so would seem to us to be adding inference
    to speculation.
    We
    agree with the parties
    that the best way
    of determining whether the alleged nuisance has been abated
    is
    to conduct
    a thorough testing program.
    We believe that
    it will be very desirable to correlate complaints and subjective
    analysis with the scientifically determined emission and air
    quality data.
    If the data accumulated during
    the
    testing
    period reveal that there has been insufficient imerovement in
    the air quality around the Respondent’s plant then methods
    may be considered for further control of the emissions.
    The charge that
    a nuisance has been created of necessity
    depends upon the subjective reaction of citizens
    in the community.
    A testing program would seem to us
    to offer a practical answer
    to the practical problem which does exist and it is at least as
    useful as inferences drawn from laboratory testing procedures.
    We note
    that the stipulation provides for secrecy and con-
    fidential treatment of the stack analysis reports, stack
    emission measurements, ground
    level measurements and other test
    results.
    The Stipulation at one point refers to such information
    as “proprietary”.
    We agree that testing procedures should not be
    revealed where public knowledge would interfere with the validity
    of
    the test result.
    However,
    we will make no advance determination
    of the secrecy of the test procedures or results. At the cciriclusion
    of the testing period the necessary data shall be made available to
    this Board and we will then determine whether the data shall remain
    confidential
    (under Rule 107 of our procedural rules)
    .
    Except for
    the secrecy provisions of the Stipulation the Proposal for Interim
    Settlement is approved.
    ORDER
    It is ordered that:
    1.
    The EPA and Tee-Pak Inc.
    shall conduct certain
    tests described below for a 180 day period
    beginning promptly after the scrubbers and moni-
    toring equipment have been installed and are
    operating efficiently.
    The test period will
    begin 140 days from the date of this Order.
    Tee—Pak will proceed with all due diligence to
    install the necessary equipment for conducting
    the tests and will promptly notify the EPA and
    the Attorney General when such equipment is satisfactorily
    operational.
    2.
    Stack Analysis.
    Within 30 days after the beginning
    of the test period a sample of Tee-Pak’s stack
    b
    144

    —5—
    emission will he drawn in the presence of one
    or more EPA representatives and an analysis of
    said sample for hydrogen sulfide will be pre-
    pared and submitted to
    the
    EPA and Tee-Pak.
    The sample will he drawn and a qualitative and
    quantitative analysis will be prepared thereon
    by
    Leon Xirschner,
    Tee-PaR’s Consultant, in
    such a scientific manner as
    shall be acceptable
    to EPA.
    3.
    Continuous Stack
    Measurements.
    Utilizing
    the
    monitoring
    equipment Tee-PaR will continuously
    measure
    its
    stack
    emissions
    of ~
    and
    will
    provide
    monthly reports of
    such measurements
    to
    the EPA.
    4.
    Ground Level
    Measurements.
    The EPA and Tee—PaR
    Inc. will
    throughout the test period
    jointly
    measure ground level
    concentrations of H2S at
    mutually agreeable locations
    in residential
    areas.
    The measurements
    will be made
    in
    a
    manner mutualy
    acceptable
    to the eartias.
    5,
    Additional
    testing.
    Beginning thirty days
    after
    the commencement of the
    test period,
    and continuing
    through the
    remainder
    of
    the
    test
    period,
    Tee-PaR
    and
    the EPA will implement
    and
    carry
    out
    additional
    testing procedures
    to he mutually
    agreed
    upon,
    including those steps and procedures outlined
    and defined
    in
    a letter dated July
    31,
    1972 from
    Tee-PaR’ s attorneys
    to
    the Attorney General
    of
    the State of Illinois
    (Representative
    of the
    EPA)
    Such -testing procedures
    shall be conducted in
    a
    scientific and acceptable manner designed to
    measure and determine the existance of
    an odor
    nuisance
    (or lack thereof)
    deriving
    from Tee-Pak’s
    emissions of
    1-12S and
    the effectiveness
    of Tee-Pak’s
    emission control program.
    6.
    Within sixty days
    after the conclusion
    of the test
    period Tee-PaR and
    the EPA shall either submit a
    Promosal for Final
    Settlement
    of this matter or
    a
    hearing shall
    be
    held for determination
    of
    the
    issues.
    7.
    Following the testing period reports of
    the stack
    analysis,
    stack emission measurements,
    ground level
    measurements
    and other odor testing shall be filed
    with
    the Pollution Control Board and
    at that time
    a determination shall
    made
    as to
    the confidential
    nature of the test results
    6
    145

    —6-
    8.
    Within
    ten days from the date
    of this Order
    Tee--PaR
    will
    post
    a
    bond.
    with
    the
    EPA
    signed
    b
    the
    appropriate
    corporate
    officers,
    in
    an
    amount
    sufficient
    to
    cover
    its
    equipment
    purchase
    obli-
    gations under this Order.
    9.
    This Order shall constitute
    a variance allowing
    Tee-PaR
    Inc.
    to proceed with emission and control
    practices which
    are not inconsistent with this
    Opinion and Order until November
    8,
    1973.
    Mr.
    Dumelle dissents.
    I,
    Christan
    L.
    Moffett,
    Clerk of
    the Illinois Pollution
    Control Board certify
    the
    above Opinion
    ane Order was adopted
    this-~~~~__day
    of No~rember, 1972
    by
    a
    vote
    of
    _____
    to
    ______—
    r
    ~
    k
    k
    S
    i
    ~‘
    _i~__~
    r
    ~istanL.~~1ofett~
    Illinois Pollution Control Board
    6
    146

    Back to top