ILLINOIS POLLUTION CONTROL BOARD
May
3,
1973
INTERNATIONAL HARVESTER COMPANY,
)
Petitioner,
vs.
)
PCB 73—101
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION AND ORDER OF THE
BOARD
(by Mr. Henss)
Petitioner International Harvester Company requests a
variance in its Project Completion Schedule to extend the
time when its waste treatment system will be in operation
from March 1973 to May 1973.
Both dates are prior to the
December 31, 1973 deadline established by Rule 408 Chapter 3
of our Regulations on Water Pollution.
Petitioner had
committed itself in
a Project Completion Schedule to achieving
compliance nine months prior to the deadline.
Delays in
delivery of the proper equipment made it impossible for
International Harvester to meet the agreed March deadline.
The EPA states that the May date for compliance
is acceptable,
but believes that the Petitioner could accomplish its purpose
by filing an Amended Project Completion Schedule.
The Agency
recommends that the Variance not be granted and that Petitioner
be directed to file an Amended Project Completion Schedule.
We see no reason to require that Petitioner take a
different procedural approach.
The matter is before us and
easily decided.
The variance is granted to May 8,
1973.
It is so ordered.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Opinion and Order was adopted
this 3rd day of May,
1973 by a vote of
4
to
0
7
—
709