1. 8—321

ILLINOIS
POLLUTION
CONTROL
BOARD
June
21,
1973
ENVIRONMENTAL
PROTECTION
AGENCY
)
P2—221
#72—249
v.
)
#72—250
)
#72—251
LACLEDE STEEL
COMPANY
)
#73-118
LARRY
~R.EATON, SPECIAL ASST.
ATTORNEY GENERAL, APPEARED ON
BEHALF OF ENVIRONMENTAL PROTECTION AGENCY
F.
WILLIAM
MCCALPIN and JOSEPH WEYHRICH~
RANDALL
ROBERTSON,
APPEARED
ON
BEHALF
OF
LACLEDE
STEEL
COMPANY
OPINION AND
ORDER
OF
THE
BOARD
(BY
SAMUEL
T.
LAWTON,
JR.):
Case #72-221 is an enforcement action filed by the Environmental
Protection Agency against LaClede Steel Company.
The amended com-
plaint alleges that Respondent,
in the operation of its Alton steel
mill,
and
particularly in the operation of its electric melt shop,
caused particulate emissions since July 1, 1970 and, specifically,
on six dates in 1971,
so as to cause air pollution in violation of
Section 9(a)
of
the
Environmental Protection
Act.
The compi.aint likewise alleges that the same operation caused
particulate emissions in violation of specified limits set forth in
Rule 3-3.2132 of the Rules
and
Regulations Governing the Control
of Air Pollution.
The
second
count
of
the
complaint alleges that particulate
emissions
from
the
foregoing
plant
violated
Rule
203(b)
of
the
air
pollution
regulations
of
the
Illinois
?ollution Control Board since
April
14,
1972,
an~that
as
a
consequence
thereof,
Respondent
was
obliged
to
meet
the
particulate
limitations
set
forth
in
Rule
203(a)
of
said
Re~u1ations.
Case #73—118 is a proceeding filed by Laclede Steel Company
under Section 40 of the Environmental Protection Act seeking review
ot an operating
permit
denial for which Laclede had made application
to the Agency on August
31,
1972.
The
x~emainingproceedings are variance petitions
seeking
relief
from various provisions of the Air Pollution Regulations and the
Regulations Governing the Control of Air Pollution,
as well as
Section 9(a) of
the
Environmental Protection
J~ct,
all as will be
set
fQrth
mare
fully
below.
8—317

—2—
Subsequent to the filing of the complaint,
variance petitions
and appeal above set forth, extensive pre—trial discovery, motions,
briefs, arguments,
and four days of public hearings s~ereheld,
after
which the parties entered into
a stipulation with the view of dis-
posing of pending matters before the Board.
The stipulation pro-
vides as follows:
“Subject to the conditions hereinafter set forth,
Complainant, Environmental Protection Agency,
and Respondent,
Laclede Steel Company, stipulate and agree as follows:
1.
Since 1969 or earlier Respondent has been engaged
in a program to expand and improve
its system for controlling
emissions from its electric melt shop.
(The term electric
melt shop
as used herein means the facility at Respondent’s
Alton plant containing its two electric arc furnaces and
continuous casting machine
‘the
primary production units’l,
and the material handling systems and equipment associated
with the primary production units and all auxiliary units,
systems and equipment provided for the proper operation of
the primary production units.)
Based upon
a study performed
by an independent source a comprehensive program utilizing
canopy hoods over the electric arc furnaces,
an improved
direct evacuation control
system, two additional new bag-
houses and interconnecting ducts was adopted.
Bids were
sought
from
various manufacturers and fabricators, and in
July,
1971, Respondent entered into
a contract under which
American Air Filter Co. agreed to perform certain engineering
and to supply the required materials.
A copy of that contract
is attached hereto.
Since
the Fall of 1971 Respondent’s
employees have been engaged in constructing and installing
the new system which will cost approximately $4,200,000.
By
June
30,
1973,
the canopy hoods, the two new baghouses and
associated and supplementary components will be installed
and ouerating.
This will eliminate the largest part of
Respondent’s emissions and bring it into compliance with
applicable laws and regulations.
The remaining portion of
the new system will be installed as conditions permit but in
any event not later than May 30,
1975.
2.
Respondent agrees that it will maintain its air
emission control system hereinabove described under the pro-
cedures set forth on the attached
‘Maintenance Program for EMS
Dust Collection System.’
Respon’dent will provide Complainant
with copies of all changes
in
or additions to said procedures
and
notify
it
of any deletions therefrom.
T~.
There is no dispute between the parties concerning the
aliega~ionscontained in Paragraph
1 of Count
I of the Amended
Complaint in PCB 72-221.
3—318

—3—
4.
With respect to the allegations of Paragraph
2 of said
Count
I:
a.
Complainant’s evidence offered by various wit-
nesses and photographs will show or tend to show that
the emissions of particulate matter from Respondent’s
electric melt shop have,
in the residential area to
the north of Respondent’s plant, soiled wash hanging
on clothes lines; prevented the enjoyment of fresh air
through open windows and the use of window fans;
become imbedded in
a freshly painted porch; dirtied
automobiles;
covered windows and desk tops in an
office with fine particles; deposited dirt on buildings,
furniture and appliances; interfered with outdoor
activities such as barbeques; and reduced the value
of real estate;
b.
Respondent’s opposing evidence will show or tend
to show that there has not been any objective reduction
in real estate values because of emissions of particu-
late matter from its electric melt shop,
that there
have been sporadic complaints in the past but much
lesser in number than is indicated by Complainant’s
evidence, and that the episodes shown by Complainant’s
evidence do not constitute violations of Section 9(a)
of the Environmental Protection Act on the dates and
within the time period alleged in the Amended Complaint;
c.
If this case were tried to completion, Respondent
would also have relied upon Section 49(e)
of the
Environmental Protection Act as
a defense to the charge
of
a violation of Section
9(a)
and would have introduced
evidence in support of that defense;
d.
If the Board finds
a violation of Section 9(a)
the
parties agree that
it
may enter an order under Section
33(b)
of the Environmental Protection Act requiring
or
directing Respondent to cease and desist from violations
of Section
9(a) and imposing a money penalty in an amount
not greater than $25,000.00.
5.
With respect to the allegations of Paragraph
3 of said
Count
I of the Amended Complaint and the allegations of Paragraph
6 of Respondent’s Answer thereto:
a.
It is stipulated and agreed by and between the
parties
hereto that said Paragraph 3 of the Amended
Complaint and said Paragraph
6 of Respondent’s Answer
thereto shall be and are hereby stricken and dismissed,
in all respects; and no evidence in respect of either
thereof
shall hereinafter be considered, except as is
contained in this Paragraph
5 of this Stipulation;
8—319

—4—
b.
It is stipulated and agreed by and between the
parties that,
for purposes
of
Rule
203(i)
(5)
of
‘Chapter 2:
Air Pollution’
of the Regulations of the
Illinois Pollution Control Board,
that Laclede Steel
Company has at all relevant times been an owner or
operator of an existing emission source which is required
to comply with Rule 3-3.2130 of the Regulations Governing
the Control of Air Pollution as amended Auqust 19, 1969;
said existing emission source including and primarily
consisting of the electric melt shop at the Alton plant
of Laclede Steel Company;
c.
It is stipulated and agreed by and between the parties
that neither party either admits or denies that,
in the
operation of the aforesaid electric melt shop, Laclede
Steel Company either complied with or violated the said
Rule 3-3.2130, but both parties further stipu1ate~and
agree that compliance with or violation of said
Rule 3-3.2130 at any time prior to date of the order
herein of the Pollution Control Board, shall not be
raised, questioned, contested or litigated for any pur-
pose whatsoever in any future action;
d.
It is stipulated and agreed by and between the parties
that,
in light of the foregoing, and for the most
propitious resolution of all matters concerned in any of
these proceedings,
for purposes of applying Rule 203 of
‘Chapter 2:
Air Pollution’ Regulations of the Illinois
Pollution Control Board,
to Laclede Steel Company, with
relation to the electric melt shop at its Alton plant,
the said Rule 203(i) (5)
shall be applicable and shall,
for all purposes, be considered to require compliance
with the applicable emission standards and limitations
of said Rule
203,
by, but in no event sooner than,
May 30,
1975.
6.
Respondent consents and agrees that on and after May 30,
1975 the emission standards and limitations of Rule 203 to be
applied to its electric melt shop shall be those contained in
Rule 203(a).
7.
The parties acknowledge that Complainant has been tem-
porarily prohibited
from proceeding with a presentation of the
issues raised by Count II of the Amended Complaint; and the parties
agree that by reason of the provisions of this Stipulation the
issuesraised in said Count II have become moot and that said
Count may be dismissed by the Pollution Control Board.
8
320

-5-
8.
Coincidentally with the entry by the Pollution Control
Board in Docket Nos. PCB 72-221 and 73-118 of an order in sub-
stantially the form appended hereto, Respondent will withdraw
or
the
Board
may
dismiss
the
requests
for
variances
which
are
the bases of Docket Nos. PCB 72-249,
72-250 and 72-251 now pend-
ing before the Pollution Control Board.
9.
In
view
of
the
agreements
and
settlements
reached
herein,
the parties agree that Docket No.
73-118 may be terminated by
the issuance of an operating permit for Respondent’s electric
melt shop, at its Alton plant, as requested by Respondent in its
application
which
forms
part
of
the
record
of
the
Environmental
Protection Agency filed by said Agency with the Pollution Control
Board
in
Docket
No.
PCB
73-118.
10.
The p.rovisions of this Stipulation shall become effective
and binding only upon approval thereof by an order of the Pollution
Control
Board.
A
draft
of
such
order
in
the
form
contemplated
by the parties is attached hereto.
If the Pollution Control Board
fails or refuses to enter such an order
(or one otherwise agreeable
to the parties thereto), then this Stipulation shall be null and
void and the statements, agreements and stipulations
of the parties
as set forth herein shall not be considered as admissions nor used,
introduced or sought to be introduced as evidence in any further
proceedings in Docket Nos.
PCB 72—221,
72—249,
72—250,
72—251
or 73—118, or in any other proceeding of any nature instituted
by Complainant or by any other person,
firm, corporation or
governmental agency.”
The Laclede Steel Company has adopted a maintenance program for
dust collection which provides as follows:
“Laclede
will on a routine basis lubricate all moving parts
and equipment in accordance with the manufacturer’s recommended
procedure.
Laclede will on a routine basis inspect all equipment asso-
ciated with the collecting system.
This inspection will include,
but not be limited
to, the following:
substation equipment; cooling
tower, pumphouse; main fans and motors; reverse air fans and
motors;
conveyors;
conveyor drives; water cooled sections, hoses;
piping;
dampers; damper drives;
and electrical control centers.
Included also will be inspection on a routine basis of ducts,
hoods, framework and housing for signs of wear from corrosion,
erosion, excessive heat,
and excessive moisture, along with
inspection of gauges, thermocouples and all other instruments to
insure accurate functioning.
In the baghouses each bag will be inspected on a routine
basis for holes or tears.
Manometer readings in the baghouses
will be recorded to check the efficiency of the cleaning cycle.
8—321

—6—
The procedures for these inspections and necessary checklists
and report forms will be worked out by the Engineering Department
in cooperation with American Air Filter Corporation and other
suppliers.
All reports are
to be prepared by the Central Main-
tenance Department which is and will be responsible for the main-
tenance of
the system and will be submitted to the Engineering
Department for review.
The Engineering Department will issue any
required
work
orders
to the Maintenance Department for any work
which these reports or periodic visual inspections by the Engineer-
ing Department reveal to be required.
‘Routine basis’
as used herein means such frequency of the
particular action involved
as
may be reasonably determined by the
Engineering Department to provide for proper operation of the
system and the protection
of Lacled&s investment.”
Pursuant
to
the
stipulation,
the
parties
have
submitted
a
proposed
orm of order which provides as follows:
“On
May
23,
1972
the
Environmental
Protection
Agency
filed
a
Complaint against Laclede Steel Company alleginq that
the
latter
had
caused
or
allowed
emissions
from
its
electric
melt
shop
located in Alton,
Illinois,
to violate Section 9(a)
of
the
Environmental Protection Act and Rule 3-3.2132 of the Rules
and
Requlations Governing Control of Air Pollution.
Thereafter, on
December
4,
:1972,
the
Environmental
Protection
Agency
filed
an
Amended Complaint
modifving
in
some
respects the allegations of
the original Complaint and adding a second Count alleging
that
Laclede
Steel
Company
was
on
April
14,
1972,
and
subsequently
so
operating its electric melt shop as to be in violation
of
Rule
203
(b)
of the Regulations issued on the latter date.
On or about
June 20,
1972, Laclede Steel Company filed three petitions
seek--
ing
variances,
respectively,
from the provisions of Rules
233(c)
and 202(b)
of the Air Pollution Regulations issued on April 14.
1972,
and
from Section 3-3.2130 of the Regulations Governing the
Control of Air Pollution as amended August 19,
1969, and
the
provisions
of Section 9(a)
of the Environmental Protection Act.
Finally,
on August 31,
1972, Laclede Steel Company filed
an
Application for an Operating Permit for its electric melt shop
After
several
intervening
revisions
and
resubmissions
that operat---
ing permit application was denied by the Environmental Protection
Agency on February 28, 1973 following which Laclede Steel Company,
on March
19,
1973,
filed a Petition for Review
of
said denial
under the provisions of Section
4~0of
the
Environmental
Protection
Act.
The foregoing constitute the several matters now before this
Board
under
the
docket numbers listed
in the caption hereof.
After extensive pre-trial discovery, motions, briefs and
arguments,
four days of public hearings and
numerous
pre—hearin~
conferences the Agency and Laclede Steel Company have entered into
a Stipulation by which they propose to settle these related cases.
That Stipulation has been presented to the Board under
the
provi-
sions of Rule 333 of the Board’s Procedural Rules.
8
322

—7—
Having considered
the
Stipulation and the entire record in
these
proceedings,
the
Board
finds
and
orders:
1.
Respondent
is found
to
have violated
Section
9(a)
of
the
Environmental
Protection
Act
by
emissions
into
the
atmosphere
from its electric
melt
shop;
2.
Respondent
is
hereby
ordered
to
cease
and
desi~t
from
any
further or
future
violations of Section 9(a)
of
the
Environ-
mental
Protection
Act
by
means of emissions into
the
atmosphere
from its electric melt shop;
3.
There
is
hereby
imposed
on
Respondent because of said
violation of Section
9(a)
as found by the Board a money penalty
in
the
amount of $25
,
000.
4.
The Board finds that Rule 203(i) (5)
of
‘Chapter
2: Air
Pollution’
of the Requlations of the Illinois Pollution Control
Board is applicable
to
Respondent with respect to ifs electric
melt shop and that it shall by
May
30,
1975 comply with the
provisions of Rule 203(a)
of said Regulations with re~pecfto
its electric
melt
shop;
5.
Count
Ii
o:
the
Amended Complaint fil~din Docket Nc.
?CB 72—221 is dismissed;
5~
The proceedino:s
in Dock~tNo~.PCB 72—249,
72—250, and
72-~2s:L
are
hereby
dismissed;
7.
The Environmental Protection Agency
is directed to issue
an
Operating Permi.t for Respondent’s electric
melt
shop pursuant
to the Application therefor as contained in the record of the
Aqency filed by said Agency with the Pollution Control Board in
Docket
~Jo.
PCB
73—118;
P.
The Stipulation filed in these proceedings is hereby
expressly
aDprcved and adopted as constituting part of this
Order.
Appended
to
the stipulation is an
exhIbit
containing the proposal
and
soecifications
submitted
by
American Filter Company, which
nroposals
have
been accepted by Laciede and
which
constitute the basis
for
the
compliance
pronram
hereinabove in the stipulation set forth.
Transcripts
of
the
hearinqs
have
been
submitted
to the Board and
a
review
~f
the
teStllft:)fl.y
estahir
shes
that.
Lad ede
s operation
has
caused
the
emission
of
particuial:es
of
a
degree
and
intensity
to
coast
:Ltoto
in teriarence
wi
ca
the
en~ovment
~i
:~fE1,
thereb
creating
a
‘~
a
L~tii
~CL
~
i
~
(cd
ne
11~ronmenta_
1’ ~
neL:~ove t~c:
:~
) i
C
p:~nlt:i
to
be
aarrar~ted
and
wiLl
imooso
it
as
na~ot o.t
o.~r final
order,

We have reviewed the program of compliance and believe that its
implementation will result in a substantial improvement of the air
quality in the Alton area.
We note that while the stipulated order
makes no reference to compliance with the particulate emission limita-
tions contained in the Rules and Regulations Governing the Control
of
Air
Pollution presently in effect, no variance from these rules
is provided and the present order gives no protection should violation
of these rules be
asserted.
Furthermore, the Company will be obliged
to reduce its emissions immediately pursuant to the cease and desist
provisions of the Order to comply with Section 9(a) of the Act so as
not to cause air pollution.
The Order will require compliance with
the provisions
of the newly-enacted air pollution regulations by the
operative date of May 30,
1975, with respect to Rule 203(a), which is
the more stringent regulation related to new equipment and operation,
applicable to
a company not presently in compliance with existing
regulations or subject to a variance.
Pursuant to the agreed Order, we shall impose a penalty in the
amount of $25,000 for the violations
of Section 9(a) aforesaid, and
direct that the Company cease and desist any violation with respect
to said section.
The variance petitions
#72—249, #72—250 and #72—251 are dismissed.
The Agency is directed to issue an operating permit for LaClede’s
electric melt shop pursuant to application as contained in the reocrd
of
proceeding
#73-118.
The
stipulation
and
all
documents
appended
thereto,
particularly
the
Maintenance
Program
for
EMS
Dust
Collection
System
and
the
e~thibit
designated Exhibit 11 are approved
and
incorporated
herein
by
refer-
ence.
This opinion constitutes the findings of fact and conclusions of
law
of
the
Board.
IT IS THE ORDER of the Pollution Control Board that:
1.
Respondent is found to have violated Section 9(a)
of the Environmental Protection Act by emissions into
the atmosphere from its electric melt shop,
as alleged
in the complaint;
2.
Respondent
is
hereby
ordered
to
cease
and
desist
from
any further violations of Section 9(a) of the
Environmental
Protection Act as
a consequence of emissions into the
atmosphere
from
its
electric
melt shop;
—8—
8
324

3.
There
is
hereby
imposed
on
Respondent because of said
violation of Section
9(a)
as
found
by
the
Board,
a
money
penalty
in
the
amount
of
$25,000.
Penalty
payment
by
certified check or money order payable to the State of
Illinois
shall
be
made
to
Fiscal
Services
Division,
Illinois Environmental Protection Agency,
2200 Churchill
Drive, Springfield, Illinois 62706 by July 21,
1973;
4.
The Board finds that Rule 203(i)
(5)
of
“Chapter
2:
Air
Pollution”
of
the Regulations of the Illinois Pollution
Control
Board
is
applicable to Respondent with respect
to
its
electric melt shop and that it
shall,
by
May
30,
1975,
comply
with
the
provisions
of
Rule
203(a)
of
said
Regulations
with
respect
to
its
electric
melt
shop;
5.
Count
II
of
the Amended Complaint
filed
in
#72-221
is
dismissed;
6.
The proceedings in Case Nos.
72-249, 72-250 and 72-251
are
hereby
dismissed;
7.
The
Environmental Protection Agency is directed to issue
an
Operating
Permit
for Respondent’s electric melt shop
pursuant
to
the
application
therefor
as
contained
in
the
record
of
the
Agency
filed
by
said
Agency
with
the
Pollution
Control
Board
in
Case
#73-118;
8.
The Stipulation filed in these proceedings is hereby
expressly approved and adopted as constituting part of
this
Order.
I, Christan Moffett, Clerk of the Illinois Pollution Control Board,
certify
that
the
above
Opinion
and
Order
was
adopted
on
the
‘~I ~
day
of
June,
1973,
by
a
vote
of
4~
to
~
üI
~.fY7~f
téL
—9—
8— 325

Back to top