ILLINOIS POLLUTION CONTROL BOARD
March 15, 1973
CITY OF DANVILLE,
Petitioner,
vs.
)
PCB 72—335
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
Larry Lessen, Attorney for Petitioner
Delbert Haschemeyer, Assistant Attorney General for the EPA
OPINION AND ORDER OF THE BOARD (by Mr. Henss)
Petitioner City of Danville makes several requests for
variance in the operation of its landfill. The principal
request is for extension of a variance we granted in PCB 71—282
allowing Petitioner a six month period ending June 9, 1972 to
apply final cover to a portion of its landfill known as the
~old site”. The entire tract consists of 56 acres. Thirty—one
acres previously used as a landfill (the old site), have been
closed since April 23, 1971. Fifteen acres not previously used
(the new site) have been developed for landfill operations more
recently under a contract the City obtained with H & L Disposal
Company.
In 1971 the City of Danville represented that immediate
close out and covering of the old 31 acre site would cost $89,000
whereas the program contemplated by them for the application of
cover within a period of six months would be accomplished without
any additional cost to the City. The record in 1971 indicated
that leachate emanating from the old landfill area ultimately
entered the Vermilion River but under all of the circumstances
we felt the six month time schedule for the application of final
cover was reasonable.
In August 1972, one month after the variance had expired,
the City of Danville filed its petition requesting extension.
Subsequently, the Petitioner filed an amended petition and waived
the requirement that ruling be made by the Board within 90 days.
7
—
28
7
2—
Petitioner contends that the failure tc meet the original
June 9, 1972 deadline was due to exceptionally wet weather, a
breakdown in “internal communications” and a 25 day strike by
municipal employees in May 1972.
Our conclusion from a review of the record.. however, is
that Danville simply did not make a serious effort to meet the
six month deadline. Rainfall during May 1972 was 2.36 inches
less than normal.
During that month H & L Disooaal Company
did not apply final cover at the old site recaure
it was allo
cating all of its efforts to
the
oneration of the
new
15
acre
landfill
site.
The toLal rainfall
for May, dune, July and
August 1972 actually war slightly
less than normal.
The
~internal
communieati~nn” problem of the riunicinafity
and a
25
day
strike by municipal employees woo
were
not involred in
the landfill
oneration could hardly constitute
~uatification
for
a one year delay in meeting the Standard,
The City
o:
Danvillo has applied f~na1
co or
tr~
‘uch
().~
the
area
hut should take immediate
steps
to coepl:
te tn
ore ject.
Petitioner contends that denial of the variance
eaLensien
would
impose
ar
unreasonable
and arbLtrar\’ hards~ir, unon the Cit,
because of the estimated $9,000 cost of
cc’rinc into corel
lance
immediately.
We regard this as a self~ir o~od ha~dm1:: nince
the municipality
has failed to oursue that coui:e
ehich
it
earlier represented would bring it into cc
lianee dun ine
1972.
According to the record the necessary additional
Tranpc) or and
esuioment was not made available until September
1972.
(P.
16, 68)
We
deny the request to extend the variance.
Other requests by the Petitioner,
however, ,v 1
Li a
Loed.
The EPA recommends that Petitioner
and
the
H
&
D~sposa~ Coopan’~
be nermitted
to
take those steps outlined in a ;uppielTlentai
permit granted by the Agency on October 2L1,
1972 which modify the
planned use of the 56 acre tract.
This modification
i.~ partly
due
to
earlier error in mapping the site.
The Petitioner
and
the
Acency have reached agreement on specific chan’os
regarding
trenching
and the
filling of low areas and ravines, and these agreements
will he incorporated in the Order.
ORDER
It is ordered that:
1. Petitioner’s request for a variance extension of
one year for the murpose of applying final cover
to the “old site~ 31 acre tract is denied.
Petitioner’s request for a variance is allowed
to the following extent:
7
—
288
o) ‘lime ~P/\
supplemental permit of October 24, 1972
is aeprovee
and the au~horizations incorporated
therein are included as a part of the variance.
h.
PetItioner
shall he permitted to excavate a
drainage ditch through the southwest corner
of the otd landfill
site.
Upon completion of
water drainage, Petitioner
will fill the
drainage to grade level only with proper landfill
co~cr material.
Petitioner will be permitted to
fill in low spots at the old landfill
site with
an accumulation of burned and exposed refuse
materia.l which is then to receive proper final
cover.
The area presently containing the burned
and
exoosed refuse is to be properly graded and
is not to be used for refuse disposal.
Petitioner
will be permitted to fill in a ravine located at
the old landfill site but only with proper final
cover material.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Opinion and Order was adopted
this
/4~
dayof March, 1973 by a vote of _____to
0
7
—
289
I