ILLINOIS POLLUTION CONTROL BOARD
    March
    8,
    1973
    ENVIRONMENTAL PROTECTION AGENCY
    *71-355
    V.
    CITY OF JACKSONVILLE
    OPINION AND ORDER OF THE BOARD
    (BY SAMUEL T.
    LAWTON,
    JR..):
    On May 23,
    1972, we entered our Opinion and Order on the Agency’s
    complaint, which had alleged violation of Section 12(a)
    of the Environ-
    mental Protection Act on four occasions,
    as a consequence of the City’s
    discharge of contaminants
    from its power and water treatment facilities
    into Mauvaise Terre Creek,
    a tributary to the Illinois River.
    The
    case was decided principally on the basis of a stipulation filed on
    February 25,
    1972, which conceded the heavy discharge of lime sludge
    into the creek and suspended solids sampling demonstrating violations,
    as alleged.
    The opinion pointed out, however,
    that the most significant
    issue was the remedial abatement program and the need to take immediate
    steps to clean up the creek and the settling lagoons which have been
    caked
    with lime sludge, causing overflowing and the continuing pollu-
    tion of the creek.
    Our Order provided as follows:
    “It is therefore ordered that the City of Jacksonville abate
    pollution of Mauvaise Terre Creek in accordance with the following pro-
    gram:
    1.
    The City shall proceed with all reasonable dispatch
    to eliminate the overflow of lime sludge from its water
    plant by the increase in the height of its lagoon berm,
    the same to be completed by June 1,
    1972.
    The City shall
    remove the existing lime sludge in its lagoons under the
    City’s contract with K.
    E.
    Vas Co., promptly upon the
    Company receiving a permit for its disposal site from the
    Environmental
    Protection
    Agency,
    or
    by
    any
    alternative
    disposal
    means
    which
    is permitted
    by
    the
    Agency.
    That.
    further, City is hereby ordered to proceed promptly
    to complete its plans and specifications for the installation
    of its lime sludge dewatering equipment and process and to
    provide that the liquid effluent from its water sludge la-
    goons be placed into the sanitary sewage system of said City.
    That complete plans and specifications are
    to be submitted
    to the Agency by August 1,
    1972, and construction
    to be
    completed within 10 months of the date on which
    a permit
    is
    issued
    by
    the
    Agency.

    2.
    That it is
    further ordered that the City of Jacksonville
    cease and desist from allowing chromium and oil wastes
    to be deposited into
    Mauvaise
    Terre Creek from City’s
    electric plant.
    That the City cease and desist the use
    of rust inhibitor containing chromium in its power plant.
    That the City further promptly complete construction of
    necessary facilities/for placing its water effluent from
    its power plant into the City’s sanitary sewer collection
    system.
    Said work
    is
    to be completed by June 15,
    1972.
    3.
    That within
    35 days of the date of this Order, the City
    shall post a bond in the amount of Ten Thousand Dollars
    ($10,000) and in
    a form satisfactory
    to the Agency to
    guarantee performance of the preceding orders.
    4.
    The City of Jacksonville shall, within thirty days hereof,
    submit to the Board and to the Agency a program for totally
    removing all lime sludge and any other contaminants which
    have become deposited in Mauvaise Terre Creek as a result
    of its discharges,
    or,
    in the alternative,
    proof that such
    a program is not economically feasible.
    The Agency shall
    comment upon such program or proof within 20 days thereafter.
    This proceeding remains open for such further order as the
    Board may deem appropriate on this
    issue.
    5.
    The City shall, within fifteen days hereof, submit to the
    Board and the Agency a complete written report indicating
    exactly what steps remain in its program for abating con-
    tinuing discharges along with the expected completion dates
    of each step.
    Thereafter, every thirty days,
    the City shall
    submit a full progress report on the program.
    6.
    The City shall pay to the State of Illinois, within thirty
    days hereof,
    the sum of One Thousand Dollars
    ($1,000)
    as
    a
    penalty for the violations
    found in this opinion.
    Payment
    shall be made payable to the State of Illinois and sent to
    the Environmental Protection Agency, Fiscal Services Division,
    2200 Churchill Drive, Springfield,
    Illinois 62706.”
    On June 20,
    1972,
    a further Order of the Board was entered modi-
    fying the second subparagraph of paragraph
    1
    of
    the
    Board’s
    Order,
    0
    read as
    follows:
    “That further, City
    is hereby ordered to proceed promptly
    to complete its plans and specifications for the installa-
    tion of its lime sludge dewatering equipment and process
    to provide that the liquid effluent from its water sludge
    lagoons be placed into the sanitary
    sewage
    system
    of~iid
    City or such other suitable alternative plan for dispi~sa1
    of
    lime
    sludge
    and
    effluent
    from
    the
    lagoons
    that
    meets
    the
    standards and approval of the Agency.
    That complete plans
    —2—
    7
    182

    and specifications. are to be submitted to the Agency by
    August 1,
    1972, and construction to be completed within
    ten
    (10) months of the date a permit
    is issued by the
    Agency.”
    Words underlined were added by the amendment.
    On June 22,
    1972,
    the City filed a program pursuant to paragraph
    4
    of the May 23,
    1972 order with respect to the removal of lime sludge
    and other contaminants now deposited in the creek.
    The program proposed
    two possible methods of reclamation,
    the first being the cleaning
    of the existing creek channel, which would
    cost approximately $600,000
    and the second being a relocation of the stream channel to a line
    par.dlel to and approximately 40 feet from the existing channel.
    The
    cost of relocation would be ap~toximately$200,000 and would take
    between
    4 and
    6 months for initial surveying,
    land acquisition and
    financing and three additional months for channel construction which
    .ould only be done between June and September, which were periods of
    minimal
    flow.
    The submission asks that the decision on the reclama-
    tion be deferred until Ju~ 1,
    1974.
    On June 29,
    1972,
    the Agency filed its comments on the program
    indicating that it could not approve the program,
    as proposed, parti-
    cularly in view of the suggested deferral of decision until
    June 1,
    1974.
    It was stated that additional information would be needed as
    to the
    anticipated cost for cleaning,
    the time involved for either cleaning
    or relocation and more detail relative to the relocation program.
    On July
    26,
    1972,
    the City filed a response to the Agency’s
    comments detailing the cost anticipated if the reclaiming and cleaning
    werefollowed which totalled $600,000 and time projections for both
    reclaiming and relocation which,
    in each instance, would entail
    a
    total of 390 days,
    or approximately
    13 months.
    On July 18, the Board had authorized further hearings on this
    matter ~s a result of the various
    submissions made.
    On October
    10,
    1972,
    a further comment was filed by the Environmental Protection Agency
    commenting on the stream relocation program and the stream reclamation
    program, again disagreeing with the deferral of decision until
    June 1,
    1974 but not indicating
    a preference as to which method, that of
    reclamation or relocation, be followed by the City.
    Hearing had been set for January
    10,
    1973.
    On December 11,
    1972,
    we received a motion from the Environmental Protection Agency to dis-
    pense with hearing, reciting the submission of the various documents
    outlined above and asking the Board to enter an Order based on all of
    the documents before it, which motion was concurred in by the City.
    On December 12,
    1972, we entered an Order stating that upon review of the
    various
    documents
    filed,
    we
    were
    unable
    to
    discern
    precisely
    what
    the
    ~$ency’s attitude is on the various alternative programs submitted on
    behalf of Respondent and directing that the hearings proceed so that
    the
    Board
    could
    be
    fully
    cognizant
    of
    the
    Agency’s
    attitude with respect
    —3—
    7
    18~

    thereto.
    Hearingwas held in Jacksonville on Tanuary 24,
    1973 at which
    time the City indicated that it preferred to pursue the program
    calling for the relocation of the stream which,
    in addition to costing
    approximately one—third of what stream reclamation would cost, would
    have significant environmental advantages, would minimize the inter-
    ference with the foliage and would provide for the burying of the
    lime sludge presently in the creek bed which would be abandoned as
    a consequence of the new realignment.
    The plan proposed would eliminate the need for hauling away the
    lime sludge and the need for finding a facility where
    it could be
    buried.
    Exhibit
    14, introduced in evidence, delineated both the
    present channel location and the proposed relocation alignment.
    The
    testimony indicated the difference between a $200,000 expenditure for
    relocation and $600,000 for reclamation.
    Earth removed by excavation
    of the new channel location would be used to bury the lime sludge in
    the existing channel
    (R.
    15).
    The program would minimize the need
    for installation of access roads and lessen the damage to the natural
    growth.
    The configuration of the new channel would also enable
    improved flow characteristics and minimize the likelihood of flood
    and overflows
    CR.
    17).
    Natural habitat would be relocated, where
    possible, and seeding and planting of trees would take place.
    A
    holding pond would be constructed at the north end of the proposed
    area to collect all lime sludge during the construction period.
    The
    program requires the approval of the State Division of Waterways
    (R.2l).
    It appears that both the City and the Agency are in agreement that the
    relocation program
    is preferrable and will,
    if followed
    as proposed in
    all respects ,result in compliance with the Board’s Order.
    We do not
    have a precise time schedule which can be used as the basis of
    a
    Board Order as we recognize that there are still several unresolved
    areas in respect to financing and land acquisition.
    We do, however,
    approve the program for relocation as submitted and will direct the
    City and the Agency to expedite its fulfillment.
    This opinion constitutes the findings of fact and conclusions
    of law of the Board.
    IT IS
    THE
    ORDER of the Pollution Control Board that the program
    of relocation of Mauvaise Terre Creek be implemented and completed
    at the earliest practicable date pursuant to Exhibit 14,
    the submissions
    of the City of Jacksonville and the testimony of witnesses heard at
    the hearing of January 24,
    1973.
    Within
    30 days
    from the date hereof,
    the City shall
    file with the Agency and the Board a proposed time sche-
    dule specifying the anticipated dates
    for submission of finalized
    plans
    for relocation,
    obtaining of the necessary financing,
    land ac-
    quisition,
    permit approval, initiation of construction and completion
    of
    the program.
    The Board reserves jurisdiction of the matter for
    —4--
    7
    184

    such other and further orders as may be appropriate.
    I, Christan Moffett, Clerk of the Illinois Pollution Control Bo~rd,
    certify that the above Opinion and Order was adopted on the
    3’
    day of March,
    1973,
    by a vote of
    3
    to
    o
    —5—
    7
    185

    I,
    V

    Back to top