ILL
    1 NOlS
    POLLUT I ON
    CONTROL
    BOARD
    November
    1,
    1973
    )
    LOBDLLL
    AND
    HALL,
    INC.
    )
    I
    iT.
    )
    PCB
    72-511
    )
    ENVIRONMENTAL
    PROTECTION
    AGENCY
    )
    )
    OPINION
    AND
    ORDER
    OP
    TIlE
    BOARI)
    (by
    Mr.
    Duinelie):
    This
    is
    a petition filed December
    26,
    1972
    for variance from
    a
    sewer ban imposed by non-certification of the Rockford Sanitary
    District.
    Hearing was held on March
    9,
    1973.
    Petitioner,
    a
    land development company, entered into an agreement
    in
    March,
    1972
    to
    purchase
    two
    tracts
    of
    land,
    one
    approximately
    123 acres and
    one
    7.5
    acres
    in
    Rockford.
    Petitioner then employed
    a professional
    engineering
    firm
    to prepare
    a piat and boundary survey
    and to begin construction drawings.
    Those plans were completed in the
    summer of
    1972.
    They also obtained construction bids
    froiri contractors.
    The proposed project would consist of single family dwellings, du-
    plexes, and townhouses condominiums
    to
    be built by other builders on
    contract or speculation.
    Petitioner sought certification by the Rockford Sanitary District
    of a Permit Application for Construction
    and Operation of
    a proposed
    sanitary sewer extension
    for the project hut was refused on November
    15,
    1972.
    The District refused to certify Petitioner’s permit appli-
    cation because
    th.e District knew that
    the proposed sewer extension
    was tributary to
    a sewer interceptor which ~vasdeficient in capacity.
    This
    refusal
    was
    based
    on
    a report
    by
    the District’s
    Consulting
    Engineers
    entitled
    the
    itarLDi~trictofRockford
    ~E~t~era~
    and
    Sewage
    Treatment,
    dated
    September.
    1972.
    The
    District’s
    certifi-
    cation
    is requir~T~inderRule 912(h)
    of the Water Regulations.
    The Environmental Protection Agency filed
    a recommendation for
    denial on January
    31,
    1973.
    It pointed out that
    the proposed
    developments would he served by the Supplementary Spring Creek
    Trunk
    Interceptor and the Spring Creek Trunk
    Interceptor both of
    which
    connact
    to
    the
    East
    Side
    Low Level
    Interceptor.
    The Agency stated
    that
    ‘a
    majority
    of
    the
    East
    Side
    Low
    Level
    Interceptor
    and
    800 lineal
    feet
    of
    the Spring Crek Trunk Interceptor have been designated
    as

    -2-
    ‘sewers deficient
    in capacity in
    1970’
    in the September 1972 Greeley
    and Hansen Report”.
    Peak flows
    of 0.391 MCD for the 123 acre tract
    and 0.090 MGD for the
    7.5 acre tract are estimated by
    the Agency.
    Lobdell
    and Flall
    on February 28, 1973 executed an indefinite
    waiver in
    this variance
    (R.3).
    In June
    the Board was ready to rule
    upon the case but Lobdell and Hall’s counsel asked to submit addi-
    tional facts
    about events which had occurred since the public hearing
    on MqTrch 9,
    1973.
    A Supplemental Petition was subsequently filed
    on July
    2,
    1973.
    The Agency on July 25,
    1973 filed
    a Supplement
    to Recommendation.
    The petitioner in the new material submitted states that
    the
    voters of the Sanitary District of Rockford voted 3-1
    on April
    3,
    1973 in favor of
    a $15,000,000 referendum to finance
    the
    local share
    of a $75,000,000 construction program over the next
    10 years.
    Lobdell
    and Hall further state
    that since the March 9,
    1973 public hearing
    the City of Rockford. has acted
    to remove some
    100 storm inlets
    which now empty into
    the “main sewage line”
    of the District by
    September
    1,
    1973.
    Lastly, the petitioner states that
    five Agency
    permits have been obtained on eight sections of sewers to relieve
    the East Side Low Level Interceptor and that “construction will
    commence immediately upon receipt of the Federal grant.”
    The Agency in its Supplement
    to Recommendation reaffirms
    its denial recommendation made six months earlier.
    It points out
    that the relief work on the sewer
    is contingent on Federal
    funds and no definite date for completion
    is
    available.
    It
    further discusses
    the basement flooding occurring
    in the area and
    again states that the petitioner’s
    developments would aggravate
    and/or expand sewer surcharging conditions.
    This
    case
    is somewhat similar
    to William
    H.
    Rogers v.
    EPA,
    PCB 73-1,
    decided May
    3,
    1973.
    In that case, involving the same
    sewer system, we granted
    a variance only on condition that 48-hour
    capacity holding tanks be installed and that truck transport be
    used after that
    time period if the sewers were still
    surcharged.
    However, holding tanks were not requested by the petitioner and
    thus
    me will not order them.
    The basement flooding with its attendant
    health and electrocution hazards must be balanced against
    the
    investment to date
    in the subdivisions and the need for housing and
    labor.
    While the petitioner alleges $165,997.17 in expenditures
    over and above
    the purchase price
    (which itself has not been paid)
    it should be pointed out that the bulk of this
    cost
    is
    $147,970
    in
    Lobdell and Hall employee charges against the project at hourly
    rates
    of $20,
    $40,
    and $50.
    These appear to be very high charges
    to make for one’s own employes services
    (R.
    142-3).
    9— 694

    -3-
    The
    ~ockfordSanitary District engineer testified that 36 calls on
    basement flooding in
    38 months were attributable to dry weather sewer
    capacity deficiency in the area
    to which Lobdell and Hall’s development
    would be tributary
    (R.
    195,
    218).
    He also stated that holding tanks might
    be an acceptable alternative
    (R.
    241).
    No costs on holding tanks appear
    in the record.
    We feel it best to deny the variance without prejudice at this
    time.
    The petitioner may refile giving the exact status of Federal
    funds for the sewer relief projects; requesting that we consider
    holding tanks; investigating the possible use of polymers
    to increase
    sewer transport capacity;
    and detailing the effect of the removal
    of the city storm inlets.
    This opinion constitutes the Board’s findings
    of facts and
    conclusions of law.
    ORDER
    The variance petition is denied without prejudice.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Opinion and Or~erwere adopted on the
    ~
    day of November,
    1973 by
    a vote of
    -
    0
    9— 695

    Back to top