ILLINOIS POLLUTION CONTROL BOARD
    October 18, 1973
    INCINERATOR, INC.
    PETITIONER
    V.
    )
    PCB 73—314
    ENVIRONMENTAL PROTECTION AGENCY
    RESPONDENT
    PEDERSEN & HAUPT, ATTORNEYS, on behalf of INCINERATOR, INC.
    LEE A. CAMPBELL, ASSISTANT ATTORNEY GENERAL, on behalf of the
    ENVIRONMENTAL PROTECTION AGENCY
    OPINION AND ORDER OF
    THE
    BOARD (by
    Mr.
    Marder)
    This action
    involves a petition to extend a variance from
    Rule 3-3.232 which
    expired on July 30, 1973. Said variance was
    granted on April 30, 1973. An extension until January 30, 1974,
    is requested.
    On August 1, 1973, the Agency filed a recommendation for an
    extension stating that a denial of this petition would impose an
    arbitrary hardship on the Petitioner.
    Incinerator, Inc., owns and operates a municipal refuse in-
    cinerator near Cicero, Illinois. The plant contains two rotary
    kilns capable of incinerating 500 tons of refuse per day. The
    plant is now equipped with high energy Venturi type air pollution
    control equipment. This equipment, however, is not functioning
    up to the performance guarantee which was entered into by Petition-
    er and their contractor, Zurn.
    Under normal conditions this request could be handled fairly
    routinely. However, in this case a long and erratic history must
    be considered. The following is a step by step history of Incin-
    eratorts dealings with the Environmental Protection Agency.
    I. PCB 71—69
    Flagrant and obnoxious discharges were proven against Incin-
    erator in an enforcement action brought against Petitioner by the
    Environmental Protection Agency on April 1, 1971. Very meager
    attempts to control these emissions were undertaken prior to this
    9
    577

    complaint. Citizen testimony during the hearing in this action
    attested to severe infringement on their ability to enjoy normal
    living conditions. As a result of this action, a large ($25,000)
    penalty and a Cease and Desist Crder were entered by the Board.
    The size of the penalty and the severe step of a Cease and Desist
    Order attest to the magnitude of the violations. The text of the
    Order in PCB 71-69 is made a part of this ooinion to reiterate the
    severity of the order.
    “1. Within ten days from the entry of this order, In-
    cinerator shall cease and desist from the operation
    of its facility in Cicero, Illinois. Operation of
    the facility shall not commence until Incinerator has
    installed and has ready for operation either the Det-
    rick-Jens wet baffle
    system
    or another comparable
    control device approved by
    the
    Agency, and until it
    has filed the variance petition required under para-
    graph 3 of this order, and until it is in compliance
    with paragraph 4 of this order. The control device
    installed must adequately abate
    the
    nuisance pollution
    as described in the opinion.
    2.
    In the event that Incinerator decides to proceed with
    the installation
    of the equipment provided for in par-
    agraph 1 of this order, it. shall post a performance
    bond in the amount of
    $200,000
    when it seeks
    approval
    from the Agency for the equipment provided in para-
    graph I.
    This sum, in the form of a bond or other
    adequate security satisfactory
    to the Agency, shall
    be forfeited to the State of Illinois should Inciner-
    ator
    operate its facility in violation of paragraph 1
    of this
    order. Upon completion of the installation
    of the equipment referred to
    in paragraph 1, this
    per-
    formance bond shall be remittod~
    3.
    Before Incinerator may commence operation of
    the
    fac-
    ility
    after shutdown, it shall
    submit to the Agency
    and
    the Board a supplemental petition for a variance.
    Such petition shall contain a firm program for bring-
    ing the facility into compliance with the existing
    Illinois standards. Upon the filing of such program,
    the Board shall authorize a further hearing on
    the
    variance petition and shall enter such further order
    as
    it
    deems necessary under the circumstances,
    4. Even
    after
    compliance with the preceding paragraphs
    of this order, Incinerator shall not operate its fac”
    ility unless the thermocouple devices in
    the
    gas stream
    are operating adequately
    and properly
    transmituing in—
    formation to the recorder device.
    570

    —3—
    5. Even after compliance with the preceding
    par-
    agraphs of this order, and until Incinerator
    has installed and has in operation equipment
    which will bring it into compliance with the
    applicable Illinois standard, it shall not ac-
    cept for incineration refuse other than dom-
    estic garbage or industrial paper wastes. Nor
    shall the amount of wastes incinerated ever
    exceed 500 tons per day at 20 moisture content.
    6. In the event that Incinerator decides to pro-
    ceed with the installation of the equipment
    provided for in paragraph 1 of this order, it
    shall file monthly progress reports with the
    Agency.
    7. Incinerator shall pay a penalty to the State
    of Illinois in the amount of $25,000.”
    II. A motion was filed by Incinerator, Inc., for stay of ord-
    er. The penalty was stayed pending appeal, with the provision
    that a bond in the penalty amount be posted. The plant was al-
    lowed to reopen at 50 percent capacity due to the filing of a
    compliance program.
    III. PCB 71—324.
    A variance was granted to Incinerator until November 1, 1972,
    Various conditions were imposed under this variance including:
    A) A 50 percent reduction in capacity
    B) An interim check (at six months) by the Agency
    C) A $300,000 bond
    D) A 0.1 grains per Standard Cubic Foot particulate
    concentration limitation
    Step (D) is noteworthy in that under Rule 3-3.232 emission
    levels are 0.2 gr/scf. Incinerator, however, has been required to
    meet a much tighter 0.i gr/scf limit.
    IV. PCB 72—416.
    An extension to the above variance was issued until January
    31, 1973. This extension was granted because Petitioner had suff-
    ered unexpected delay on electrical supply, and because some of its
    equipment was damaged in transit.
    One additional condition was imposed at that time.
    The require-
    ment
    was that a stack test be run and the results monitored by
    the Agency.
    V. PCB 73-23.
    A further extension was granted until April 30,
    1973. The
    S
    57~

    —4—
    reason for this extension was that the weather did not permit stack
    testing.
    An additional condition imposed
    at
    that time was
    the
    requirement
    for two more bonds
    in the amount of $60,000.
    VI. PCB 73—204.
    Yet another extension was granted until July 30, 1973. The
    reason for this extension was to allow more time for its testing
    company to complete laboratory work.
    This tortuous path leads us to the present PCB 73-314, which re-
    quests still another extension. Petitioner alleges that its now
    installed scrubber has malfunctioned and is obtaining particulate
    emissions of 0.156 gr/scf.
    PCB 71—325 calls for a 0.1 gr/scf lim-
    it. Perhaps
    more relevant is that by December 31, 1973, Petition-
    er will fall under Rule 203 (e) (2); at that time the effective
    standard will be 0.08 gr/scf.
    Steps are underway
    to correct the malfunctioning scrubber, and
    in Pet. Exhibit “A” a letter by
    Zurn Industries outlines the steps
    being taken.
    The variance extension requested will run right into the worst
    weather of the year. If
    this extension is granted, it
    would ocen
    up the request for yet another extension on the same grounds
    used
    in PCB 73-2 3 (poor weather for stack tests).
    The only factor in
    Petitioner’s
    favor is that citizen complaints have dropped off
    dramatically as a result of interim steps taken.
    As mentioned in PCB 72-416, the absence of a variance does not
    require the incinerator to be shut down. It
    simply leaves the Pet-
    itioner open to an enforcement action. The same facts demonstrating
    arbitrary or unreasonable hardship in a
    variance proceeding would
    constitute a defense in an enforcement oroceeding, should one en-
    sue.
    In Zurn’s letter to Petitioner (Exhibit A), it is evident that
    with a little effort complete compliance could be accomplished very
    shortly after
    the
    date of this order.
    In PCB 71—324, a condition for a variance grant was that Incin-
    erator comply with a 0.1 gn/scf loading. Upon termination of this
    variance the required loading will revert to 0.2 gn/scf as required
    by Rule 3-3.232. This fact may indeed render this action moot.
    However, it is important for Petitioner to remember that on Decem-
    ber 31, 1973, the new Rule 203 (e) (2) will be effective, which
    will limit emissions to 0.8 gr/scf of effluent gas corrected to 12
    percent carbon dioxide.
    9— 580

    —5
    This Opinion constitutes the findings of fact and conclus-
    ions of law of the Board.
    ORDER
    IT IS THE ORDER of the Pollution Control Board that Incinera-
    tor’s petition for a variance is hereby denied.
    IT
    IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, certify that the above Opinion and Order was adopt-
    ed by the Board on the
    f~’~
    day of ‘~J~--~J
    ,
    1973, by
    a vote of
    ~ _____to
    ~
    9—581

    Back to top