ILLINOIS POLLUTION CONTROL BOARD
    September 26, 1973
    CITY OF ST. CHARLES
    )
    )
    and
    )
    )
    SWIFT AND COMPANY
    )
    )
    v.
    )
    PCB 73-247
    )
    ENVIRONMENTAL PROTECTION AGENCY
    )
    Mr. Richard J. Kissel and Mr. Alvin Catella appeared on behalf of
    City of St. Charles and Swift and Company;
    Mr. John B. Slattery, Assistant Attorney General, appeared on behalf
    of Environmental Protection Agency.
    OPINION AND ORDER OF THE BOARD (by Mr. Dumelle):
    Petition was filed June 14, 1973 by the City o:E St. Charles
    (tlCityU) and Swift and Company (“Swift”) for variance from varsious
    water pollution regulations.
    The Agency filed a recommendation on July 27, 1973 and essentially
    recommended denial. On August 22, 1973, a supplemental recommendation
    was filed recommending a grant subject to certain conditions. Public
    hearing was held on August 27, 1973 in St. Charles.
    The City has a sewage treatment plant which for the 15-month
    period from January 1, 1972 to March 31, 1973 has been averaging
    21 mg/l BOD5 and 73 mg/l suspended solids. The relevant standard,
    Rule 404(b), is 20 mg/i BOD5 and 25 mg/l suspended solids effective
    at least as early as July 1, 1972. Variance is requested from this
    Rule until a plant expansion can be completed by August 15, 1974.
    Swift has a new dry sausage plant under construction in St. Charles.
    The plant will employ 262 persons with an annual payroll of $3,525,000
    and will cost $16,000,000. It will begin operations about October 29,
    1973 and over a 12-week period will take over processing now housed
    in an oH, obsolete plant in Chicago. Swift
    was
    denied an operating
    permit by the Agency on March 30, 173 because the St. Charles plant
    was near its design capacity. The Agency :interprets their variance
    request as being from Rules 901 and 902.
    In considering the City’s variance, it is useful to treat it as
    separate and distinct from Swift. The effect of the
    additional load
    from Swift of initially 170,000 gpd.
    with
    pretreatment is stated by
    9
    — 343

    -2-
    the City’s consulting engineer, Mr. Bernard G. Bosch, to be
    “minimal” (R. 26). We then have to consider whether the City of
    St. Charles, with a suspended solids discharge almost 200 over
    a July 1, 1972 standard, has tried to rectify its problem in good
    faith or has caused its problem to come into being by delay.
    The verified petiti.on recites the delay occasioned the City
    by the Northeastern Illinois Planning Commission between April, 1971
    and August, 1972. This is a 16-month period coming at a significant
    point in the development of expansion plans. While we give this
    argument some weight, we do point out that the Board cannot grant
    to NIPC the power to alter deadlines of the Board. We would urge
    that wastewater treatment planning be kept current for all
    communities in order that planning itself not be an excuse for continued
    pollution. Further, NIPC would be the first to say that its recommenda-
    tions are not binding upon the Federal government as it decides to
    issue construction grants. There are actual cases, as NIPC knows, in
    which NIPC recommendations have not been followed by the Federal
    government. Thus, we might say ~Eff~tSt. Charles should have followed
    an independent course and requested Federal funds without NIPC. But
    the appeals from this course would probably have consumed as much time.
    St. Charles now has the Federal grant of $1,205,925 and is under
    construction.
    Thus, the problem is fast on its way to solution. Phase I of
    the plant expansion is due to be completed November 1, 1973 (R. 17,
    19). Phase II, which will raise the plant capacity from 4.0 MCD to
    8.0 MCD will be done by April 1, 1975, but the critical new final
    tanks will be done August 15, 1974.
    We grant the variance to the City until August 15, 1974 allowing
    them to discharge 25 mg/l BODE (instead of 20) and 37 mg/i suspended
    solids (instead of 25) until that date to be computed in a manner as
    specified in Rule 404(h). The deposition of Edward Marek of the
    Agency (August 2, 1973) states that no adverse effects have been
    observed, but also that high river flows have prevented sampling.
    We do not require the hiring of an additional sewage treatment
    operator because that is dependent upon the supply of operators. If the
    plant is understaffed and hence, operated incorrectly, then the Agency
    has a remedy in an enforcement action if it chooses. We also do not
    require the extra filter because the demonstration filter can be used
    in an emergency.
    As to Swift, the Agency would require pretreatment of flows and
    a nocturnal discharge of much of it. Since Swift agrees, we will
    require this. We do not hold with the Agency on not permitting a
    Swift discharge beyond 170,000 gpd., if Phase I is not done. To do
    so would jeopardize the orderly startup of this new food processing
    plant. While no evidence appears in the record, the additional 200,000
    gpd. at full Swift flow should not make a major difference on an
    effluent already at 4 MGD and using by then improved final tanks. We
    9— 344

    -3-
    grant the variance to Swift from Rules 901 and 902,
    This Opinion constitutes the findings of fact and conclusiofls
    of law of the Board.
    ORDER
    1. Variance is granted to the City of St. Charles from Rule 404(h)
    until August 15, 1974 to discharge BOD5 at up to 25 mg/i and
    suspended solids at up to 37mg/i computed as in Rule 404(h).
    2. The construction and operation of the final tanks of Phase II
    shall be the first portion implemented by the City and shall be
    completed by August 15, 1974.
    3. Polymers shall be added to the clarifying tanks and/or activated
    carbon shall be added to the aeration tanks by the City as con-
    sidered necessary by the Agency to meet the BUD5 or suspended
    solids limits set in #1 above.
    4. A performance bond of $5,000 is required of the City to insure
    construction of the equipment referred to in #2 above.
    5. Variance is granted to Swift and Company from Rules 901 and 902
    to permit it to connect its new dry sausage plant to the St.
    Charles sewer system.
    6. Maximum flow to be discharged by Swift shall be 370,000 gpd.pre-
    treated to not more than 150 mg/i BOD5, 150 mg/i suspended
    solids, and SO mg/i of oil; all based upon 2~-hour,30 day
    average composite sampling.
    7. Fifty-four percent or more of Swift’s wastewater shall be dis-
    charged between 8:00 p.m. and 8:00 a.m.
    8. i~:nthly reports of the volume, time of flow and strength of
    ~~tewater in sufficient detail to check difference to the condi-
    ~cns of this Order shall be filed with the Agency and the City
    by Swift no later than the 20th day of the month following each
    calendar month after November, 1973 for the duration of the
    variance.
    9. A performance bond in the amount of $20,000 is required of Swift
    to insure construction of the pretreatment equipment required
    to meet #6 above.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control Board,
    certify that the abo e Opinion and Order was adopted by the Board on
    the
    ~
    day of
    _______________,
    1973, by a vote of ~
    to C)
    9
    345

    Back to top