ILLINOIS POLLUTION CONTROL BOARD
    September 13, 1973
    HOWARD
    AND
    NARY JO PERREAULT ADAMS,
    Petitioners,
    vs.
    )
    PCJ3
    73—266
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    Howard Adams and Mary Jo Adams pro se
    James
    K.
    Jenks, Assistant Attorney General for
    the
    EPA
    OPINION AND ORDER OF THE BOARD
    (by
    Mr.
    Henss)
    Petitioners purchased real estate in Lake Forest,
    Illinois
    during October 1971 with the intention of constructing
    a resi-
    dence on it.
    The real estate lies within the area serviced by
    the Lake Forest sewage treatment plant in the North Shore Sani-
    tary District, and at the time of the purchase Petitioner
    admittedly had knowledge of the sewer connection prohibition
    (Order No.
    7 of League of Women Voters vs.
    North Shore Sanitary
    District, PCB 70—7,
    12,
    13,
    14).
    Construction of the residence commenced in June
    1972.
    In
    order to comply with
    the
    “sewer ban’1, Petitioners installed a
    k~oldingtank specified by
    a sanitary engineer and approved by the
    City of Lake Forest.
    Mr.
    and Mrs. Adams say that
    “a representative
    frcm
    the City was personally present when the holding tank was
    installed,
    and he oversaw such installation”.
    Sewage accumulated
    ir the tank
    is periodically removed by
    a commercial service
    ccmpany.
    Normal usage of the plumbing by this family of four
    would require emptying of the tank every
    2 or
    3 days.
    Occupancy of the new residence began in February 1973.
    Petitioner has now experienced
    a back up of sewage into the resi-
    dence causing damage to floors and carpeting.
    The sewage back up
    was termed a “gross inconvenience, in addition
    to which an
    unsanitary condition exists which could be injurious
    to Petitioners,
    their children and others”.
    Petitioner has attempted to minimize
    the sewage problem by performing such daily routines
    as laundering
    and bathing at commercial facilities or at the homes of friends,
    which are within the area serviced by the North Shore Sanitary
    9
    257

    —2—
    District.
    Toilets and other plumbing facilities
    in their home
    are used as little a~possible.
    Even with these adjustments,
    Petitioners must have their holding tank emptied about once
    a
    week at
    a cost of about $150 per month.
    The
    record does not
    disclose
    where
    this sewage is
    taken.
    Finally, Petitioner
    advises that
    a septic tank in
    this
    location is not reasonable
    because of
    the
    expense and the possible loss of trees from
    the
    digging up of the yard and grounds.
    A variance is now recuested to allow a sewer line connection
    to
    the Lake Forest sewer system.
    The Environmental
    Protection
    Agency
    recommends
    that the variance be denied.
    The Lake Forest
    plant,
    a primary treatment facility was designed to
    treat an
    average
    flow
    of
    1.2 MCD.
    The current average flow of 1.33
    MCD
    receives
    alum
    treatment,
    primary sedimentation and chlorination
    prior to being discharged to Lake Michigan.
    Maximum design flow
    is
    3.0
    MCD.
    During peak
    flow periods sewage with only sodium
    hypochlorite added is bypassed to the Lake.
    Petitioner’s
    connection
    would
    generate
    approximately
    400 gallons of sewage
    per
    day and would add to the current sewage plant bypassing
    problam.
    Petitioner’s hardship is
    clearly
    self
    imposed.
    With the
    simplest mathematics
    they could have calculated that
    a
    1200
    gallon tank will become full in
    3 days when normal usage
    is
    400
    gallons
    per
    day.
    Obviously,
    when
    full,
    it
    must
    be
    emptied
    in
    order
    to
    allow
    continued
    usage.
    The
    alternative
    is
    sewage
    on
    the
    carpet.
    We
    have
    said:
    11f
    the
    ban
    is
    to
    have
    any
    meaning,
    we
    must
    hold,
    and
    we
    have
    held,
    that
    in
    general
    one
    who
    coriunences
    construction
    after
    a
    connection
    ban
    is
    imposed
    does
    so
    at
    his
    Peril;
    and
    any hardships resulting
    from actions
    taken
    after
    that
    date
    must
    he
    regarded
    as
    self—inflicted
    and
    entitled
    to
    no
    con-
    sideration11.
    Simpson
    v.
    Cinnamon
    Creek,
    PCB
    72-368;
    Cinnamon
    Creek
    v.
    EPA,
    PCB
    72-377.
    The
    data
    contained
    in
    the
    Agency’s
    Recommendation
    indicate
    that
    the
    Lake
    Forest
    treatment
    facility
    is
    not
    in
    compliance with
    our Regulations.
    However,
    we
    have
    been
    advised
    that
    Phase
    I
    of
    the
    Clavey
    Road
    project
    is
    within
    three
    weeks
    of
    completion.
    Hopefully,
    the
    Lake
    Forest
    treatment
    plant
    tie-in
    to
    the
    Clavey
    Road plant
    will
    be accomplished within one
    week of full operation
    at the Clavey Road
    plant.
    Following that tie-in
    to Clavey Road,
    Petitioners sewer connection
    will
    he acceptable.
    As
    we
    did
    in Bereskin
    and
    Solomon
    vs.
    EPA,
    FCB
    73-143,
    we
    will
    allow
    a
    conditional
    variance
    in
    order
    that
    Petitioner
    may
    proceed
    with
    construction
    work
    up
    to
    the
    sewer
    line
    short
    of
    actual connection.
    This will allow Petitioner
    to connect to the
    Lake Forest sewer system immediately after the Clavey Road plant
    begins accepting the
    additional
    sewage.
    Petitioner’s
    sewer
    connection shall not take place until after the connection
    of
    9
    258

    —3—
    Lake Forest treatment plant
    to the Clavey Road facility.
    ORDER
    It
    is the order of the Board that:
    Petitioners are granted
    a variance from our Order prohibiting additional sewer connections
    to the North Shore Sanitary District.
    This variance is subject
    to the following condition:
    No
    connection
    shall
    be
    made
    to
    the
    subject
    sewer until after the Lake Forest system has
    been tied in to the Clavey Road plant and the
    additional capacity of the North Shore Sani-
    tary District following the completion of
    construction currently underway is sufficient
    to meet the effluent standards of the Pollution
    Control Board.
    Mr. Odell abstains.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board,
    hereby
    certify
    the
    boy
    Opinion
    and
    Order
    was
    adopted
    this
    /31’~
    day
    ~
    ,
    1973 by a vote of
    3
    to ~
    9
    259

    S
    I

    Back to top