ILLINOIS POLLUTION CONTROL BOARD
    September 6, 1973
    REILLY TAP.
    AND CHEMICAL CORPORAT ION,
    Petitioner,
    vs.
    )
    PCB 73—218
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    Max K.
    Naegler, Attorney for Petitioner
    Thomas Cengel, Assistant Attorney General for the EPA
    OPINION AND ORDER OF
    TIlE BOARD (by Mr.
    flenss)
    Reilly Tar and Chemical Corporation requests a 3 month
    variance from Rule 206(c) of the Air Pollution Control Regulations
    which on December 31, 1973 will limit the emission of carbon
    monoxide.
    Petitioner has operated its coal tar distillation plant in
    Granite City, Madison County, Illinois since 1932. It purchases
    crude high temperature coal tar, a “waste’~ product of steel mills,
    and distills it to produce various grades of coal tar pitch and
    creosote. The crude coal tar is stored in tanks and transferred
    to stills for the distillation process. Petitioner utilizes four
    10,000 gallon stills and two 6,000 gallon stills to process about
    520,000 lbs. of crude coal tar daily. The plant operates 5 days
    per
    week
    and employs about 54 persons.
    After each still is filled with crude, heat is applied, and
    this distills off creosote oil vapor and various noncondensable
    gasses. The distilled gas and vapors are passed through a condenser
    to lic~uify the creosote, which is collected in receivinn pans.
    The noncondensable gasses, includinq carbon monoxid~, exit to the
    atmosphere throuch vents at the receivinq pan~
    An independent test laboratory analyzed these gasses by gas
    chromotography in 1972. The test revealed that Petitioner~s total
    carbon monoxide release was 1.40 lbs,/hr, Using an air flow rate
    of 7 cfm, the Agency estimated the 1.40 lhs./hr. emission rate was
    equivalent to about 9,000 ppm. Rule 206(c) allows Petitioner to
    emit a maximum of 200 ppm (adjusted to 50 excess air) after
    December 31, 1973.
    9
    197

    —2—
    Petitioner’s first three applications for operating permit
    were denied by the Agency for “lack of information, lack of data,
    and lack of compliance schedules’t. A fourth application was denied
    on May 2, 1973 and Reilly Tar then filed the variance petition.
    At this time, there are no control devices on the distillation
    unit capable of reducing carbon monoxide emissions to acceptable
    levels. Petitioner has submitted a Compliance Plan and Project
    Completion Schedule for the installation of a low volume waste gas
    burner, type D.F.S. Fumeabator. This device will burn the various
    gasses which at the present time are emitted to the atmosphere, so
    that the final emission will be essentially water vapor and carbon
    dioxide. The installation of this control equipment will be on the
    following schedule:
    Part A
    -
    July 1973
    -
    Evaluation of the Fumeabator on
    Petitioner’s new enamel plant (also located
    in Granite City).
    Part B
    -
    October 1973
    -
    Petitioner to apply for a construction
    permit for the Fumeabator on its coal tar
    refinery.
    Part C
    -
    November 1973
    -
    Petitioner will enter into a
    binding agreement to purchase the equipment.
    Part D
    January 1974
    Petitioner expects delivery of the
    equipment.
    Part E
    -
    March 1974
    -
    Petitioner expects equipment to be
    installed and operational and expects to
    demonstrate compliance with Rule 206(c) of
    the Air Pollution Control Regulations.
    The record shows that a Fumeahator has been installed at
    Petitioner’s new enamel plant which is located adjacent to the coal
    tar refinery. William Justin, Petitioner’s Director of Environmental
    Control, testified that the Fumeabator system at the enamel plant was
    received with safety devices normally considered as standard components
    of such equipment. However, because of the highly flammable nature of
    the Reilly gasses, the Reilly engineering staff decided to devise an
    additional protection system to insure that fire could not flash back
    through the piping network and cause an explosion. The additional
    safety devices include steam—jacketed flame arrestor, steam ejector
    to move the gas stream and automatic valves. The presence of naphtha—
    lene in the waste gas of the Reilly plant presented a special problem
    in the design of the system. Naphthalene solidifies at normal ambient
    temperatures and could accumulate at certain critical points in the
    piping network thereby plugging the safety devices. These and other
    9
    198

    —3—
    operational difficulties have delayed start-up of the enamel plant,
    but Petitioner advises that the delay probably would not affect the
    Project Completion Schedule as submitted. Petitioner indicates
    that the installed cost for the incinerator system at the distillation
    plant would be about $20,000.
    Although Reilly has similar onerations at other locations,
    its Granite City facility was selected as the site for installation
    and testing of the incinerator control system. Petitioner plans to
    use this method of pollution control not only at Granite City but
    at its other factories if the method proves satisfactory.
    A company official testified that production capacity of
    $40,000 to $70,000 per week would be lost if the plant were forced
    to cease operations during the first three months of 1974. The
    record indicates that Petitioner could install the incinerator
    equipment at the distillation plant and have the equipment in
    operation by the December 31, 1973 deadline. A back up incinerator
    device has been located and is available in the event the first system
    is found unsatisfactory.
    Initially, the Agency recommended that we deny the variance.
    This recommendation was changed after Petitioner demonstrated to
    the Agency that, because of the potentially explosive nature of the
    waste gas stream, complete testing was necessary to insure the safety
    of Reilly’s employees and to protect the plant from fire. In its
    Amended Recommendation, the EPA recommends granting the variance.
    Petitioner’s carbon monoxide emissions, while above the allow-
    able rate, are not alarmingly high. Testimony indicates that
    Petitioner’s hourly carbon monoxide emissions are equivalent to
    carbon monoxide emissions from 12 automobiles driving 10 miles.
    We believe the primary concern in this case must be for the
    safety of
    the
    employees. Petitioner is testing the new incinerator
    now. A back up device will
    be
    available in the event the Fumeabator
    system proves unsatisfactory,
    The Project
    Completion Schedule
    indicates
    that
    Petitioner will
    achieve compliance within three months
    of the deadline. We do not find this delay unreasonable in view of
    the dangers inherent in installation of an untested system. We
    shall grant the variance subject to conditions which will assure
    installation of the control equipment.
    ORDER
    It is the order of the Board that:
    1. Reilly Tar and Chemical Corporation is granted variance
    from Rule 206(c) of the Air Pollution Control Regu-
    lations at its Granite City tar distillation plant
    until March 31, 1974.
    9
    199

    —4—
    2. Variance is conditioned upon the submission to the
    Agency of quarterly reports detailing progress or
    lack of progress in installation of the Fumeabator
    or other control equipment at the Granite City tar
    distillation plant. Such reports shall commence
    on October 1, 1973.
    3. Petitioner shall, by October 1, 1973,. post a bond in
    the amount of $10,000 in a form acceptable to the
    Environmental Protection Agency, quaranteeing the
    installation and operation of suitable carbon monoxide
    control equipment by March 31, 1974. The bond shall
    be mailed to: Fiscal ServicesDivision, Illinois EPA,
    2200 Churchill Road, Springfield, Illinois 62706.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, he~ebycertify the above Opinion and Order was adopted
    this
    (, ~
    day of
    ~Vr4k.w.6.4.&.~
    1973 by a vote of 4/ to ~
    9
    200

    Back to top