ILLINOIS POLLUTION CONTROL BOARD
    August 30, 1973
    )
    BENJAMIN HARRIS ?~ COMPANY
    )
    )
    )
    v.
    )
    PCB 73-215
    )
    )
    ENVIRONMENTAL PROTECTION AGENCY
    )
    )
    ORDER OF
    THE
    BOARD (by Mr. Durnelle)
    It is the Order of the Board that:
    1. Variance is granted from Rules 2-2.54 and 3-3.111 to operate
    the cupola, rotary furnace and two crucible furnaces until
    February 1, 1974 provided however that the cupola and rotary
    furnaces shall never be operated simultaneously during the
    term of the variance.
    2. Petitioner shall report monthly beginning October 1, 1973 to
    the Agency the time and duration of usage of the equipment
    listed in No. 1 above and the weight and type of materials.
    processed by each cupola or furnace listed above.
    3. Petitioner shall accomplish “Phase One” and “Phase Two” of
    its program as listed in the variance petition. All gas
    flow and analysis data shall be submitted to the Agency within
    three (3) days of receipt of it by the petitioner.
    4. The Agency shall issue permits necessary to accomplish “Phase
    One” and “Phase Two”.
    5. Petitioner shall
    exert all efforts to obtain engineering data
    (especially gas flow) in the time of this variance in order to
    be prepared to
    install proper control equipment should the
    variance be extended.
    IT IS SO ORDERED.
    I, Christan L. Noffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Order was adopted on the
    Jo~’
    day of August, 1973 by a vote of
    3—o
    Christan L. Moffett,Q~4lerk
    Illinois Pollution L~’ntrol Board