ILLINOIS POLLUTION CONTROL BOARD
    January 3, 1974
    GENERAL TIRE AND RUBBER COMPANY
    )
    (MOUNT VERNON TIRE PLANT),
    Petitioner,
    v.
    )
    PCB 73—371
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    Don Musick and William Henrick, Attorneys for Petitioner
    Fred Hopper, Assistant Attorney General for the EPA
    OPINION AND ORDER OF THE BOARD (by Mr. Henss)
    General Tire and Rubber Company is in the final phase of
    construction of a $40 million radial tire manufacturing plant
    in Mt. Vernon, Illinois. Plant heat and process steam require-
    ments for the plant are to be supplied by two 70 million Btu/hr.
    Murray-Trane boilers.
    On July 23, 1973, Petitioner applied to the Environmental
    Protection Agency for a construction permit for the oil fired
    boilers. At that time, Petitioner specified that *6 fuel oil
    with a sulfur content of 0.74 would b~used for fuel. Satisfied
    that Petitioner’s emissions would he in compliance with all Rules
    and Regulations, the Agency granted the construction permit on
    September 12, 1973.
    After making application for the construction permit but
    before the Agency approval, Petitioner discovered that it was
    unable to secure any firm commitment for the low sulfur fuel
    oil. General Tire then filed a request for variance from Rule 204
    of the Illinois Air Pollution Control Regulations in order to
    temporarily allow the burning of #6 fuel oil containing 3 maximum
    sulfur content (2.5 typical).
    In the Petition for Variance, Petitioner stated that the plant,
    designed to produce 2,000 radial tires per day, was scheduled for
    startup in
    mid-November
    1973. Attached to the Petition were copies
    of letters from 9 major oil
    companies which substantiate
    10
    529

    —2—
    Petitioner’s claim that extensive efforts to secure low sulfur
    fuel oil have been fruitless. Adding to Petitionerts fuel
    problem is the present fuel allotment program which is based on
    1972 fuel usage.
    Petitioner was not in operation during 1972
    and thus
    did not establish a base allotment on which to secure
    fuel for 1973.
    General Tire maintains that the requirement for
    variance
    will exist until the Company can
    1) secure adequate commitment
    for supplies of #2 fuel oil, #5 low sulfur fuel oil, or #6 low
    sulfur fuel oil, or 2) select, design, engineer and install a
    flue gas desulfurization unit on the plant’s single stack.
    General
    Tire has already initiated efforts to
    control sulfur oxide and
    estimates that a flue gas
    desulfurization control program will
    cost from $300,000 to $1 million.
    If the variance is allowed, General Tire agrees to
    1) con-
    tinue to seek low sulfur fuel oil, 2) seek a long—term contract
    for low sulfur fuel oil, or, 3) in the event such fuel oil contracts
    are not secured by August 1, 1974, install sulfur oxide removal
    equipment by May 30, 1975.
    The Agency states that Petitioner has made a serious attempt
    at compliance and should be granted the variance subject to certain
    conditions. An Agency representative visited the plant site on
    September 4, 1973 where he discussed the proposed variance with
    several area residents. They made no objection to the granting
    of the variance.
    A public hearing on the variance request was held on November 20,
    1973. Petitioner’s plant engineer, John Cappellin, testified that
    the plant is now scheduled for startup in mid-December 1973. During
    the design phase of the plant, General Tire had originally considered
    natural gas, #2 fuel oil and *6 fuel oil for the plant boilers.
    Natural gas was quickly eliminated from further consideration when
    it was learned that supplies of this fuel were not available for
    commercial establishments in the Mt. Vernon area.
    After filing the variance petition, General Tire was able to
    secure 550,000 gallons of #6 fuel oil from a local supp1ier~ The
    fuel oil, thought to have a sulfur content of 0.96, was tested
    and found to have a sulfur content of 1.07. About 35,000 gallons of
    #2 fuel oil was obtained during this time. Petitioner plans to
    start its boilers on #2 fuel oil (low sulfur) and then switch to
    the #6 fuel oil when sufficient heat has been applied to the more
    viscous #6 oil to allow a smooth flow to the boilers (R. 17).
    10
    530

    —3—
    Once the plant achieves maximum capacity, approximately 5
    million gallons of fuel oil will be required annually (R. 10).
    A commitment for an additional 1 million gallons from the local
    supplier has been obtained (R. 15) and should last through the
    startup phase or until early fall of 1974. Sulfur content of
    the additional fuel was not revealed in the record.
    Petitioner has already obtained preliminary cost figures
    for its proposed flue gas desulfurization system. William Lang,
    Manager of Chemical Engineering and Chairman of the Corporate
    Environmental Control Committee, testified that the Chemical
    Construction Corporation roughly estimated $1.1 million as the
    construction cost of the proposed system (R. 36). The system
    wou~Erequire about 24 months for construction.
    General Tire has
    investigated the feasibility of constructing
    additional facilities at Mt. Vernon to remove the sulfur from high
    sulfur fuel oil prior to burning and is now investigating the
    possibility of gaining proprietary access to low sulfur fuel oil
    by investing money in an oil refinery (R. 44).
    Robert J. Schreiher, Jr., an Agency engineer, testified that
    Petitioner’s sulfur dioxide emissions would be about 3,388 lbs.
    per day if the plant were operating in compliance with the Regu-
    lations. He estimated that the burning of 1.07 sulfur fuel oil
    would add an additional 372 lbs. of sulfur dioxide per day over
    the allowable rate. Schreiber testified that there were no large
    (5,000 lbs./day) sulfur dioxide emission sources in the Mt. Vernon
    area presently. Schreiber also testified that it was his opinion
    that the sulfur dioxide emissions from the plant would not pose
    any serious health hazard for the area (R. 54). If fuel with a
    higher sulfur content is ultimately used, of course the sulfur
    dioxide emissions would be higher.
    We believe Petitioner has proven’its need for a variance.
    The attempt to secure adequate supplies of low sulfur fuel oil
    was exhaustive and fruitless. Time will be needed to obtain a
    low sulfur fuel supply or install flue gas desulfurization equipment.
    By using present fuel oil supplies Petitioner will add about 10
    more sulfur dioxide to the Mt. Vernon atmosphere than the Company
    would emit if it were operating in compliance, but the Agency does
    not believe this quantity of additional emissions will create any
    serious health hazards in the area. Petitioner has indicated that
    it is willing to comply with the conditions requested by the Agency.
    General Tire has invested $40 million in an area which needs
    the stimulus of industry. Ultimately Petitioner will employ 450
    to 1,000 persons. The Company has expended a great deal of effort
    in its attempt to comply with the Regulations. It has committed
    itself to the installation of sulfur dioxide control equipment in
    10—531

    —4—
    the event it is unable to secure contracts for adequate supplies
    of low sulfur fuel oil. From the record we believe that the
    Company will continue with its efforts until compliance is achieved.
    The variance will be granted subject to those conditions suggested
    by the Agency.
    ORDER
    It is the Order of the Pollution Control Board that:
    General Tire and Rubber Company be granted a variance
    from Rule 204 of the Illinois Air Pollution Control
    Regulations for its Mt. Vernon tire plant until
    December 20, 1974. The variance is subject to the
    following conditions:
    a) Petitioner shall continue good faith negotiations
    for securing an adequate supply of low sulfur fuel
    oil and immediately use such oil upon its avail-
    ability regardless of any other date set forth in
    this order.
    b) Petitioner shall submit quarterly progress reports
    to the Environmental Protection Agency.
    Said
    progress reports shall commence on January 15, 1974
    and shall provide details on the characteristics
    and usage of fuel oil, progress in choosing a
    control option, and negotiations for long term
    contracts guaranteeing an adequate supply of low
    sulfur fuel oil.
    c) Petitioner shall reapply to the Board for any
    extension of this variance by September 20, 1974
    if compliance with Rule 204 of the Air Pollution
    Control Regulations has not been achieved by that
    date.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Opinion and Order was adopted
    this
    .3~
    day ~
    ,
    1974 by a vote of ~ to
    O_.
    10
    532

    Back to top