ILLiNOIS POLLUTION CONTROL BOARD
December 20, 1973
)
PUTNAM COUNTY SCHOOLS
)
UNIT SCHOOL DISTRICT 535
)
)
)
v.
)
PCB 73~463
)
)
ENVIRONMENTAL PROTECTION AGENCY
)
)
)
ORDER
OF TI-fE BOARD (by Mr. Dumelle)
ni order to make a decision on the basis of the record
before the Board the following additional information is required:
(a) an explanation of the delay in seeking bids between
July 2, 1973 and October 10, 1973,
(b) the reasons why the cracked aerobic digester tank
cannot be repaired immediately to prevent leakage into
the aeration system,
(c) the status of bids for the new school building
construction and whether or not the needed sewage plant
construction is included,
(d) the source of funds (current taxes or bond issue) to
enlarge the sewage plant and
(e) the feasibility, if any, of connecting the school
discharge to a municipal or sanitary district sewage
treatment plant.
Petitioner shall supply the needed information within 30 days
from the date of this Order and make simultaneous service upon the
Agency.
IT IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Order was adopted on
the ~
G’~’I
day
of December, 1973 by a vote of ____________________________
Christan L. Moffett,,.’~erk
Illinois Pollution c~j 5.’trol Board
10—475