ILLINOIS POLLUTION CONTROL BOARD
March
28,
1974
WAREHAM’S DAIRY, A Division Of
Holland Ice Cream And Custard
Company,
Petitioner,
v.
)
PCB 74-45
ENVIROUMENTAL PROTECTION AGENCY,
Respondent,
Ervin Caldemeyer, Vice President and Treasurer,
on behalf of
Petitioner;
John H.
Rein, Attorney,
on behalf of Environmental Protection
Agency.
OPINION AND ORDER OF THE BOARD
(by Dr. Odell)
The Petitioner, Holland Ice Cream and Custard Company
(now Holland Dairies,
Inc.)
owns substantially all of the out-
standing common stock of Wareham’s Dairy,
Inc., which processes
dairy products near Taylorville,
Illinois.
On January 25,
1974,
the Illinois Pollution Control Board
(thereinafter Board)
received
a petition for variance In which the Petitioner seeks an extension
of time to comply with the Board’s Order in Environmental Protection
Agency v.
Holland Ice Cream and Custard Company, PCB 71—319
(March
29, 1973), and, more specifically, seeks an extension of time to
complete corrections to its spray irrigation treatment System at
its Wareham Dairy plant adjacent to Taylorville,
Illinois.
Prior to February
3,
1972, wastes from Petitioner’s Wareham
Dairy plant were discharged into a holding tank and then to extended
aeration and settling tanks In which oxidation and settling occurred.
Due to
the inadequacies of this system of treating Petitioner’s
wastes,
the Board found on February 3,
1972,
that Petitioner was in
violation of Section 12(a)
of the Illinois Environmental Protection
Act
(Act)
and portions of Sanitary Water Board Rules and Regulations
Number Six
(SWB-6)
for failing to meet color and turbidity standards
and for failing to operate its treatment facilities
at design
efficiency.
Paragraph
3 of the Board’s Order stated that “Holland
shall submit to the Board and to
the Agency a firm program for
achieving compliance with all applicable regulations respecting its
discharge of liquid wastes.
Such a program shall provide for com-
pliance in the shortest practicable time.”
After considerable
delay and repeated interchange with the Environmental Protection
Agency (hereinafter Agency)
during the next year,
a program was
developed to construct an irrigation field of six 1.5—acre plots
designed to be used separately on
a six—day rotating basis. The
I
1
—
709
—2--
average design
flow is
30,000 gallons per day, utilizing pumps
designed to pump 125 gallons per minute with nozzels, each dis-
bursing 62.5 gallons per minute at
80 pounds pressure to the
farthest point in the irrigation field.
After the compliance program was developed by Petitioner
in
consultation with the Agency,
the Board ordered on March
29,
1973,
(PCB 71—319) Petitioner to comply with the following timetable:
“Date by which contracts
are to be awarded
30 days after Agency
permit for installation
of the system is
issued.
Start of
construction
.
.
.
15 days after contracts
are awarded.
Completion of con-
struction
4 months after construction
is started.
Start of full operation
.
.
1 week after construction
is completed.”
Subsequent events which relate to the present petition for
variance are summarized below from
the
Agency’s Recommendation
that was received by the Board on March
5,
1974.
The Agency
issued to Petitioner on May 25,
1973, permit ~l973—EA—l055
for
construction and operation of
a spray irrigation facility to
control water pollution, and approved his Project Completion
Schedule, Certificate #1973—194—PCS,
on August 20,
1973.
The
spray irrigation facility started operation on November 16,
1973,
but the submersible pumps did not operate at required design
pressure and a water problem developed in one spray field because
of
a broken drain tile.
During
late
December,
1973,
and early
January, 1974,
further difficulties were encountered, including
flooding of five of the six spray irrigation fields and freezing
of the spray irrigation facility, which resulted in pollution
of the Flat Branch of the South Fork Sangamon River.
On January
9,
1974, Petitioner diverted its plant wastes back to its extended
aeration basin to abate further pollutional discharges until the
spray irrigation facility could be rehabilitated.
On January 15,
1974, Petitioner notified its Agency by letter of
“the following
steps being taken to rectify the problems with its spray irrigation
system:
(a)
The contractor will repair and/or replace,
if necessary,
the automatic control valve on January 14,
1974, and
have it back in operation by January
18,
1974.
(b)
Only those irrigation fields not covered by water will
be used.
(c)
The existing levee will be raised three feet.
fl
—
/10
—3—
(d)
The field
tile causing infiltration into the field
will be located and its flow diverted around the
field.
(e)
Reseed in the Soring,
if
necessary,
to obtain grass
cover.”
The Petitioner stated that the new spray irrigation facilities cost
approximately $75,000
to January 25,
1974, when this petition for
variance was filed.
The Agency believes that Petitioner’s plan to temporarily
divert its plant wastes back to the previously abandoned extended
aeration treatment system
is the “most logical and practical short-
term approach”
(even though the effluent produced is not entirely
satisfactory)
,
while Petitioner’s spray irrigation system is
promptly rehabilitated to
fully meet applicable standards.
“The Agency believes that Petitioner’s requested variance
would not have a prolonged adverse environmental impact on the
receiving stream.”
However,
they stated that care should be taken
to avoid a possible odor nuisance problem during warm weather by
lime application or other alternatives.
The Agency believes that Petitioner
~~a)“has acted dili-
gently in attempting to comply with the Board’s past Orders and the
applicable Rules and Regulations” and
(b)
“has and will continue
to act diligently in solving its present problems with its spray
irrigation system.”
The Agency recommended that this petition
for variance be granted, with a timetable suggested by Petitioner,
but with certain conditions, including
a maximum time limit of
September 30,
1974,
for completion.
The Board concurs
in this
aoproach, and the following Order is written accordingly.
ORDER
The Illinois Pollution Control Board hereby grants
Petitioner
a variance from Section 12(a)
of the Environmental
Protection Act to rehabilitate its spray irrigation treatment
system according to the following time schedule and subject to
the other conditions specified below:
(1)
Petitioner shall take any and all measures which
would assure completion
of improvements
in its spray irrigation
treatment system by the earliest practicable date, but no
later
than September 30,
1974, with the following progress datelines:
(a)
Date by which plan to bring
Petitioner into Compliance
with Act and applicable Rules
and Regulations submitted to
Agency
65 days,
if possible,
after this petition
for variance was sub-
mitted by Petitioner,
but not later
than
April 15, l974~
—
711
—4—
(b)
Completion of construction
and start of full operation
of rehabilitated system
.
.
.
.
120 days aftE~rapproval
by Agency.
(2)
In the operation of its extended aeration sy~itemduring
the interim period, Petitioner shall undertake all measures nec-
essary to minimize environmental harm, including the apolication of
lime or other feasible alternatives to prevent the occurrence of an
odor nuisance during the summer months.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify tha
the above Opinion and Order was adopted
on the
~.3
“day of
ft~
,
1974, by a vote of
~
to 0
QL~,ri
~4J~
Christan L. M~tt.
Clerk
11—
712