ILLINOIS POLLUTION CONTROL BOARD
    March
    28,
    1974
    WAREHAM’S DAIRY, A Division Of
    Holland Ice Cream And Custard
    Company,
    Petitioner,
    v.
    )
    PCB 74-45
    ENVIROUMENTAL PROTECTION AGENCY,
    Respondent,
    Ervin Caldemeyer, Vice President and Treasurer,
    on behalf of
    Petitioner;
    John H.
    Rein, Attorney,
    on behalf of Environmental Protection
    Agency.
    OPINION AND ORDER OF THE BOARD
    (by Dr. Odell)
    The Petitioner, Holland Ice Cream and Custard Company
    (now Holland Dairies,
    Inc.)
    owns substantially all of the out-
    standing common stock of Wareham’s Dairy,
    Inc., which processes
    dairy products near Taylorville,
    Illinois.
    On January 25,
    1974,
    the Illinois Pollution Control Board
    (thereinafter Board)
    received
    a petition for variance In which the Petitioner seeks an extension
    of time to comply with the Board’s Order in Environmental Protection
    Agency v.
    Holland Ice Cream and Custard Company, PCB 71—319
    (March
    29, 1973), and, more specifically, seeks an extension of time to
    complete corrections to its spray irrigation treatment System at
    its Wareham Dairy plant adjacent to Taylorville,
    Illinois.
    Prior to February
    3,
    1972, wastes from Petitioner’s Wareham
    Dairy plant were discharged into a holding tank and then to extended
    aeration and settling tanks In which oxidation and settling occurred.
    Due to
    the inadequacies of this system of treating Petitioner’s
    wastes,
    the Board found on February 3,
    1972,
    that Petitioner was in
    violation of Section 12(a)
    of the Illinois Environmental Protection
    Act
    (Act)
    and portions of Sanitary Water Board Rules and Regulations
    Number Six
    (SWB-6)
    for failing to meet color and turbidity standards
    and for failing to operate its treatment facilities
    at design
    efficiency.
    Paragraph
    3 of the Board’s Order stated that “Holland
    shall submit to the Board and to
    the Agency a firm program for
    achieving compliance with all applicable regulations respecting its
    discharge of liquid wastes.
    Such a program shall provide for com-
    pliance in the shortest practicable time.”
    After considerable
    delay and repeated interchange with the Environmental Protection
    Agency (hereinafter Agency)
    during the next year,
    a program was
    developed to construct an irrigation field of six 1.5—acre plots
    designed to be used separately on
    a six—day rotating basis. The
    I
    1
    709

    —2--
    average design
    flow is
    30,000 gallons per day, utilizing pumps
    designed to pump 125 gallons per minute with nozzels, each dis-
    bursing 62.5 gallons per minute at
    80 pounds pressure to the
    farthest point in the irrigation field.
    After the compliance program was developed by Petitioner
    in
    consultation with the Agency,
    the Board ordered on March
    29,
    1973,
    (PCB 71—319) Petitioner to comply with the following timetable:
    “Date by which contracts
    are to be awarded
    30 days after Agency
    permit for installation
    of the system is
    issued.
    Start of
    construction
    .
    .
    .
    15 days after contracts
    are awarded.
    Completion of con-
    struction
    4 months after construction
    is started.
    Start of full operation
    .
    .
    1 week after construction
    is completed.”
    Subsequent events which relate to the present petition for
    variance are summarized below from
    the
    Agency’s Recommendation
    that was received by the Board on March
    5,
    1974.
    The Agency
    issued to Petitioner on May 25,
    1973, permit ~l973—EA—l055
    for
    construction and operation of
    a spray irrigation facility to
    control water pollution, and approved his Project Completion
    Schedule, Certificate #1973—194—PCS,
    on August 20,
    1973.
    The
    spray irrigation facility started operation on November 16,
    1973,
    but the submersible pumps did not operate at required design
    pressure and a water problem developed in one spray field because
    of
    a broken drain tile.
    During
    late
    December,
    1973,
    and early
    January, 1974,
    further difficulties were encountered, including
    flooding of five of the six spray irrigation fields and freezing
    of the spray irrigation facility, which resulted in pollution
    of the Flat Branch of the South Fork Sangamon River.
    On January
    9,
    1974, Petitioner diverted its plant wastes back to its extended
    aeration basin to abate further pollutional discharges until the
    spray irrigation facility could be rehabilitated.
    On January 15,
    1974, Petitioner notified its Agency by letter of
    “the following
    steps being taken to rectify the problems with its spray irrigation
    system:
    (a)
    The contractor will repair and/or replace,
    if necessary,
    the automatic control valve on January 14,
    1974, and
    have it back in operation by January
    18,
    1974.
    (b)
    Only those irrigation fields not covered by water will
    be used.
    (c)
    The existing levee will be raised three feet.
    fl
    /10

    —3—
    (d)
    The field
    tile causing infiltration into the field
    will be located and its flow diverted around the
    field.
    (e)
    Reseed in the Soring,
    if
    necessary,
    to obtain grass
    cover.”
    The Petitioner stated that the new spray irrigation facilities cost
    approximately $75,000
    to January 25,
    1974, when this petition for
    variance was filed.
    The Agency believes that Petitioner’s plan to temporarily
    divert its plant wastes back to the previously abandoned extended
    aeration treatment system
    is the “most logical and practical short-
    term approach”
    (even though the effluent produced is not entirely
    satisfactory)
    ,
    while Petitioner’s spray irrigation system is
    promptly rehabilitated to
    fully meet applicable standards.
    “The Agency believes that Petitioner’s requested variance
    would not have a prolonged adverse environmental impact on the
    receiving stream.”
    However,
    they stated that care should be taken
    to avoid a possible odor nuisance problem during warm weather by
    lime application or other alternatives.
    The Agency believes that Petitioner
    ~~a)“has acted dili-
    gently in attempting to comply with the Board’s past Orders and the
    applicable Rules and Regulations” and
    (b)
    “has and will continue
    to act diligently in solving its present problems with its spray
    irrigation system.”
    The Agency recommended that this petition
    for variance be granted, with a timetable suggested by Petitioner,
    but with certain conditions, including
    a maximum time limit of
    September 30,
    1974,
    for completion.
    The Board concurs
    in this
    aoproach, and the following Order is written accordingly.
    ORDER
    The Illinois Pollution Control Board hereby grants
    Petitioner
    a variance from Section 12(a)
    of the Environmental
    Protection Act to rehabilitate its spray irrigation treatment
    system according to the following time schedule and subject to
    the other conditions specified below:
    (1)
    Petitioner shall take any and all measures which
    would assure completion
    of improvements
    in its spray irrigation
    treatment system by the earliest practicable date, but no
    later
    than September 30,
    1974, with the following progress datelines:
    (a)
    Date by which plan to bring
    Petitioner into Compliance
    with Act and applicable Rules
    and Regulations submitted to
    Agency
    65 days,
    if possible,
    after this petition
    for variance was sub-
    mitted by Petitioner,
    but not later
    than
    April 15, l974~
    711

    —4—
    (b)
    Completion of construction
    and start of full operation
    of rehabilitated system
    .
    .
    .
    .
    120 days aftE~rapproval
    by Agency.
    (2)
    In the operation of its extended aeration sy~itemduring
    the interim period, Petitioner shall undertake all measures nec-
    essary to minimize environmental harm, including the apolication of
    lime or other feasible alternatives to prevent the occurrence of an
    odor nuisance during the summer months.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify tha
    the above Opinion and Order was adopted
    on the
    ~.3
    “day of
    ft~
    ,
    1974, by a vote of
    ~
    to 0
    QL~,ri
    ~4J~
    Christan L. M~tt.
    Clerk
    11—
    712

    Back to top