ILLINOIS POLLUTION CONTROL BOARD
    March 28, 1974
    ILLINOIS CENTRAL GULF RAILROAD,
    Petitioner,
    v.
    )
    PCB 73—550
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    James T. Bradley, Attorney for Illinois Central Gulf Railroad
    John T. Bernbom, Attorney for the EPA
    OPINION AND ORDER OF THE BOARD (by Mr. Henss)
    Illinois Central Gulf Railroad requests variance from
    Rules 403, 404(f), 408(a) and 1002 of the Illinois Water Pollution
    Control Regulations for a period of one year. Petitioner owns
    and operates a facility known as the “Mechanical Facility at
    South Joliet” for the maintenance, repair, fueling, sanding and
    laundering of locomotives. The facility is located about 1/2
    mile east of Illinois Route 53 and 1 mile north of Interstate 80
    along the northern bank of Sugar Run Creek.
    During normal operations Petitioner discharges 10 gallons
    of waste water per minute into Sugar Run Creek. This increases
    during and following rains. The waste water, consisting chiefly
    of oil and chemicals, results from oil spills and certain main-
    tenance practices in addition to liquid waste generated in
    cleaning the locomotives. Chemicals in the waste water are
    primarily radiator treatment chemicals and cleaning agents.
    Petitioner states that an analysis of the waste water revealed:
    40 mg/l oil, 60 mg/l BOD and 25 mg/l suspended solids.
    The parties in this matter have presented a Stipulation of
    Facts from which we are to decide the case. The Agency recommends
    granting the variance, and after a review of this document we
    agree that Petitioner has met its burden of proof.
    Illinois Central Gulf Railroad became the surviving corpor-
    ation through a merger of Illinois Central Railroad and Gulf
    Mobile and Ohio Railroad in August 1972. Petitioner states that
    ~97

    —2—
    during and for some period after the merger negotiations the
    “direction of railroad efforts to abate pollution at its
    newly acquired railroad facilities throughout Illinois and
    other States” were “substantially confused and disrupted”.
    Essential abatement facilities were not included in the 1973
    budget “because of additional time required to complete the
    then on-going facility—merger survey”.
    Consequently, Petitioner claims it was impossible to
    “retain a pollution engineering report, together with the
    preparation of plans, specifications and an estimate of project
    cost, and to contract for the project so as to both construct
    the facility and make it operational before December 31, 1973.”
    Subsequent to the merger the following events occurred:
    September—December
    Petitioner attempted to obtain a
    1972
    Refuse Act Permit or a Corps of
    Engineers Permit.
    November 1972
    Agency advised Petitioner of new
    Federal NPDES requirements.
    March 1, 1973
    Preliminary plans and cost estimates
    for proposed Joliet abatement facilities
    were completed.
    August 1973
    Agency was provided with copy of pre-
    liminary plans.
    September 7, 1973
    Petitioner provided Agency with copy
    of Project Completion Schedule for
    proposed waste treatment facility.
    September 12, 1973
    Petitioner filed application for
    construction permit
    for proposed waste
    treatment facility.
    September 18, 1973
    Agency was provided with copy of final
    plans and specifications for proposed
    treatment facilities.
    October 18, 1973
    Agency informed Petitioner that its
    Project Completion Schedule had been
    disapproved.
    October 29, 1973
    Petitioner informed Agency of plans
    to seek a variance since the treatm~
    facilities could not be in operati::~
    by December 31, 1973.

    —3—
    December 4, 1973
    Agency issued permit for construction
    and oDeration of the “Emergency Oil
    and Spill Containment and Treatment
    Facility for Joliet, Illinois”.
    Petitioner’s “Emergency Oil and Spill Containment and Treat-
    ment Facility” plan will provide oil collection pans to collect
    spillage of fuel oil and other types of oil waste and a system
    for collecting and carrying waste water to a two cell lagoon
    system. The lagoon system will provide for containment and
    treatment of the waste water prior to discharge of the liquid
    into Sugar Run Creek. The Agency was of the opinion that the
    complexity of the construction project warrants the 15 months
    compliance schedule submitted by Petitioner.
    Completion of the contract and construction phase of the
    project will take at least 12 months. P~riother three
    months ~s
    required after completion of construction before the system can
    be placed into operation. We were not told the specific need
    for the additional three months, but a review of the plans indicates
    that the time could be used for testing of electrical circuits,
    piping systems, and other start—up procedures. The Agency has
    approved the additional time period.
    Petitioner claims that a denial of the variance would force
    Petitioner to shut the facility down or risk monetary penalties.
    A facility shutdown would severely disrupt maintenance practices
    since all other similar facilities operated by Petitioner are
    operating at capacti’y. Locomotives which are normally fueled
    and maintained at the Joliet facility would be taken elsewhere,
    resulting in a shortage of locomotives in the Joliet area, in--
    creased fuel usage for the extra distance travelled, and the
    serious disruption of a coal train operating between a southern
    Illinois coal mine and Plaines, Illinois. Elimination of freight
    car repair and maintenance could result in damage to the freight
    cars and increase the likelihood of derailments.
    We believe the record in this case is sufficient to satisfy
    the requirements for the variance. Both parties recognize that
    the Board is limited to granting variances for a period of one
    year and that an extension of this variance may be required for
    an additional period of up to three months.
    The parties say that a ‘performance bond is neither required
    nor recommended”, but it is our custom to require the posting of
    bond for the more complex construction projects. This authority
    is de~ivedfrom Section 36(a) of the Act. We shall require a
    bond in this case.
    — 899

    —4—
    ORDER
    It is the Order of the Pollution Control Board that Illinois
    Central Gulf Railroad is granted a variance from Rules 403, 404(c)
    404 (f)
    ,
    408 (a) and 1002 for its Joliet maintenance facility until
    March 28, 1975 for the purpose of construction and operation of
    the “Emergency Oil Spill Containment and Treatment Facilities” as
    presented in the petition for variance. This variance is subject
    to the following conditions:
    1. Petitioner shall submit monthly progress reports
    to the Environmental Protection Agency. Said
    progress reports shall commence on April 28, 1974
    and shall provide details of Petitioner’s progress
    towards completion of the new waste treatment
    facilities.
    2. Petitioner shall not increase the strength or
    quantity of discharges and shall take every
    reasonable measure to limit spillage and to
    contain discharges.
    3. Petitioner shall, by April 28, 1974, post a
    bond in the amount of $40,000 in a form
    acceptable to the Environmental Protection
    Agency, such bond to be forfeited in the
    event Petitioner fails to install the new
    waste treatment facilities by the end of
    the compliance schedule. The bond shall be
    mailed to: Fiscal Services Division,
    Illinois EPA, 2200 Churchill Road, Springfield,
    Illinois 62706.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Opinion and Order wa adopted
    this
    ~
    day of
    ________
    ,
    1974 by a vote of ____to~

    Back to top