ILLINOIS POLLUTION CONTROL BOAPD
    November
    8,
    1973
    UNION CARBIDE CORPORATION,
    Petitioner,
    V.
    )
    PCI3
    73—313
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    3.
    A.
    Lipe, Attorney for Petitioner
    Thomas A. Cengel, Assistant Attorney General for the EPA
    INTERIM OPINION AND ORDER OF
    THE
    BOARD
    (by Mr.
    Uenss)
    Petitioner Union Carbide Corporation requests
    30 day con-
    tinuance
    in
    order
    to
    allow
    the
    parties
    to
    submit
    additional
    argument
    or
    information.
    The
    Motion
    is
    allowed.
    We
    believe
    it
    may
    assist
    the
    parties
    in
    their
    preparation
    of
    additional
    pleadinqs,
    factual stipulations or argument if they receive our present under-
    standing of the background and issues of this case.
    The following
    is issued for that purpose.
    Union Carbide Corporation produces high quality coke from
    petroleum by—products at its plant located near Robinson,
    Illinois.
    Each year the Company uses about 300,000 tons of petroleum raw
    materials, which are purchased from several refineries,
    Union
    Carbide applies heat
    to its raw materials in a process
    called
    calcining,
    to drive off oxygen, water vapor and volatile materials
    in the form of gasses.
    Particulate matter
    is also emitted
    in the
    process.
    Most of the petroleum coke produced at this plant
    is
    used
    within the Union Carbide Corporation for the production
    of carbon
    and graphite electrodes,
    carbon arc lighting devices, dry cell
    batteries,
    brushes for electric motors and generators, foundry
    castings and nose cones for rocket missiles.
    The plant operates
    24 hours per day throughout the year, except for an occasional
    shutdown for repairs, and employs
    37 persons.
    It was constructed
    in 1958 but was not purchased by Union Carbide until April
    1971.
    There are two inclined rotary kilns, each measuring
    10’
    in
    diameter by 180’
    in length.
    A natural gas fired burner at the
    lower end supplies heat of 1450°F.
    The petroleum raw ni~iteria1
    is fed into the elevated end of the kiln,
    and the revolving motion
    of the inclined kiln causes the raw material to
    flow by gravity to
    the lower end as
    the heat drives off volatile hydrocarbons
    and
    water.
    Gasses and entrained particulate matter from the kiln enter
    a
    combustion chamber where excess air is introduced
    to burn any
    combustible material prior to exhausting
    through a
    145’
    sLack.
    10—39

    —2—
    The hot calcined petroleum coke is gravity fed from the burner
    end of the kiln into an enclosed rotating water spray cooler which
    reduces the temperature of the coke to about 350°F.
    Exhaust
    gasses and entrained particulate matter from the inlet section of
    each cooler pass through a cyclone prior to exhausting through
    a
    40’ stack.
    Exhaust gasses and entrained particulate matter from
    the outlet section of each cooler exhaust through a 115’ stack
    which serves both coke coolers.
    The finished product is carried
    by bucket elevator to a storage bin from which it is loaded into
    railroad cars.
    Each- tf the identical kilns can process about
    18 tons per
    hour under normal operating conditions.
    Petitioner can produce
    different grades of coke by varying the quantity of air introduced,
    the heat and retention time,
    Rarely do the two kilns produce the
    same product at the same time.
    Union Carbide Corporation filed its petition for variance on
    July 31, 1973 asking for relief from Rules 103(b) (2),
    103(b) (6) (E)
    104, and 203(b)
    of the Illinois Air Pollution Control Regulations.
    These Rules relate to operating permits, compliance programs and
    particulate emission standards for existing emission sources.
    Specifically, Petitioner sought a fifteen month variance to operate
    kiln #1 and a
    24 -month variance to operate kiln
    #2 pending installation
    of air pollution control devices.
    Subsequently, Union Carbide
    amended the petition and now seeks permanent variance from Rule 203(b)
    on condition that Petitioner “discharge not in excess of
    24
    lbs. per
    hour of particulate matter from each of its new stacks”.
    A public
    hearing on the Amended Petition was held on October
    3,
    1973.
    The Agency has recommended that the variance be denied.
    The
    Agency states that Petitioner
    is in violation of the currently
    applicable particulate regulation, Rule 3-3.111 of the Rules and
    Regulations Governing the Control of Air Pollution.
    The Agency
    further states that since Union Carbide was in violation on the
    date the Air Regulations went into effect in April 1972 Petitioner
    will be required to meet the more stringent “new source” standard
    of Rule 203(a) by December 31,
    1973.
    Petitioner has not requested
    a variance from either the current
    standard, Rule 3—3.111, or the standard it must meet on December 31,
    1973,
    Rule
    203(a).
    The parties are in basic disagreement in their interpretation
    of the Regulation and do not agree as to the Standard which must
    be met.
    The Agency contends “that the process weight rates from
    the two kilns must be aggregated for purposes of determining the
    allowable under Rule 203(a)”.
    Rule
    203(a)
    states “No person shall
    cause or allow the emission of particulate matter into the atmos-
    phere in any one hour period from any new process emission source
    10—40

    —3—
    which, either alone or in combination with the emission of
    particulate matter from all other similar new process emission
    sources at
    a plant or premises, exceed the allowable emission
    rate specified...
    .“
    (emphasis supplied)
    If the two kilns are
    “similar sources” the Standard to be met is 17.2 lbs./hr.
    If,
    as Petitioner contends,
    the two kilns are not similar sources each
    kiln will be allowed emissions of 11.86
    lbs./hr. for a total of
    23.72 lbs./hr.
    from the plant.
    The evidence revealed that two months after Union Carbide
    purchased the plant, the EPA sent the Company an emission in-
    ventory questionnaire with instructions to complete the question-
    naire and hold it until someone from the EPA visited the facility.
    Union Carbide calculated emissions from each of its two kiln
    stacks at
    313 lbs./hr. and stated that emissions were 626 lbs,/hr.
    The record
    is not clear whether emissions from three other stacks
    located at the inlet and outlet of coke coolers, were included in
    the calculation.
    The information was presented to an Agency
    investigator in December 1971,
    and in January 1972 the EPA warned
    Petitioner
    of possible prosecution for excessive particulate
    emissions.
    The EPA letter stated that Union Carbide was limited
    to particulate emissions of 28.29 lbs./hr. from each kiln pursuant
    to Rule 3-3.111 of the Rules and Regulations Governing the Control
    of Air Pollution.
    Petitioner had already engaged the services of Automated
    Process Surveys of New York to make a study and recommendation
    as to the design of
    a control system for the kiln emissions.
    This was done about six months after Petitioner took possession
    of the plant, and stack tests had been performed during January
    1972, prior to Petitioner’s receipt of the warning letter from
    the EPA.
    The stack tests revealed that emissions from #1 stack
    were 260 lbs./hr. and emissions from #2 stack were 100 lbs./hr.
    It was not specifically stated whether the three stacks
    which
    were attached to the spray coolers were tested in January
    1972 but
    we infer from the entire record that they were not.
    In June 1972, Automated presented its report.
    It was recommended
    that two large fans be installed to blow air into the combustion
    chambers on the theory that additional air would supply more
    oxygen for combustion and increased turbulence would help complete
    the combustion of carbon particles to carbon dioxide and water.
    Union Carbide installed the fans at a cost of $15,000 on one of
    the two combustion chambers.
    This installation was completed in
    December 1972.
    Petitioner attempted to perform a stack
    test on
    the newly equipped kiln in January 1973 but was prevented from
    doing so by extremely cold weather.
    The company claims that
    there was
    “visual improvement”
    in the stack discharge, but the
    stack test was not taken until March 1973.
    10
    41

    —4—
    Stack tests taken in March 1973 revealed that the stack
    serving the fan equipped combustion chamber was still emitting
    142 lbs./hr.
    In addition,
    the stack venting the inlet to the
    coke cooler was emitting 15 lbs./hr. and the common stack
    which was venting the outlet from both coke coolers was emitting
    60 lbs./hr.
    These tests convinced Union Carbide that, despite
    the conclusions and recommendations of Automated Process Surveys,
    the addition of fans alone would not provide the degree of control
    necessary to achieve compliance with the Regulations.
    During
    this period Petitioner also received a report from Chemstress
    Consulting Company which had been hired to investigate “every
    possible method for abatement controls of our Robinson stack except
    the incinerating settling chamber”
    (R.
    33).
    The evidence indicates
    that Chemstress evaluated six possible methods, found that only
    two methods would bring compliance with the Regulations but would
    recommend neither of them
    (R.
    34).
    The record failed to describe
    any of the methods evaluated by Chemstress and the report was not
    submitted in evidence.
    Chemstress recommended the incinerating
    settling chamber as the control method which should be adopted
    (R.
    34)
    In June 1972 Petitioner had employed Air Resources Inc.
    to
    evaluate and propose an incinerating settling chamber which would
    bring the stacks into compliance
    (R.
    33)
    Air Resources also evaluated five other systems which were
    rejected for various reasons.
    We will not dwell upon those but
    list them as:
    Granular bed filter
    not proven commercially
    Dry mechanical collector
    would reduce particulates
    to
    53 lbs./hr.,
    an insufficient reduction.
    Fabric filter
    -
    would require over 1400 gallons per
    minute of water to lower the temperature of the
    gas to 350°,the maximum operating temperature of
    the baghouse,
    and would require 8.5 million
    kiliowat hours of electricity
    (KWH)
    .
    Capital
    costs would be $1.7 million and annual operating
    costs $370,000.
    This method would also involve
    other environmental prohlems since 33 tons per
    day of fluffy material would have to be disposed
    of in
    a landfill and the generation of 8.5
    million KWH of power would require the nearby
    power plant to burn 4700 tons per year of high
    sulfur Illinois coal.
    Electrostatic Precipitator
    -
    high efficiency could not
    be guaranteed due to the nature of the particulate
    matter.
    An extensive cooling system would be
    necessary to reach the 700°operating temperature
    of the electrostatic precipitator.
    This system
    10—42

    —5—
    would consume about 4.3 million
    KWH
    per year
    and would produce 33 tons per day of dry partie-
    ulate matter with attendant landfill costs.
    Wet
    scrubber
    would
    require 12.8 million KWH of
    energy,
    capital costs of
    $1.9 million and operating
    costs of $420,000 per year.
    Water consumption of
    approximately 500 gallons per minute for each kiln
    could create a water pollution problem.
    Disposal
    of
    66 tons per day of wet filter cake would require
    14
    acres of
    land over
    a
    5 year period, winter
    operations might be difficult due to freezing
    problems and a possible visibility hazard from
    steam plume.
    This method would require the burning
    of 7000 ton of coal per year at the nearby power
    plant.
    Air Resources recommended the combination settling chamber--
    combustion chamber method as the “most applicable abatement device”
    for the following reasons:
    1)
    The capital cost of approximately $1,500,000 was the
    lowest of the six control systems.
    2)
    The operating costs were by far the lowest of
    all the
    alternatives which were considered.
    3)
    The system was reliable and proven in similar appli-
    cations and is the only system in present commercial
    use in the United States in this application.
    4~ There would be no attendant solid waste disposal,
    water pollution,
    or other environmental disadvantages.
    5)
    It required no power consumption.
    Preliminary designs for the combustion chamber called for the
    construction of chambers approximately
    70’
    long,
    27’ wide and 27’
    high on each kiln system.
    Each chamber would be lined with re-
    fractory brick and exhaust through new 10’
    diameter stacks
    145’
    in height.
    At page V-l of the Air Resources report was found the
    rationale for the Air Resources design:
    “The basis on which this
    preliminary design was completed is contained in Table
    IV.
    Also,
    the Union Carbide personnel stressed that the down time required
    for installation be minimal.
    This restriction eliminated the most
    economical installation in which
    a common stack would serve both
    kilns”.
    (emphasis supplied)
    10
    43

    —6—
    Originally, the schedule included 15 months installation
    time for the first chamber with the second chamber to be com-
    pleted
    9 months after the first.
    After consultation between
    Petitioner .and Air Resources,
    it was decided that both chambers
    could be constructed simultaneously thereby reducing the total
    schedule to about
    16 months
    (R.
    42)
    .
    A maximum of seven
    (7)
    days down time for system tie-in was allowed for each chamber.
    Gary Nagl, Project Manager for Air Resources,
    testified
    that the proposed chambers would allow for the complete com-
    bustion of all combustible material to carbon dioxide and water
    (R.
    74).
    The control system could reduce Petitioner’s particulate
    emissions to 11.86
    lbs./hr.
    from each kiln stack
    (R.
    76)
    .
    The
    particulate matter emitted would consist solely of ash type
    material,
    60
    of which would be ash residue from the raw petroleum
    material and the remainder silica, alumina, ferric oxide and
    calcium oxide from the eroded kiln refractory lining.
    Although
    Nagl initially said that to the best of his knowledge the particulate
    emissions were not toxic in nature,
    he finally stated that he was not
    qualified to testify about the toxicity of the materials
    (R.
    95).
    At the time the Regulations were adopted on April
    14, 1972 the
    Union Carbide plant was obviously not in compliance with Rule 203(b)
    and was not under
    a variance.
    Therefore,
    Rule 203(c)
    is applicable.
    That Rule provides that Petitioner must be in compliance with the
    more stringent provisions of Rule 203(a)
    (new emission sources)
    by
    December 31,
    1973.
    The current particulate Regulation is Rule 3-3.111
    of the Rules and Regulations Governing the Control of Air Pollution.
    Neither the original nor the amended variance petition addressed that
    fact.
    Petitioner has not requested
    a variance from Rule 3-3.111 or
    Rule 203(a)
    but specifically asks for a permanent variance from
    Rule 203(b),
    a Rule which is inapplicable to Petitioner’s operation.
    It seems therefore,
    that
    the
    Petition should be dismissed without
    prejudice.
    We assume that Union Carbide might file
    a new Petition for
    Variance or an amendment in this action and will therefore indicate
    some guidelines which might be useful in future proceedings.
    Permanent variances have not been granted and we do not foresee the
    time when they will be.
    Legislative intent, we believe,
    is found
    in Section
    5(b)
    of the Environmental Protection Act:
    “It is the purpose of this Act...to restore, protect,
    and enhance the quality of the environment and to
    assure that adverse effects upon the environment are
    fully considered by and borne by those who cause them.”
    10—44

    —7—
    We do not find any legislative intent that excessive
    emissions of contaminants should continue indefinitely.
    The
    legislative purpose to “restore” environmental quality leaves
    no room for permanent variances.
    Variances
    are granted where
    compliance with the Statute or applicable regulations would
    impose an arbitrary or unreasonable hardship and even then the
    polluter must have a reasonable plan to bring the facility into
    compliance.
    The granting of
    a variance is not taken lightly
    by this Board.
    In Mt. Carmel Public Utilities Company vs.
    EPA,
    PCB 71—15 we
    stated:
    “Except for cases of
    ‘no technology available’
    this
    Board must require that those who seek a
    ‘shield
    against enforcement cases’
    (which is what a variance
    is) must have
    a definite program to control
    the
    emissions
    with
    existing control technologyt’.
    (See
    also:
    Harold
    L. Swords vs. EPA,
    PCB 70—6,
    Central
    Illinois Public Services vs.
    EPA,
    PCE 71—261,
    71—262,
    71-263 and 71—264, Hardwick Bros.
    Co.
    vs.
    EPA,
    PCB 71—17,
    Flintkote Co. vs.
    EPA, PCB 71-68, Chambers, Bering,
    Quinlan Co.
    vs. EPA, PCB 71—102, Metropolitan Sanitary
    District
    (Village of Streamwood) vs.
    EPA, PCB 71—183,
    York Center Community Cooperative vs.
    EPA, PCB 72-7,
    and Laesch Dairy Company vs.
    EPA, PCB 72—93.)
    Without reservation we reaffirm the criteria for grant of
    a
    variance.
    Where control technology is available and its use will
    not impose an unreasonable hardship upon the Petitioner,
    a variance
    can only be granted upon a showing of eventual compliance with the
    Standard.
    In this case the parties disagree as to
    the
    standard to be met.
    The Amended Petition states:
    “that prior to this time Petitioner’s
    engineers had been under the impression that the Agency would treat
    each of the two new stacks as a separate source for orocess weight
    rate calculation purposes”
    (Amended Petition for Variance, p.
    2).
    However, Mr. Nagl testified as
    follows:
    Mr. Cengel:
    When you started this orogram were you asked
    to come up with
    a program which met a specific
    level in terms of emissions?
    Mr. Nagl:
    We were asked to come up
    with
    a program
    which will put the plant in compliance with
    the Regulations.
    Mr. Cengel:
    You were not asked for a specific figure?
    Mr. Nagl:
    During the course of it we decided it was going
    to be a single source requiring 11.86 lbs./hr.
    10—45

    —8—
    Mr. Cengel:
    Who was we you are speaking of?
    Mr. Nagl:
    Union Carbide and Air Resources.(R.
    97)
    Petitioner fails
    to identify the Agency employee who allegedly
    interpreted the two kilns as two separate emission sources
    The
    record simply does not support Petitioner’s allegations that the
    EPA had committed itself to that interpretation.
    If each kiln
    is considered
    a separate emission source, then
    Union Carbide
    will
    have to meet
    a limitation of
    11.86
    lbs./hr,
    for each of the two kilns or a plant total of
    23.72 lbs./hr,
    Rule
    203(a).
    The settling chamber-combustion chamber which is
    proposed by Union Carbide would apparently meet this limitation.
    On the other hand,
    if Petitioner’s two kilns are adjudged “similar”
    under Rule
    203(a)
    ,
    Petitioner will be required to meet a total
    emission rate of 17.2 lbs./hr.
    Union Carbide claims that the
    proposed control system can not meet such requirements.
    In our opinion adopting the Air Pollution Control Regulations
    we said:
    “similar sources are to be aggregated for purposes of
    determining the applicable process weight.
    The
    significance of this provision is that more effective
    controls are required on larger units, both because
    of their greater potential for harm and because of
    well recognized deficiencies of scale in control
    equioment.
    This graduated control requirement was a
    feature of the original Bay Area Table.
    It is
    important,
    therefore,
    to treat multiple units of the same kind on
    the same premises as if they were one, both to prevent
    circumvention by building several small units instead
    of one large one and because of
    the
    practicality
    of
    applying a single large control device to a number of
    small like sources.
    Because these latter policies do
    not apply to sources of different kind,
    it
    is not
    necessary to aggregate
    a basic oxygen furnace with an
    asphalt saturator,
    or even with a sintering plant,
    for purposes of this Rule.”
    We chose not to include a definition of “similar emission
    sources”
    in Rule
    201 of the Regulations because the physical
    complexity of many facilities would require the careful sifting
    of all pertinent information before two or more sources could be
    adjudged similar.
    A rigid definition simply could not encompass
    all of the various factors
    that might arise
    from the multiplicity
    of Illinois emission sources.
    Thus, we determined that a case by
    case determination would be required.
    Since neither the current Regulations nor the prior Rules were
    in force at the time of construction, the Union Carbide plant was
    10—46

    —9—
    obviously not built with circumvention in mind,
    The
    question
    of circumvention might arise
    in future proceedings since the
    Air Resources report at page V—I clearly states that Union
    Carbide placed such restrictions on Air Resources
    that the
    consulting firm had to eliminate “the most economical install-
    ation in which
    a common stack would serve both kilns”.
    These
    restrictions, we are told, were necessary to limit down time
    and were therefore
    a matter of economics and not an attempt to
    circumvent the Regulations.
    But the current plan for concurrent
    construction of control systems might now remove this objection
    to the single stack concept.
    We have previously said that one
    reason for the rule is
    the “practicality of applying a single
    large control device to
    a number of small like sources”.
    However,
    we do not have sufficient information in this case to determine
    if one common control system is practical.
    We need information
    regarding:
    1.
    The chemical and physical characteristics of
    materials entering the process, leaving the
    process as product and leaving the process
    as
    emissions in the operation of the
    two
    kiln
    systems.
    2.
    Frequency of and reasons
    for producing dissimilar
    products in the simultaneous operation of the kilns.
    3.
    Proximity of the two kiln systems and economic
    reasonableness and technical feasibility of the
    single large combustion——settling chamber
    in
    comparison to other plans which have been
    advanced.
    While these guidelines are not to limit the issues,
    the Board
    does
    feel that these are some of the matters which should be more
    fully developed.
    In deciding whether the two kilns are similar
    sources we will consider not only the product and the useage of
    the kilns, but whether they were constructed or modified to circum-
    vent the Regulations and whether it is practical to treat them as similar
    for control purposes.
    The issue of “practicality”
    involves not
    only questions of technical and economic feasibility, but an
    assessment of total impact on the environment.
    We note that some
    forms of control create other environmental problems,
    i.e. water
    pollution,
    the burning of coal at power plants.
    If it
    appears
    that the total environment may be damaged by considering the
    stacks to be “similar sources” then it would seem to be impractical
    to consider them as similar.
    10—47

    —10—
    ORDER
    Thirty day continuance
    is allowed for the purpose of
    allowing the parties to submit additional pleadings,
    factual
    stipulation or written argument.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, he4eby certify the above Opinion and Order was adopted
    this
    ~day
    of ~
    ,
    1973 by
    a vote of
    ~
    to
    0
    10—48

    Back to top