ILLINOIS POLLUTION CONTROL BOARD
March
7,
1974
GENERAL
ELECTRIC
COMPANY
(MIDWEST
FUEL
RECOVERY
PLANT)
PETITIONER
v.
)
PCB
73—512
ENVIRONMENTAL
PROTECTION
AGENCY
RESPONDENT
OPINION
AND
ORDER
OF
THE
BOARD
(by
Mr. Marder)
This action involves a request for variance filed December 7,
1973,
by General Electric Company to allow operation of its Midwest
Fuel Recovery Plant.
Relief is sought from Rule 207
(e)
(2) of the
Illinois
Air Pollution Control Regulations as
it
applies to industrial
nitrogen oxide emissions.
The Agency in its recommendation dated Feb-
ruary 27, 1974, recommends a grant subject to certain conditions.
The Mic~westFuel Recovery Plant
(MFRP)
is located near Morris in
Grundy County.
It is wholly owned by General Electric.
The MFRP is
a chemical reprocessing plant designed to take partially spent fuel
and to
recover
the
unused
uranium,
plutonium
and
neptunium
for
recycle
as
fresh fuel in order to preserve these natural resources and to pro-
vide waste forms suitable for long term storage.
This is accomplished
by dissolving the fuel material in strong nitric acid and subjecting
this feed stream to chemical separation steps to purify the uranium and
other elements.
The plant is designed to process about
300 tons per year
of
spent fuel which is equivalent to the spent fuel from about
ten
large
nuclear power plants.
High activity wastes resulting from this process are calcined to an
inert oxide form and the other wastes are immobilized for storage on
site
in
reinforced, lined concrete structures.
Because only a small
amount
of
the
products
from
the
plant
are
shipped
in
the
nitrate
form,
it
is necessary that the bulk of the nitric acid used in the process be
decomposed and reconstituted to minimize the utilization of nitric acid
and to prevent potential large scale releases to the environment.
The
control equipment incorporated at the MFRP to achieve such a maximum
re-
cycle
system
includes
calciners,
scrubbers
and
absorbers
installed
at
an aggregate cost of $2,500,000.
Petitioner
was
previously
granted
a
variance
for
this
plant.
In
PCB
72-477,
the Board held that
a variance was warranted subject to certain
conditions.
At the time of the previous grant it was anticipated that
the
MFRP
would
have started up, and that actual on—site environmental
data would have been generated.
However, due to pre-operational and
11
—
469
—2
start up procedures, the MFRP has not yet begun operations.
Petitioner
contends that said plant will not commence operations before June
1974.
The above
facts
testify
that any variance granted today would be in ess-
ence a “first” variance.
Therefore the information (i.e~,hardship, en-
vironmental impact, and compliance plan) would be essentially the same
as for the grant of P~B72-477.
Petitioner contends that during the
past
year
there
have
been
no
significant
advances
in
technology
for
the
control
of
nitrogen
oxide
emissions
applicable
to
the
operation of the
MFRP.
It would serve no purpose to reiterate the background generated in
PCB 72-477.
For such detail the reader is referred to the opinion
offered in PCB 72-477, which may be found in the Board’s records, Vol.
7, Page
219.
Pert~inentparts of said opinion are hereby incorporated
by
reference.
The Agency has recommended that
a stack test be performed to verify
the
quantity
of
nitrogen
oxide
generated,
and
that
no
further
variance
be granted until a firm compliance plan be
submitted.
The Board will
require an acceptable stack test, but will not close the door on future
variances.
Future variances will depend on what efforts Petitioner
takes to comply
(e.g., Research and Development program) and must con-
sider the economic and technological criteria involved.
This Opinion constitutes the findings of fact and conclusions of
law of the Board.
ORDER
IT IS THE ORDER of the Pollution Control Board that:
Petitioner
is granted a variance for its MFRP facility from Rule
207
(e)
(2)
of the Illinois Air Pollution ~Reouiations for one year
from the date of this Order, so
as to allow
a maximum daily emission
of nitrogen oxide of 350 lbs/day subject to the following conditions:
A)
Within sixty
(60)
days after the facility has begun normal
operations, Petitioner shall have a stack test performed,
which shall be conducted in
a manner satisfactory to the
Agency.
The Agency shall be notified at least five
(5)
days in advance of the test, and shall have the right to
have representatives witness the test.
B)
Petitioner shall continue to submit hourly nitrogen oxide
average
n~ntrM-imn
data,
and shall on a monthly basis
submit monthly average data.
C)
Petitioner shall notify the Agency at least ~thirty (30)
days prior to making any process modifications
which
would affect nitrogen oxide emissions.
D)
Petitioner shall continue to diligently pursue methods
to reduce its nitrogen oxide emissions either by control
—3—
equipment and/or internal process changes.
IT
IS
SO
ORDERED.
I,
Christan
L.
Moffett,
Clerk
of
the
Illinois
Pollution
Control
Board,
certify that the above Opinio
and Order was adopted by ~e
Board on the
74.~
day of
(~
,
1974,
by a vote of
~
to
0