ILLINOIS POLLUTION CONTROL BOARD
March- 7,
1974
ILLINOIS POWER COMPANY
(WOOD RIVER)
)
v.
)
PCB 73—483
ENVIRONMENTAL PROTECTION AGENCY
)
OPINION
AND
ORDER OF THE BOARD
(by Dr. Odell)
On November 14,
1973,
Illinois Power Company
(IP) filed
with the Illinois Pollution Control Board
(Board)
a petition
for variance from Rule 408
(suspended and total dissolved solids)
of Chapter
3: Water Pollution Regulations, from January
1 through
June 30, 1974.
Petitioner alleged suppliers’ delays in shipment
of material and equipment as the impediment
to their compliance
by December 31, 1973.
The Board’s interim Order of January 1O~
1974, gave IP 21 days to supply necessary information to enable
the Board to make
a proper decision. The Board also requested
a
waiver of
30 days to the 90—day requirement specified in Section
38 of the Illinois Environmental Protection Act.
Petitioner
submitted additional information on February 19, 1974,
A 30—
day waiver was received on January 16,
1974.
On February 15,
1974,
the Environmental Protection Agency
(EPA)
filed its
Recommendation.
Petitioner currently owns and operates a coal—fired electric
power generating station, known as the Wood River
Station, near
the town of East Alton, Madison County, Illinois.
In April, 1972,
Petitioner contacted consulting engineers to determine what steps
would be necessary to comply with the newly adopted Water Pollution
Regulations which stated that compliance with Rule 408 had to be
achieved by December 31, 1973.
By July,
1972,
it was decided
that repipirig and sump pumps would have to be installed in order
to direct effluents to an ash lagoon for final treatment, thereby
satisfying Rule 408
(suspended and total dissolved solids).
Petitioner decided at that time to incorporate these ideas into
its EPA permit application.
However, Petitioner did not apply
for its permit until May,
1973; permits were issued by the EPA
in August,
1973.
IP ordered pumps in June,
1973, and awarded
the piping contract in mid-August,
1973.
A manufacturer’s strike
delayed the pipe shipment; 95
of the order was not received until
February 14,
1974.
Design changes in the sump pumps delayed
delivery to Petitioner.
Two
sets of duplex pumps were received
on February 8,
1974;
and the third set of duplex pumps was expect-
ed to be shipped on February 18, 1974.
—2—
The EPA recommended that the six-month variance be granted.
The EPA stated in its Recommendation of February
15’,
1974:
“5. The Agency notes that though delay in filing a permit
application until May of 1973 appears unusually long, Petitioner
apparently believed at the time
of
this submittal that timely
compliance was possible.”
“6.
The Agency believes that Petitioner reasonably
anticipated that timely compliance could be met if contracts
were awarded by September 1, 1973.”
“7.
The Agency believes that the facts as presented by
Petitioner, indicate that the delays encountered were substant-
ially beyond its control and that the Petitioner took reason-
able measures to avoid delay.
Thus the Agency believes that to
require timely compliance would impose an arbitrary or unreason-
able hardship.”
The determination of whether a hardship has been self-
imposed turns on the facts and circumstances of each case.
The
test of unreasonable hardship is not satisfied when a petitioner
negligently but in good faith fails to comply with the Act,
rules, or regulations.
A hardship is self—imposed
if
a reason-
able, prudent man in the same or similar circumstances would
not have acted the same way.
Measured against this test,
we
believe Petitioner’s variance should be granted.
While looking
with a jaundiced eye on Petitioner’s delay in applying for its
permit, Petitioner’s diligence in undertaking studies in April,
1972, convinces us that more probably than not IP’s actions were
reasonable and that the hardship is not self-imposed.
This constitutes the findings of fact and conclusions of
law of the Board.
ORDER
IT IS THE ORDER of the Pollution Control Board that:
1.
Petitioner be given a variance from Rule 408
(suspended
and total dissolved solids)
of Chapter Three: Water Pollution
Regulations,
from January 1 through June
30,
1974.
2.
Petitioner submit monthly reports to the EPA setting
out its progress toward compliance with Rule 408.
These
reports should be sent to:
Illinois Environmental Protection Agency
Division of Water Pollution Control
2200
Churchill Road
Springfield, Illinois 62706
11
—464
—3—
I, Christan
L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify that the a ove Opinion and Order was
adopted on the
‘7”¼day of
m
,
1974, by a vote of
~
to~
__
441s1tt
Christan L. ~~9rett,
Clerk