1. nificant adverse effect on the public for the following reasons:
      2. nificantly to photochemical smog.
      3. 2) There will be no objectionable odor nuisance.
      4. This Opinion constitutes the findings of fact and conclusion of lawof the Board.
      5. IT IS SO ORDERED.

ILLINOIS POLLUTION CONTROL BOARD
February 21,
1974
FS SERVICES, INC.
KINGSTON MINES TERMINAL
PETITIONER
v.
)
PCB 73—518
ENVIRONMENTAL
PROTECTION
AGENCY
•)
RESPONDENT
EVEN
A.
STR7~WN, ATTORNEY,
in
behalf
of
FS
SERVICES,
INC.
MICHAEL GINSBERG, ATTORNEY,
in
behalf
of
the
ENVIRONMENTAL PROTECTION
AGENCY
OPINION
AND
ORDER OF THE BOARD
(By Mr. Marder)
This
case comes to the Board on the petition of FS Services,
Inc.,
for a variance from Chapter
2, Rule 205
(a)
of the Board’s Regulations,
filed December 10,
1973,
for its Kingston Mines Terminal.
No hearing
was held.
The Environmental Protection Agency recommends the variance
be granted.
FS Services,
Inc.,
is a regional cooperative providing 140 member
companies throughout Illinois,
Iowa,
and
Wisconsin with wholesale manu-
facturing, purchasing,
supplies, and services.
FS is owned by the 140
companies it sells to, which are local farm cooperatives.
FS Services,
Inc., owns and operates three petroleum terminals in
Illinois.
They are located in Albany, Norris City, and Kingston Mines.
These
facilities supply gasoline and middle distillates to its member
companies, who in turn resell the products
at retail to local farmers.
The facility has seven stationary storage tanks, all with a capacity
in excess of 40,000 gallons.
Only one of these tanks complies with
Rule 205
(a), which tank has a floating roof.
As of December 31,
1973,
Rule 205
(a) made it
a violation to store
more than 40,000 gallons of volatile organic materials in
a stationary
storage tank,
unless:
11 —341

—2—
1)
The
tank
has
a
pressure
capable of
withstanding
the
vapor
pressure
of
such
materials,
so
as
to
prevent
vapor
or
gas
loss
to
the
atmosphere
at
all times;
2)
Is equipped
with
a
floating roof which rests
on
the vola-
tile organic material and is equipped with
proper
seals
to
prevent escape of vapor or gas
to the atmosphere;
3)
The tank must have
a vapor recovery system consisting
of:
A vapor gathering system capahie of collecting 85
or
more of the uncontrolled volatile organic material
that would be
othe~ise
emstted
to
the
atmosphere, and
a vapor disposal system capable of processing such
vola-
tile organic material so
as to prevent their emission
to the atmosphere.
4)
The tank is an existing
cone
roof
tank
used
exclusively for
the storage of Illinois crude
oil,
subject
to certain con-
ditions.
At
the
facility
in question, six
of
cheir
storage
tanks
do
not con-
form
with
this
rule.
Petitioner
alleges
that
the
hydror;libaw
emiss ions
for
the
six tanks
will
be
acprox.imately
66
lbs
p
3:.
The
bgency in its
recoin—
mendat.ion
calculates
that
the
•c.unissi•on
wil I
be
77~7l
lbs/hr
(Agency
Rec,
P.
3).
The
Agency
further
states
that
due
to
assumptions
that
can
be
used
in
the
calculation,
the
difference
is
not
unreasonable.
During
the
corporate
year
1972li3,
the
asoline
throughput
at the fac-
ility
was
76,200,000
galions~
The Petitioner alleges tli
it.
)t~
O:cOIfle
aware
that compliance
with Rule
205
(a)
would be required on December
31,
1973,
until March
27,
1973,
at which time Petitioner retained Procon,
Inc.,
as consult-
ants for the proposed
emission
control
On
June
1,
1973, the
Petitioner’s
board
of
directors
authorized
$177,000 for a vapor recovery system.
Preliminary
design and engineer-
ing are complete.
Petitioner’s proposed schedule for completion of the recovery system
is
as
follows:
Application
for
construction permit
Dec.
30,
1973
Order
of vapor recovery unit
Jan.
15, 1974
Advertise for bids
Feb.
1,
1974
Award contract and begin construction
March
1,
1974
Complete schedule for modification of
June
15, 1974
six tanks
installation and assembly of vapor re-
August 2,
1974
covery
unit
Final
completion and shakedown
September
15,
1974
11
—342

—3—
Petitioner alleges
a 150 day lead time from the time of ordering
the vapor recovery unit and delivery.
During the delivery time, Pet-
itioner will be doing work preliminary to the installation of the vapor
recovery
unit
including:
1)
Modification of the six tanks
2)
Construction of the vapor gathering manifold
3)
The necessary connections between the manifold and
the
tanks.
The
tank
modification
work will take two weeks per tank, with one
tank
out
of service at
a time.
When.the vapor recovery system is de-
livered,
all
work
preliminary
to its installation will be complete.
The
Agency
feels
the
above
compliance
plan
is
reasonable
and
will
bring
the facility into compliance with the rule.
Petitioner alleges, and the Agency does not rebut, that the emissions
from the tanks during the running of the variance would not have any sig-
nificant adverse effect on the public for the following reasons:
1)
The hydrocarbon emissions have
a low photochemical
reactivity,
and
accordingly do not contribute sig-
nificantly
to photochemical smog.
2)
There will be no objectionable odor nuisance.
3)
There
is
not
a large concentration
of
storage
tanks
in
the
area
that
are
hydrocarbon
emitters,
leading
to the conclusion that ambient air quality will have
low hydrocarbons.
Should
Petitioner
be
denied
this
variance,
it
could
not
cover
its
commitment to supply fuel
to
its customers from its other facilities.
This
would cause a loss not only to Petitioner, but
also to those sup-
plied
by him, who would not be able to get a sure supp.y
of gasoline.
The Board takes notice that a stable supply of fuel is necessary to
keep
our
agricultural
output
sufficient to meet our needs.
Although the Board feels that the delay and resultant hardship are
clearly self-imposed, Petitioner’s
activities
since March
27,
1973,
litigate the circumstances considerably.
It is clearly the responsi-
bility of Petitioner
to keep abreast of regulations in its field,
and
a lack of knowledge thereof is not qrounds for protection.
However,
in the instant case, the Board finds
that the hardship inflicted on
Petitioner
and
the
ultimate
consumer
would
be such that
a variance
is warranted.
The Board further finds that the
environmental impact of Petitioner~s
continued operation for the period of its compliance plan is not signif-
icant enough to move the Board to deny the Petition.
Petitioner has shown good faith in taking on this compliance program
which we find
is a reasonable one.
The Agency recommended a grant of a variance only until September 15,
11—343

—4—
1974.
Petitioner requested a variance for one year,
or the time to com-
plete the work on the facility.
The Board finds nothing on the record
to indicate that the construction should go past the proposed completion
date, but the Board takes notice that some delay is possible, and so
grants Petitioner
a variance until October 15, 1974, or when the project
is completed, whichever
is the shorter period of time.
This Opinion constitutes the findings of fact and conclusion of law
of the Board.
ORDER
IT IS THE ORDER of the Pollution Control Board that Petitioner,
FS
Services,
Inc.,
be
granted a variance until October
15,,
1974,
or
the
completion of their compliance plan, whichever comes first, from Rule
205
(a) of Chapter
2,
Part II, of the Board’s regulation, for six stor-
age tanks at its Kingston Mines facility, subject to the following con-
ditions:
1)
Petitioner shall submit bi-monthly reports to the
Environmental Protection Agency, beginning one
month from the entry of this Order, indicating pro-
gress made toward completion of its proposed com-
pliance plan.
2)
Respondent shall, within
35 days from the date of
this Order, post
a performance bond in a form sat-
isfactory to the Agency in the amount of $50,000,
guaranteeing installation of equipment to comply
with Rule 205
(a).
IT IS SO ORDERED.
I, Christan L. Moffett,
Clerk of the Illinois Pollution Control
Board, certify that the above Opin’on and Order was adopted by the
Board on the
~1~)*
day of .~7
,
1974, by a vote of
___
tOt)
11
344

Back to top