ILLINOIS
    POLLUTION
    CONTROL
    BOARD
    February
    21,
    1974
    ~JOBNDEERE & COMPANY, EAST
    )
    MOLINE
    WORKS,
    )
    Petitioner,
    )
    v.
    )
    PCB
    73—497
    )
    ENVIRONMENTAL
    PROTECTION
    AGENCY,
    )
    )
    Respondent.
    OPIWIOli MiD ORDER
    OP
    THE
    BOARD
    Iby
    Mr.
    Benss)
    Petitioner Deere
    & Company filed Petition for Variance on
    November 26, 1973 seeking variance from Rule 3—3.112 of the Rules
    and Regulations Governing the Control of Air Pollution.
    Specifically,
    Petitioner seeks approval of its plan to burn coal in boiler
    17
    or
    18 at its East Moline Works in the event oil and gas are unavail-
    able in sufficient quantities to meet plant demand in excess of the
    capacity of boiler 19, a controlled boiler.
    Deeie’s East Moline Works employs about 5,000 people for the
    assembly of combines.
    Seven boilers are utilized at the facility
    for process reanirements and heat.
    Two
    of
    the
    boilers
    are
    gas
    or
    oil-fired, three are gas or coal’ fired and two operate on coal
    alone.
    This variance concerns the operatiod of boilers
    17,
    18
    and
    19, all of which are gas or coal fired boilers.
    Boilers 17 and 18
    are uncontrolled travelling grate boilers with a steam capacity of
    80,000 lb./hr.
    each.
    Boiler
    19
    is a multiclone equipped spreader
    ctoker type boiler with a steam capacity of 130,000 lb./hr.
    Fuels used at the facility vary on a daily basis according to
    the availability of natural gas and the weather.
    As an example,
    Pctitioner states that fuel used during December 1972, a maximum
    demand month, was:
    Fuel
    &wunt used
    Percentage
    Coal
    60,301 x 106 Btu
    36.5
    Gas
    96,706 x 106 Btu
    58.6
    Oil
    4,255 x 106 Btu
    2.6
    Propane
    3,823 x 106 Btu
    2.3
    Total
    165,085 x 106 Btu
    100.0
    11-327

    —2—
    Propane
    is not actually burned in the boilers but is used inter—
    changeably with natural gas in the forge shop.
    Petitioner states
    that any curtailment in propane availability will result in
    a require-
    ment to divert additional natural gas from the boilers to the forge
    shop thus causing
    a fuel shortage for the boilers.
    Petitioner
    is unable to determine the extent to which coal will
    have to be burned since the burning is dependent upon the weather
    and possible gas curtailment, neither of which Petitioner can control
    or predict.
    However, based on 1972 records, Petitioner states that
    the coal equivalent for the maximum monthly oil usage was 205 tons.
    The 1972 records also reveal that 234 tons of •coal per month will be
    required for each
    5
    curtailment in natural gas supplies or diversion
    of natural gas to forge shop use.
    Based on Public Health Service
    Publication AP-42, Petitioner estimates the expected particulate
    matter and sulfur dioxide emissions from boilers
    #7 and #8
    as follows:
    Calculations
    for
    10,350
    I3TU Coal
    Lbs./Ton
    Lbs./l06 BTU
    Particulates
    (13 x 7.5
    Ash)
    97.5
    4.7
    SO2
    (38 x 2.35
    sulfur)
    89.3
    4.3
    Petitioner estimates that maximum emission rates
    of 516 lbs./hr.
    particulates and 474 lbs./hr.
    sulfur dioxide would occur when either
    boiler
    #7 or
    #8
    is operating full capacity on coal.
    If the boiler
    is operated at less than
    full capacity,
    the emissions will of cour~e
    be lower.
    Petitioner contends that any injury to the public from the
    grant of this variance would vary according to the capacity at which
    the boiler would be operating,
    and that this operating level depends
    on weather conditions
    and gas availability, factors which cannot be
    estimated.
    The possibility of injury to the public from the increased
    emissions must be weighed against the consequences
    of a variance
    denial.
    Petitioner states that a variance denial would result in
    employee layoffs
    (no figures cited)
    and an inability to satisfy the
    pressing demand for products needed in the food production industry.
    Coal burned at Petitioner~sboilers has an average ash content
    of 7.5
    and an average sulfur content of
    2.35.
    The following Table
    is the Agency’s estimate of Petitioner’s particulate matter and
    sulfur dioxide emissions:
    11 —328

    —3—
    Rule 3—3.112 Rule 203(g)
    Allowable
    Allowable
    Allowable
    Parti~ulates
    SO2
    SO2
    Parti~u1atesParticulates
    Boiler
    lb/l0
    BTU
    lb/b6 BTU lb/b6 BTU lb/lO
    BTU
    lb/b6 BTU
    I
    Operates on gas or oil
    2
    Operates on gas or oil
    5*
    4.68
    4.38
    6.0
    .6
    0.32
    6*
    4.68
    4.38
    6.0
    .6
    0.32
    4.68
    4.38
    6.0
    .6
    0.176
    8
    4.68
    4.38
    6.0
    .6
    0.176
    9
    .51
    4.38
    6.0
    .6
    0.141
    *
    Emergency stand—by only
    Particulate emissions from the boilerhouse are currently regulated
    under Rule 3-3.112.
    After May 30, 1975 Petitioner must comply with
    the particulate emission limitations of Rule 203(g)
    of the Air Pollution
    Control Regula~ions. As noted above, Petitioner~ssulfur dioxide
    emissions are presently within the regulatory constraints
    of
    Rule 204,
    Deere has proposed and partially implemented a comprehensive
    compliance plan which encompasses not only boilers #7,~#8, and #9 but
    the entire scope of energy requirements for its East Moline Works.
    The
    compliance plan shows the installation of electrostatic precipitators
    on boilers
    #7,
    #8 and #9 by November 1,
    1975,
    Since the date of in-
    stallation will not place Deere in compliance by the May 30,
    1975
    effective date of Rule 203 (g)
    ,
    Deere plans to curtail coal burning
    at the facility from May 30, 1975 until November 1,
    1975 or such date
    as the electrostatic precipitators may be placed in operation.
    The
    electrostatic precipitator program is on schedule, but Petitioner
    states that the schedule is already so tight that it cannot be signifi-
    cantly accelerated.
    The second phase of Deere~scompliance program was officially
    enatiated on May 16,
    1973.
    In view of the many commendable aspects
    of this program, the Board feels that the program should be here
    repeated as an example and informative aid to other companies experiencing
    similar fuel allocation problems.
    The first program called for:
    1.
    A conscientious attitude on the part of Deere employees
    arising at least in part from a Company presentation
    showing the need for fuel conservation.
    2.
    Reduced preheat of forge furnaces 1/2 hour, saving
    61.4 x 106 BTU/day.
    3.
    All unnecessary machines and lights are turned off.
    Discovery of failure to do this results in notification
    to the department supervisors.
    11—329

    —4—
    4.
    All light switches have been identified and labelled
    to facilitate more selective use of lighting.
    5.
    The power house efficiency has improved as it
    approaches its design capacity.
    Having realized a
    6.5
    reduction in fuel usage from the above
    program,
    Deere embarked on additional fuel saving measures for fiscal
    year
    1974 that are designed to reduce fuel usage by an additional
    5.5.
    These additional measures are:
    Action
    Status
    1.
    Lower factory building temperatures
    from 70°to 65°F.
    50
    complete
    2.
    Reduce office temperatures
    to 68°F.
    100
    complete
    3.
    Shut down heat and vent unit in the
    work—in-process
    area of Building V.
    100
    complete
    4.
    Install automatic controls on Dept.
    902 paint conveyors so that wash
    system pumps and burners will
    automatically shut down when there
    are no parts going through the system. Investigation Started
    5.
    Develop alternate methods of heating
    forging billets and eliminating
    various hot processes.
    Investigation Started
    6.
    Continue employees awarer4ess program,
    including posters and letters to
    employees describing energy situation
    and methods for conservation at home
    and on the job.
    Continuing Process
    7.
    Recycle weld fume exhausts
    in Bldg.
    R-9 through approved air cleaning
    devices reducing heated makeup air
    requirements by
    16 February 1974.
    Contract Let
    8.
    Install 1-1/2”
    of urethane insulation
    on walls of Bldg.
    V and V-2 by
    22 December 1973.
    Material Delivered
    Because of these measures, Deere is hopeful that there will ha no
    need
    to use the coal burning variance even if grailted.
    Deere
    al:;o
    states that it does not plan to burn any coal unless absolutely

    —5—
    necessary nor does it plan to burn any more coal than necessary
    to sustain minimum working conditions.
    The Agency commended Deere’s fuel savings program and recommended
    the variance be granted subject to certain conditions.
    The Board
    joins the Agency in commending Deere for its comprehensive fuel
    savings program.
    The corporate attitude thus shown convinces this
    Board that Deere is sincere in its commitment to minimize any coal
    burning in boilers
    #7 or
    #8.
    Deere is committed to installing
    electrostatic precipitators on the coal burning boilers on
    a time
    schedule that is acceptable to the Agency.
    The fuel savings
    program represents an excellent example of what can be accomplished
    through corporate foresight and determination.
    We believe Deere
    has satisfied the prerequisite for a variance and we shall grant
    the variance requested subject to certain conditions.
    Finally, the Agency recommends
    that the Board require
    a stack
    test to insure compliance with Rule
    203(g).
    However, very high
    collection efficiencies are ordinarily achieved with electrostatic
    precipitators,
    and
    we
    have
    not
    been
    presented
    any
    information
    showing
    that
    Petitioner’s
    program
    might
    fail
    to
    provide
    the
    degree
    of control r~quiredto meet the emission limitations.
    The electro-
    static precipitators will not be operational during the one year
    term
    of
    this
    variance.
    If
    Deere
    petitions
    for
    an
    extension
    of
    this
    variance, or if the Agency can reasonably question the efficiency
    of Deere’s control program, then we would like
    to hear arguments
    as to whether such testing should be required.
    However, we shall
    not
    at
    this
    time
    require
    a
    stack
    test.
    ORDER
    It is the Order of the Bo3rd that Deere
    &
    Company be granted
    a
    variance from Rule 3-3.112 of
    the Rules and Regulations Governing
    the Control of Air Pollution for
    its East Moline Works until
    February 14,
    1975 for the purpose of burning coal
    in boiler #7
    or *8
    in the event that oil and gas are unavailable in sufficient quantities
    to meet the plant demand in excess of the capacity of boiler #9.
    This
    variance is subject to the following conditions:
    1.
    Petitioner shall utilize boiler
    #9 on coal and
    available gas prior to operating boiler
    *7 or
    *8.
    Petitioner shall make quarterly reports of all
    operations involving boiler #7 or #8, demands
    required during the operations of boiler *7 or
    *8,
    and available gas during the period of operation.
    These
    reports
    Shall
    be
    submitted
    to:
    The
    Illinois
    Environmental
    Protn~nn
    Aqency,
    Divi~Hon
    of
    Aix
    Pollution
    Control,
    Reqion
    1
    Office,
    4332
    North
    Main
    Street,
    Rockford,
    Illinois
    61103.
    11
    —331

    —6—
    2.
    Petitioner
    shall
    include
    in
    its
    quarterly
    report,
    progress
    made
    toward
    completing
    its
    anticipated
    reduction of energy demand.
    3.
    Petitioner
    shall
    apply
    for
    all necessary construction
    and operating permits
    for the electrostatic pre-
    cipitator control units
    for boilers
    #7,
    #8, and #9.
    4.
    Petitioner
    shall,
    by March 29,
    1974 post
    a bond
    in
    theamount
    of
    $100,000
    in
    ~
    form
    acceptable
    to
    the
    Environmental
    Protection Agency,
    such bond
    to ~e
    forfeited
    in the event Petitioner fails to install
    the pollution control
    on boilers
    #7,
    #8
    and
    #9 as
    specified
    in
    its Compliance Plan
    or any amendments
    thereto.
    Bond
    shall
    be mailed to:
    Fiscal
    Services
    Division,
    Illinois
    EPA,
    2200 Churchill
    Road,
    Springfield,
    Illinois
    62706.
    I,
    Christan L.
    Moffett, Clerk
    of
    the Illinois
    Pollution Control
    Board, hereby certify the
    above Opinion and Order was adopted this
    ~f~~day
    of
    ~
    1974 by
    a vote of ___too
    ii
    332

    Back to top