ILLINOIS POLLUTION CONTROL BOARD
    June 20, 1974
    AMOCO
    CHEMICALS
    CORP.
    PETITIONER
    )
    PCB 74-121
    v.
    )
    PCB 74—122
    )
    PCB 74—123
    )
    ENVIRONMENTAL
    PROTECTION
    AGENCY
    )
    RESPONDENT
    OPINION
    AND
    ORDER
    OF
    THE
    BOARD
    (by
    Mr.
    Marder)
    These
    cases
    come
    to
    the-
    Board
    on
    Petition
    of
    Amoco
    Chemicals
    Corp.,
    filed
    April
    21,
    1974.
    PCB
    74—121
    requests
    a
    variance
    from
    Rule
    204
    (f)
    for
    operation
    of Petitioner’s multi-purpose additives plant at Amoco Oil’s Wood
    River
    Refinery,
    until
    February
    28,
    1975.
    PCB
    74-122
    requests
    variance
    from
    Rule
    205
    (g)
    for
    operation
    of
    Petitioner’s detergent additives plant,
    at Amoco Oil’s Wood River
    Refinery, until February 21, 1975.
    PCB 74-123 requests variance from Rule 205
    (g) for operation of
    Petitioner’s multi—purpose additive plant,
    at Amoco Oil’s Wood Riv—
    er Refinery until March
    31,
    1975.
    These Petitions are related to variances granted in PCB 73-399,
    73-400,
    73-401.
    In these matters the Board granted variances for
    the
    units
    until
    June
    30, 1974.
    The reader is urged to refer to our earlier opinion on these mat-
    ters as to the units’ operations and the control methodology being
    installed
    (PCB 73—397
    401,
    December 20, 1973,
    Vol.
    10, Pg.
    439,
    of the Board’s published opinions).
    No hearing was held.
    PCB 74—121: The Agency in its recommendation suggests that this
    variance only be granted until January
    21,
    1975.
    Petitioner states as its reason for variance extension that key
    equipment will not~bedelivered on time,
    in order to comply with
    our earlier Order.
    Petitioner further alleges that other than the
    proposed control system,
    the only other way to comply
    is to shut down
    the unit.
    12
    595

    —2—
    Petitioner has submitted documents showing an effort to expeditious-
    ly complete its control system (Exhibits A,B, and C attached to Petition)
    The Board finds that Petitioner is diligently pursuing its control pro-
    gram.
    Petitioner alleges, and submits supporting documents,
    that at monhior
    ing stations surrounding the Wood River Refinery the Federal Primary ~nd
    Secondary Ambient Air Quality Criteria are being met for sulphur dioxide
    while this unit is operating.
    Therefore, Petitioner alleges that
    there
    will be no adverse environmental impact on the ambient air quality
    in
    the area
    (Petition Pp.
    2-3, Exhibit D attached).
    The Agency concurs
    that Petitioner’s program will aid in attainment of the Federal Mnbient
    Air Quality Standards
    (Agency Rec.
    P.
    4).
    The Agency further states that it has received no comments from the
    public regarding this variance (Agency Rec.
    p.
    4)
    The Agency believes that
    as Petitioner’s past compliance has been
    timely and cooperative that Petitioner’s action in seeking this variance
    extension is
    in good faith
    (Agency Rec.
    P.
    3).
    The Agency only objects
    to the sketchy timetable for completion, and
    therefore recommends that variance be granted only until January
    31,
    1975.
    The Board feels that since we are talking about a month~sdelay
    only,
    that
    the Board will grant the variance for the full time requested,
    subject
    to
    the
    condition
    that
    monthly
    reports
    be filed with the Agency,
    and that Petitioner shall complete its project in the shortest possible
    time.
    PCB
    74-122:
    The Agency recommends
    that this variance be granted only
    until December 31,
    1974.
    Petitioner is requesting an extension of a variance granted by the
    Board in PCB 73-400 from Rule 205
    (g)
    for operation of its detergent
    additives plant until February 21,
    1975.
    Petitioner states as reason for its variance extension request that
    after testing and research,
    it was not able to eliminate a step in their
    processing which was hoped would eliminate the emission problem.
    Elim-
    ination of the process step caused a product that did not prove adequate
    when tested in two series of tests, ending in the fall of 1973 and Feb.
    21, 1974
    (Pet.
    P.
    2)
    Since Amoco must now return their filtration step in the process, it
    feels that 12 months
    are necessary in order to bring the unit into
    corn—
    pliance
    (Pet.
    p.
    3).
    This work will entail modifications in the com-
    pletely enclosed pressure system (Agency Rec.
    P.
    2).
    Petitioner alleges, and has provided supporting documents
    (Exhibit
    A attached to Petition)
    referring to a study
    done in December 1972 and
    January 1973, that Petitioner’s hydrocarbon emissions did not cause am
    blent concentrations likely to produce damage to vegetation, humans, c
    animals.
    (Pet.
    P.
    3)
    Amoco also alleges that changes over the year
    since the test was conducted would show significant reductions In
    emi~
    ions ly Petitioner,
    and, in fact,
    others in the area
    (Pet.
    P.
    3).

    —3—
    Amoco has assumed that if total ambient hydrocarbon levels were due
    to Amoco, the unit in question would still only amount to 0.009 ppm
    (Pet.
    P.
    4).
    The Agency states that based on information supplied by the Petition-
    er, non-methane hydrocarbons were 2.02 ppm during a test period a year
    ago.
    The allowable ambient air standard is
    .24 ppm hydrocarbons.
    The
    Agency also mentions Petitioner’s
    allegation that hydrocarbon emissions
    have been reduced by 2/3 since the tests were conducted
    (Agency Rec.
    P.
    3).
    The Agency is of the opinion that the proposed control system will
    bring Petitioner’s unit into compliance with Rule 205
    (g)
    (Agency Rec.
    p.
    3).
    The Agency also feels that Petitioner
    is exercising good faith and
    diligence in seeking the variance extension (Agency Rec.
    P.
    3).
    The Agency only objects to the length of time requested by Petition-
    er for the variance.
    The Agency feels the variance should only be ex-
    tended until December 31, 1974, because of Petitioner’s
    failure to
    allege a proper time schedule for project completion.
    Also,
    the Agency
    feels that Petitioner’s emissions are so much above the standard that
    the unit should be brought into compliance as soon as possible.
    The
    Board
    will
    grant
    Amoco
    the
    variance
    for
    the
    time
    requested,
    subject
    to
    its
    filing
    a
    project
    completion
    schedule
    with
    the
    Board
    and
    the
    Agency
    within 21 days of the issuance of this Order.
    PCB 74-123: The Agency tecommends that this variance be granted un-
    til December 31, 1974.
    Petitioner states as its reason for extensionof its previously
    granted variance that late equipment delivery precludes
    completion of
    the control project before the expiration of the previously granted
    variance.
    Amoco
    has
    experienced
    difficulty
    in
    preparation
    of
    a
    cost
    estimate.
    There was also a two—month delay in an appropriation approval from the
    company
    headquarters.
    Amoco has also experienced numerous delays
    in receiving approval
    drawings
    from
    its
    supplier.
    An
    order
    was
    placed
    on
    December
    7,
    1973.
    Approval
    drawings
    were
    to
    be
    received by Petitioner six weeks
    after
    placing the order, but to the date of the Petition they had not been
    received.
    Amoco alleged that certain of the equipment would be delivered in
    early
    May,
    1974.
    If
    this equipment is received and installed,
    over
    one—half of the emissions will be eliminated by June
    30, 1974
    (Pet.
    P.
    2)
    Petitioner alleges that emissions from the entire refinery are not
    dangerous
    to
    vegetation,
    humans,
    or
    animals.
    Hourly
    concentrations
    12—59~

    —4—
    in
    excess
    of
    0.08
    ppm
    could
    have
    been
    expected
    only
    twice
    a
    year
    stead of only once as permitted by the national primary and ambient
    air quality standards.
    (Pet.
    P.
    3)
    Assuming Petitioner is responsible
    for
    ambient
    hydrocarbons,
    taking this unit as a
    3.4
    contributor
    total refinery, this unit’s contribution can be estimated at .069
    ambient concentration
    (Pet.
    P.
    3, Exhibit A attached to Petition),
    The
    Agency
    in
    its
    recommendation
    states
    that
    there
    are
    numerous
    other
    sources
    in
    the
    area.
    While the allowable ambient
    air
    standard
    is
    0.24,
    testing
    last
    year
    by Petitioner showed the average non-methane
    hydrocarbon
    level
    at
    2.02
    ppm
    (Agency
    Rec.
    p.
    3).
    The
    Agency
    is
    of
    the
    opinion
    that
    this
    control
    program
    will
    about
    compliance
    with
    Rule
    205
    (g).
    The
    Agency
    also
    states its belief that Petitioner is
    exercising
    good faith in its request for this variance (Agency Rec.
    P.
    3).
    The Agency’s sole objection to the requested variance is to
    length.
    The Agency
    believes
    that
    Petitioner
    should
    be
    able
    to
    work on
    the
    control system by December 31, 1974 (Agency Rec.
    P.
    whereas Petitioner is requesting additional time to allow for
    ment delivery slippage
    (Pet. P~
    ~).
    The
    Board finds that Amoco shall be granted a variance from
    205
    (g) for the full time requested,
    subject
    to
    the
    condition
    equipment
    is
    received,
    it
    shall
    be
    installed
    as
    soon
    as
    possible
    placed
    in
    operation.
    Hardship
    for
    granting
    these
    variances
    was
    adequately
    proved
    earlier
    cases,
    but
    as
    a
    brief
    resume,
    the
    ~oard
    found
    that
    should
    these
    variances
    not
    be
    granted,
    the
    only
    method
    of
    controlling
    emissions
    from
    these
    units
    is
    by
    shut.ting
    them
    down.
    Such
    shutdown
    would
    then
    necessitate
    closing
    the
    entire
    refinezy,
    thereby
    causing
    lack
    ot
    110,000
    barrels
    of
    oil
    being
    refined.
    This
    would
    cause
    stantial loss
    to the Petitioner and to the public.
    This Opinion constitutes the
    findings
    of
    fact
    and
    conclusions
    law
    of
    the
    Board.
    ORDER
    IT
    IS
    THE
    ORDER of the Pollution Control Board that:
    1)
    Petitioner
    is granted
    a variance
    from
    Rule
    204
    (f)
    of
    the
    Board’s Rules and Aegulations
    for
    its
    multi-purpose
    additiv
    plant until Februari
    2B,
    1075,
    or to the
    date
    when
    the
    posed control equipment
    Is installed, whichever is shorter.
    2)
    Petitioner
    is granted
    a variance from Rule 205
    (g)
    of the
    Board’s
    Rules an~r~eguiaticnsfor its detergent additives
    plant, until February ~
    1~75 or
    to
    the
    date,
    when
    the

    —5—
    proposed control system is completed, whichever is shorter,
    subject to the condition that Petitioner submit within 21
    days of the issuance of this Order a project completion
    schedule as to its compliance program.
    3)
    Petitioner
    is granted variance from Rule 205
    (g)
    for oper-
    ation of its multi-purpose additives plant until March
    31,
    1975, or to the date when the proposed control equipment
    is installed, whichever is shorter, subject to the condition
    that
    as such control equipment is received,
    it shall be put
    into service as
    soon as possible.
    Orders 1,
    2, and
    3 above are conditioned by the following:
    A)
    Petitioner shall apply for all necessary construction and
    operating permits from the Agency.
    B)
    Petitioner shall supply monthly progress reports to the
    Agency on the control equipment projects for the three
    units and a final report upon completion of each project.
    C)
    Petitioner shall keep in effect the bond ordered in the
    previous opinion of the Board for $50,000
    to guarantee
    installation of air pollution control equipment as ord-
    ered above.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board,
    certify that the above Opinion and Order was adopted by the
    Board on the 20th day of
    June,
    1974,
    by a vote of
    5 to
    0,
    12
    599

    Back to top