ILLINOIS POLLUTION CONTROL BOARD
June 20, 1974
AMOCO
OIL CO.
PETITIONER
)
v.
)
PCB 74—120
ENVIRONMENTAL PROTECTION AGENCY
)
RESPONDENT
ORDER OF THE BOARD
(by Mr. Marder)
This case comes to the Board on Petition of Amoco Oil Co. for
extension of a variance granted by the Board in PCB 73-398 (opin-
ion issued December 20, 1973),
filed April
1,
1974, from Rule
205
(g)
of Chapter
2 of the Board~sRules and Regulations,
until Dec-
ember
31,
1974.
The Agency filed its recommendation in this matter June
10, 1974,
suggesting this extension be granted only until October 31,
1974.
No hearing was held.
This case stems from a variance granted by the Board in PCB 73-
398.
For a detailed discussion on the proáess and control program
therein considered,
the reader is advised to refer to our December
20, 1973,
decision.
Petitioner
is requesting variance from Rule 205
(g) of Chapter 2
of the Board’s Rules and Regulations
for its catalytic reforming
unit.
Emissions from this unit are hydrocarbons, and are to be controlled
by
the use of
a smokeless flare.
Amoco
is requesting this extension because of alleged equipment
delivery delays.
Amoco alleges that if this variance is not granted,
the only other method of control available would be to shut down the
unit.
At the time of the Petitioner~sfiling Amoco expected to receive
the flare equipment in mid-April,
1974.
At the earliest, this would
bring construction to completion in late July,
1974.
Amoco does not
believe this time frame is adequate, and so
is asking the variance
be
granted until December 31, 1974
(Pet.
Pg.
2)
in
order to avoid
repeat-
ed
variance petitions.
12
--
591
—2—
Amoco alleges that in November 1973 it reduced,continuous hydrocar-
bon emissions from its blowdown stack from 105 lbs/hr to 17.5 lbs/hr
(Pet.
Pg. 2).
Amoco has submitted
(Exhibit A attached to Petition)
a survey of
hydrocarbon emissions from its Wood River Refinery taken during Dec-
ember l9~’and January 1973.
Amoco alleges that the analysis showed
at that ti.
hat the emissions from the refinery had minimal impact
(Pet.
P.
3).
Since the time of the survey Amoco alleges it has reduced emissions
from the unit in question by about 88 lbs/hr
(Pet.
P.
3).
The Agency states that non—methane hydrocarbon concentrations
in
the area of the refinery were 2.02 ppm during the test period last
year, while the primary ambient air quality standard is
0.24 ppm (Agen-
cy Rec.
P.
4)
.
There are numerous other sources of hydrocarbon emiss-
ions
in the area
(Agency Rec.
P.
4).
The Agency objects to the length of the requested variance.
They
state that Petitioner’s supplier indicates construction of the proposed
equipment can be completed by September 1, 1974
(Agency Rec.
P.
4).
The Board finds that because of the already extensive slippage in
the schedule of compliance to date,
that it is reasonable to allow
Amoco the extra two months requested to complete their compliance pro-
gram, subject to the condition that they install equipment as received
and put it into operation as soon as possible.
Hardship in this matter was determined in the previous opinion
(PCB 73-398), but as
a general review, the Board found that failure to
grant the variance would necessitate shutting down the unit,
and that
this would cause
a loss of
8000 to 9000 ~barre1s of reformate per day.
The Board finds that Amoco Oil Co. has met its burden of proof for
a variance under Sec.
35 of the Environmental Protection Act.
This Opinion constitutes the findings of fact and conclusions of
law of the Board.
ORDER
IT
IS THE ORDER of the Pollution Control Board that Petitioner,
Amoco Oil Co.,
is granted variance from Rule 205
(g)
of Chapter 2
of the Board’s Rules and Regulations in order to operate its catalytic
reforming unit located at its Wood River, Illinois, Refinery, until
December 31,
1974,
or upon completion of the installation of the poll-
ution control equipment, whichever period of time is shorter, subject
to the following conditions:
1.
As Petitioner receives equipment,
it shall be installed
and put into operation as soon as possible.
12
—
592
—3—
2.
Petitioner shall send to the Agency at the address
below monthly progress reports as to the completion
of the project.
Environmental Protection Agency
2200 Churchill Road
Springfield,
Illinois 62706
3.
Petitioner shall notify the Agency when all equipment
is installed.
4.
Petitioner shall apply for all construction and opera-
ting permits required.
5.
Petitioner shall maintain in effect the performance
bond as ordered in PCB 73-397
—
401 to guarantee in-
stallation of equipment as ordered.
I, Christan L. Moffett,
Clerk of the Illinois Pollution Control
Board, certify that the above Opinion and Order was adopted by the
Board
on
the~~*\
day of
~
1974, by a vote of
____
to
__
ii
12
—
593